- Latest available (Revised)
- Point in Time (01/02/1991)
- Original (As enacted)
Version Superseded: 19/11/2003
Point in time view as at 01/02/1991. This version of this provision has been superseded.
You are viewing this legislation item as it stood at a particular point in time. A later version of this or provision, including subsequent changes and effects, supersedes this version.
Note the term provision is used to describe a definable element in a piece of legislation that has legislative effect – such as a Part, Chapter or section.
Electricity Act 1989, Section 36 is up to date with all changes known to be in force on or before 11 November 2024. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations.
Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.
(1)Subject to subsections (2) and (4) below, a generating station shall not be constructed, extended or operated except in accordance with a consent granted by the Secretary of State.
(2)Subsection (1) above shall not apply to a generating station whose capacity—
(a)does not exceed the permitted capacity, that is to say, 50 megawatts; and
(b)in the case of a generating station which is to be constructed or extended, will not exceed the permitted capacity when it is constructed or extended;
and an order under this subsection may make different provision for generating stations of different classes or descriptions.
(3)The Secretary of State may by order provide that subsection (2) above shall have effect as if for the permitted capacity mentioned in paragraph (a) there were substituted such other capacity as may be specified in the order.
(4)The Secretary of State may by order direct that subsection (1) above shall not apply to generating stations of a particular class or description, either generally or for such purposes as may be specified in the order.
(5)A consent under this section—
(a)may include such conditions (including conditions as to the ownership or operation of the station) as appear to the Secretary of State to be appropriate; and
(b)shall continue in force for such period as may be specified in or determined by or under the consent.
(6)Any person who without reasonable excuse contravenes the provisions of this section shall be liable on summary conviction to a fine not exceeding level 5 on the standard scale.
(7)No proceedings shall be instituted in England and Wales in respect of an offence under this section except by or on behalf of the Secretary of State.
(8)The provisions of Schedule 8 to this Act (which relate to consents under this section and section 37 below) shall have effect.
(9)In this Part “extension”, in relation to a generating station, includes the use by the person operating the station of any land (wherever situated) for a purpose directly related to the generation of electricity by that station and “extend” shall be construed accordingly.]
Textual Amendments
F1S. 32A inserted (1.10.2001) by 2000 c. 27, s. 63; S.I. 2001/3266, art. 2, Sch. (subject to transitional provisions in arts. 3-20)
Modifications etc. (not altering text)
C1S. 36 restricted by S.I. 1990/442, art. 3(1)(a)
C2S. 36 modified (S.) (27.5.1997) by 1997 c. 8, ss. 57(2), 278(2) (with ss. 64, 219)
S. 36 modified (S.) (27.5.1997) by 1997 c. 10, ss. 10(2), 31, 40(2) (with ss. 9(3), 10(5), 38(6))
C3S. 36: transfer of certain functions (S.) (1.7.1999) by S.I. 1999/1750, art. 2, Sch. 1 (with art. 7)
C4S. 36(2) modified (S.) by S.I. 1990/392, art. 2
C5S. 36(2) modified (E.W.) (1.12.2001) by S.I. 2001/3642, art. 2
C6S. 36(2) modified (S.) (26.9.2002) by The Electricity Act 1989 (Requirement of Consent for Offshore Generating Stations) (Scotland) Order 2002 (S.S.I. 2002/407), art. 3
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: