There are currently no known outstanding effects for the The Town and Country Planning (Miscellaneous Temporary Modifications) (Coronavirus) (Scotland) Regulations 2021.
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
Scottish Statutory Instruments
Town And Country Planning
Made
27th August 2021
Laid before the Scottish Parliament
31st August 2021
Coming into force
29th September 2021
The Scottish Ministers make the following Regulations in exercise of the powers conferred on them by sections 32, 35A, 35B, 35C, 43A(10) and (11), 58(3D), 59(8D) and 275 of the Town and Country Planning (Scotland) Act 1997(1), section 16(7) of the Planning (Listed Buildings and Conservation Areas) (Scotland) Act 1997(2), section 12(9) of the Coronavirus (Scotland) Act 2020(3), section 9(9) of the Coronavirus (Scotland) (No. 2) Act 2020(4) and all other powers enabling them to do so.
1.—(1) These Regulations may be cited as the Town and Country Planning (Miscellaneous Temporary Modifications) (Coronavirus) (Scotland) Regulations 2021 and come into force on 29 September 2021.
(2) In these Regulations—
“the Act” means the Town and Country Planning (Scotland) Act 1997, and
“the Listed Buildings Act” means the Planning (Listed Buildings and Conservation Areas) (Scotland) Act 1997.
2.—(1) In the definition of “emergency period” in section 58(3C) (duration of planning permission) of the Act, for “on 30 September 2021” substitute “at the end of 31 March 2022”.
(2) In the definition of “emergency period” in section 59(8C) (planning permission in principle) of the Act, for “on 30 September 2021” substitute “at the end of 31 March 2022”.
(3) In the definition of “emergency period” in section 16(6) (duration of listed building consent) of the Listed Buildings Act, for “on 30 September 2021” substitute “at the end of 31 March 2022”.
3.—(1) In the definition of “extended period” in section 58(3C) of the Act for “on 31 March 2022” substitute “at the end of 30 September 2022”.
(2) In the definition of “extended period” in section 59(8C) of the Act for “on 31 March 2022” substitute “at the end of 30 September 2022”.
(3) In the definition of “extended period” in section 16(6) of the Listed Buildings Act for “on 31 March 2022” substitute “at the end of 30 September 2022”.
F14. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Textual Amendments
F25. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Textual Amendments
6.—(1) The provisions specified in paragraph (2) are revoked.
(2) The provisions are—
(a)regulations 4 and 5 of the Town and Country Planning (Emergency Period and Extended Period) (Coronavirus) (Scotland) Regulations 2021(5), and
(b)the Town and Country Planning (Emergency Period and Extended Period) (Coronavirus) (Scotland) Amendment Regulations 2021(6).
7.—(1) The Town and Country Planning (Development Management Procedure) (Scotland) Regulations 2013(7) are amended in accordance with paragraphs (2) and (3).
(2) In regulation 7 (pre-application consultation) for paragraph (2)(b)(ii) substitute—
“(ii)details as to how (including by what electronic means) further information may be obtained concerning the proposed development,”.
(3) In regulation 7A (temporary relaxation of pre-application consultation requirements during coronavirus emergency period)—
(a)omit paragraph (2)(b) and “and” immediately preceding that paragraph, and
(b)in paragraph (3) for “on the date on which Part 1 of the Coronavirus (Scotland) Act 2020 expires in accordance with section 12 of that Act” substitute “at the end of 31 March 2022”.
8.—(1) The Town and Country Planning (Pre-Application Consultation) (Scotland) Amendment Regulations 2021(8) are amended in accordance with paragraphs (2) and (3).
(2) In regulation 1(1) (citation, commencement and interpretation) for “1 October 2021” substitute “1 April 2022”.
(3) In regulation 10 (transitional and savings provisions)—
(a)for “1 October 2021” substitute “1 April 2022”, and
(b)in paragraph (b) for “8” substitute “7”.
9.—(1) The Town and Country Planning (Schemes of Delegation and Local Review Procedure) (Scotland) Regulations 2013(9) are amended in accordance with paragraph (2).
(2) In regulation 7A(2) (temporary removal of requirement to hold meeting of local review body in public during Coronavirus emergency period) for “on the date on which Part 1 of the Coronavirus (Scotland) Act 2020 expires in accordance with section 12 of that Act” substitute “at the end of 30 September 2021”.
TOM ARTHUR
Authorised to sign by the Scottish Ministers
St Andrew’s House,
Edinburgh
(This note is not part of the Regulations)
These Regulations make amendments to the definitions of “emergency period” and “extended period” in sections 58(3C) and 59(8C) of the Town and Country Planning (Scotland) Act 1997 (“the Act”), as it has effect by virtue of paragraphs 8 to 10 of schedule 7 of the Coronavirus (Scotland) Act 2020, and in section 16(6) of the Planning (Listed Buildings and Conservation Areas) (Scotland) Act 1997 (“the Listed Buildings Act”). These Regulations also make amendments to the Town and Country Planning (Development Management Procedure) (Scotland) Regulations 2013, the Town and Country Planning (Schemes of Delegation and Local Review Procedure) (Scotland) Regulations 2013 and the Town and Country Planning (Pre-Application Consultation) (Scotland) Amendment Regulations 2021.
Regulations 2 and 3 amend the definitions of “emergency period” and “extended period” in sections 58(3C) and 59(8C) of the Act and in section 16(6) of the Listed Buildings Act
As currently defined by sections 58(3C) and 59(8C) of the Act, as amended by S.S.I. 2020/254 and S.S.I. 2021/100, the “emergency period” began on 7 April 2020 and would end on 30 September 2021 and the “extended period” began on 7 April 2020 and would end on 31 March 2022. As amended by these Regulations the “emergency period” is the period which began on 7 April 2020 and will end at the end of 31 March 2022 and the “extended period” is the period which began on 7 April 2020 and will end at the end of 30 September 2022.
As currently defined by section 16(6) of the Listed Buildings Act, as amended by S.S.I. 2020/254 and S.S.I. 2021/100, the “emergency period” began on 27 May 2020 and would end on 30 September 2021 and the “extended period” began on 27 May 2020 and would end on 31 March 2022. As amended by these Regulations the “emergency period” is the period which began on 27 May 2020 and will end at the end of 31 March 2022 and the “extended period” is the period which began on 27 May 2020 and will end at the end of 30 September 2022.
Regulation 4 makes saving provisions in respect of planning permissions granted before the expiry of the emergency period. The provisions of sections 58 and 59 of the Act, as they had effect immediately before the expiry of the emergency period continue to have effect, with modifications, in relation to the duration of planning permissions granted before the expiry of the emergency period. The modifications are that the powers to make regulations to further amend the definitions of “emergency period” and “extended period” will not continue to have effect after the expiry of the Coronavirus (Scotland) Act 2020 at the end of 31 March 2022.
Regulation 5 makes equivalent saving provisions in respect of listed building consents granted before the expiry of the emergency period. The provisions of section 16 of the Listed Buildings Act continue to have effect as immediately before the expiry of the Coronavirus (Scotland) Act (No. 2) 2020, with modifications in relation to the duration of listed building consent granted before the expiry of the emergency period. The powers to make regulations to further amend the definitions of “emergency period” and “extended period” will not continue to have effect after the expiry of the Coronavirus (Scotland) (No. 2) Act 2020 at the end of 31 March 2022.
The provisions of regulations 4 and 5 replace and supercede the saving provisions contained in regulations 4 and 5 of the Town and Country Planning (Emergency Period and Extended Period) (Coronavirus) (Scotland) Regulations 2021. Those provisions are therefore revoked by regulation 6 along with the Town and Country Planning (Emergency Period and Extended Period) (Coronavirus) (Scotland) Amendment Regulations 2021 which amended them.
Regulation 7 amends the Town and Country Planning (Development Management Procedure) (Scotland) Regulations 2013 to modify the information required to be included in notices published under regulation 7(2) of those Regulations and to align the dates of the emergency period with the changes made by regulation 2 of these Regulations.
Regulation 8 amends the date on which the Town and Country Planning (Pre-Application Consultation) (Scotland) Amendment Regulations 2021 come into force from 1 October 2021 to 1 April 2022 and makes consequential changes to the related transitional and savings provisions.
Regulation 9 amends the Town and Country Planning (Schemes of Delegation and Local Review Procedure) (Scotland) Regulations 2013 to remove, with effect from the end of 30 September 2021, the temporary suspension of the requirement to hold a meeting of a local review body in public.
1997 c. 8. The functions of the Secretary of State were transferred to the Scottish Ministers by virtue of section 53 of the Scotland Act 1998 (c. 46). Sections 58(3D) and 59(8D) have effect by virtue of paragraphs 8 to 10 of schedule 7 of the Coronavirus (Scotland) Act 2020 (asp 7). The definitions of “emergency period” and “extended period” in sections 58(3C) and 59(8C) were amended by S.S.I. 2020/254 and S.S.I. 2021/100.
1997 c. 9. Section 16(6) was inserted by, and section 16(7) has effect by virtue of, paragraph 2 of schedule 4 of the Coronavirus (Scotland) (No. 2) Act 2020 (asp 10). The definitions of “emergency period” and “extended period” in section 16(6) were amended by S.S.I. 2020/254 and S.S.I. 2021/100.
2020 asp 7 as amended by the Coronavirus (Extension and Expiry) (Scotland) Act 2021 (asp 19).
2020 asp 10 as amended by the Coronavirus (Extension and Expiry) (Scotland) Act 2021 (asp 19).
S.S.I. 2013/155 as relevantly amended by S.S.I. 2020/124.
S.S.I. 2013/157 as relevantly amended by S.S.I. 2020/124.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Policy Note sets out a brief statement of the purpose of a Scottish Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Scottish Statutory Instrument accessible to readers who are not legally qualified and accompany any Scottish Statutory Instrument or Draft Scottish Statutory Instrument laid before the Scottish Parliament from July 2012 onwards. Prior to this date these type of notes existed as ‘Executive Notes’ and accompanied Scottish Statutory Instruments from July 2005 until July 2012.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including:
The data on this page is available in the alternative data formats listed: