Print Options
PrintThe Whole
Act
PrintThe Whole
Part
PrintThe Whole
Cross Heading
PrintThis
Section
only
Status:
Point in time view as at 20/01/1997. This version of this provision has been superseded.

Status
You are viewing this legislation item as it stood at a particular point in time. A later version of this or provision, including subsequent changes and effects, supersedes this version.
Note the term provision is used to describe a definable element in a piece of legislation that has legislative effect – such as a Part, Chapter or section.
Changes to legislation:
Housing Act 1985, Section 193 is up to date with all changes known to be in force on or before 09 March 2025. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations.

Changes to Legislation
Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.
193 Power of local housing authority to execute works.E+W
(1)If a repair notice is not complied with the local housing authority may themselves do the work required to be done by the notice.
[(2)For the purpose of this Part compliance with the notice means beginning and completing the works specified in the notice,—
(a)if no appeal is brought against the notice, not later than such date and within such period as is specified in the notice;
(b)if an appeal is brought against the notice and is not withdrawn, not later than such date and within such period as may be fixed by the court determining the appeal; and
(c)if an appeal brought against the notice is withdrawn, not later than the twenty-first day after the date on which the notice becomes operative and within such period (beginning on that twenty-first day) as is specified in the notice.
(2A)If, before the expiry of the period which under subsection (2) is appropriate for completion of the works specified in the notice, it appears to the local housing authority that reasonable progress is not being made towards compliance with the notice, the authority may themselves do the work required to be done by the notice.]
(3)The provisions of Schedule 10 apply with respect to the recovery by the local housing authority of expenses incurred by them under this section.
[(4)If, after the local housing authority have given notice under section 194 of their intention to enter and do any works, the works are in fact carried out by the person having control of the dwelling-house [house in multiple occupation] or part of the building in question, any administrative and other expenses incurred by the authority with a view to doing the works themselves shall be treated for the purposes of Schedule 10 as expenses incurred by them under this section in carrying out works [in a case where the repair notice has not been complied with].]