Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.
(1)The acquiring authority may execute in respect of any of the land which they are authorised to acquire by the compulsory purchase order a declaration in the prescribed form vesting the land in themselves from the end of such period as may be specified in the declaration (not being less than [F13 months] from the date on which the service of notices required by section 6 below is completed).
[F2(1A)But an acquiring authority may not execute a declaration in respect of land if they have served a notice to treat in respect of that land and have not withdrawn it.
(1B)In subsection (1A) the reference to an authority having “served” a notice does not include cases in which the authority is deemed to have served a notice.]
(2)For the purposes of this Act a certificate by the acquiring authority that the service of notices required by section 6 below was completed on a date specified in the certificate shall be conclusive evidence of the fact so stated.
[F3(3)For the purposes of this Act the “vesting date” in relation to any land that is actually specified in a general vesting declaration is—
(a)the first day after the end of the period specified in the declaration in accordance with subsection (1) above, or
(b)if a counter-notice is served under paragraph 2 of Schedule A1 within that period in relation to land, the day determined as the vesting date for the land in accordance with that Schedule.
(4)For the purposes of this Act, the “vesting date” for any land that is deemed to have been specified in a general vesting declaration by Schedule A1 is the day determined as the vesting date for the land in accordance with that Schedule.]
Textual Amendments
F1Words in s. 4(1) substituted (3.2.2017) by Housing and Planning Act 2016 (c. 22), ss. 184, 216(3); S.I. 2017/75, reg. 3(d) (with reg. 5)
F2S. 4(1A)(1B) inserted (3.2.2017) by Housing and Planning Act 2016 (c. 22), ss. 185, 216(3); S.I. 2017/75, reg. 3(d) (with reg. 5)
F3S. 4(3)(4) substituted for s. 4(3) (3.2.2017) by Housing and Planning Act 2016 (c. 22), s. 216(3), Sch. 18 para. 2; S.I. 2017/75, reg. 3(k) (with reg. 5)
Modifications etc. (not altering text)
C1S. 4 excluded (2.10.2014) by The Clocaenog Forest Wind Farm Order 2014 (S.I. 2014/2441), arts. 1, 21(b) (with art. 33)
C2S. 4 excluded (26.2.2015) by The Cornwall Council (A30 Temple to Higher Carblake Improvement) Order 2015 (S.I. 2015/147), arts. 1, 20(1)
C3S. 4 restricted (1.4.2015) by The Knottingley Power Plant Order 2015 (S.I. 2015/680), arts. 1, 20(1)(b) (with Sch. 8 para. 10)
C4S. 4 excluded (21.4.2015) by The Crossrail (Plumstead Sidings) Order 2015 (S.I. 2015/781), arts. 1, 16(b)
C5S. 4 excluded (30.6.2015) by The Swansea Bay Tidal Generating Station Order 2015 (S.I. 2015/1386), arts. 1, 27(1)(b) (with arts. 51, 53)
C6S. 4 excluded (7.8.2015) by The Preesall Underground Gas Storage Facility Order 2015 (S.I. 2015/1561), arts. 1, 31(1)(b) (with art. 44)
C7S. 4 excluded (14.8.2015) by The Hirwaun Generating Station Order 2015 (S.I. 2015/1574), arts. 1, 19(1)(b) (with art. 30)
C8S. 4 excluded (14.8.2015) by The Progress Power (Gas Fired Power Station) Order 2015 (S.I. 2015/1570), arts. 1, 20(1)(b)
C9S. 4 excluded (30.9.2015) by The Network Rail (Blackthorn and Piddington) (Land Acquisition) Order 2015 (S.I. 2015/1684), arts. 1, 12(1)(b)
C10S. 4 excluded (30.12.2015) by The Port Talbot Steelworks Generating Station Order 2015 (S.I. 2015/1984), arts. 1, 15(b) (with art. 26)
C11S. 4 excluded (3.4.2019) by The Millbrook Gas Fired Generating Station Order 2019 (S.I. 2019/578), arts. 1, 20(1)(b)
C12S. 4 excluded (16.4.2020) by The Reinforcement to the North Shropshire Electricity Distribution Network Order 2020 (S.I. 2020/325), arts. 3, 20(1)(b) (with arts. 7, 20(2))
C13S. 4 excluded (21.5.2020) by The Lake Lothing (Lowestoft) Third Crossing Order 2020 (S.I. 2020/474), arts. 1, 25(1)(b) (with arts. 51, 57)
C14S. 4 excluded (11.6.2020) by The M42 Junction 6 Development Consent Order 2020 (S.I. 2020/528), arts. 1, 26(b) (with art. 37)
C15S. 4 excluded (18.6.2020) by The A63 (Castle Street Improvement, Hull) Development Consent Order 2020 (S.I. 2020/556), arts. 1, 22(1)(b) (with arts. 5, 44)
C16S. 4 restricted (30.6.2022) by The Network Rail (Essex and Others Level Crossing Reduction) Order 2022 (S.I. 2022/651), arts. 1, 27(1)(b) (with art. 27(2))
C17S. 4 excluded (13.7.2022) by The A47 Blofield to North Burlingham Development Consent Order 2022 (S.I. 2022/738), arts. 1, 26(1)(b) (with arts. 4, 50)
C18S. 4 restricted (2.8.2022) by The Network Rail (Oxford Station Phase 2 Improvements (Land Only)) (No. 2) Order 2022 (S.I. 2022/872), arts. 1(1), 13(1)(b)
C19S. 4 restricted (2.8.2022) by The Network Rail (Oxford Station Phase 2 Improvements (Land Only)) Order 2022 (S.I. 2022/871), arts. 1(1), 13(1)(b)
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: