Search Legislation

Electricity Act 1989

 Help about what version

What Version

 Help about advanced features

Advanced Features

Status:

Point in time view as at 15/01/2015. This version of this provision has been superseded. Help about Status

Close

Status

You are viewing this legislation item as it stood at a particular point in time. A later version of this or provision, including subsequent changes and effects, supersedes this version.

Note the term provision is used to describe a definable element in a piece of legislation that has legislative effect – such as a Part, Chapter or section.

Changes to legislation:

Electricity Act 1989, Section 64 is up to date with all changes known to be in force on or before 13 November 2024. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations. Help about Changes to Legislation

Close

Changes to Legislation

Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.

64 Interpretation etc. of Part I.E+W+S

(1)In this Part, unless the context otherwise requires—

  • the 1973 Act” means the M1 Fair Trading Act 1973;

  • the 1980 Act” means the M2 Competition Act 1980;

  • [F1“the 2013 Amending Regulation” means Regulation 2013/347/EU of the European Parliament and of the Council of 17 April 2013 on guidelines for trans-European energy infrastructure and repealing Decision 2006/1364/EC and amending Regulations 2009/713/EC, 2009/714/EC and 2009/715/EC;]

  • F2. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

  • [F3“the Agency” means the Agency for the Cooperation of Energy Regulators established under the Agency Regulation;]

  • [F3“the Agency Regulation” means Regulation 2009/713/EC of the European Parliament and of the Council of 13 July 2009 establishing an Agency for the Cooperation of Energy Regulators;]

  • [F4authorised distributor” means a person who is authorised by a licence or exemption to distribute electricity;]

  • [F5authorised supplier” means a person who is authorised by a licence or exemption to supply electricity;]

  • " [F6the CMA "means the Competition and Markets Authority;]

  • [F7construct” and “construction”, in relation to so much of a generating station as comprises or is to comprise renewable energy installations, has the same meaning as in Chapter 2 of Part 2 of the Energy Act 2004;]

  • [F3“designated regulatory authority” means an authority designated in accordance with Article 35 of the Electricity Directive;]

  • [F3“designated regulatory authority for Great Britain” means the authority designated by virtue of section 3A of the Utilities Act 2000;]

  • [F4distribute” in relation to electricity, has the meaning given by section 4(4), and cognate expressions shall be construed accordingly;]

  • [F3“distribution exemption holder” means a person who—

    (a)

    is distributing electricity for the purpose mentioned in section 4(1)(bb); and

    (b)

    is authorised to do so by an exemption;]

  • electrical plant” means any plant equipment, apparatus or appliance used for, or for purposes connected with the generation, transmission[F8, distribution] or supply of electricity, other than—

    (a)

    an electric line;

    (b)

    a meter used for ascertaining the quantity of electricity supplied to any premises; or

    (c)

    an electrical appliance under the control of a consumer;

  • electric line” means any line which is used for carrying electricity for any purpose and includes, unless the context otherwise requires—

    (a)

    any support of any such line, that is to say, any structure, pole or other thing in, on, by or from which any such line is or may be supported, carried or suspended;

    (b)

    any apparatus connected to any such line for the purpose of carrying electricity; and

    (c)

    any wire, cable, tube, pipe or other similar thing (including its casing or coating) which surrounds or supports, or is surrounded or supported by, or is installed in close proximity to, or is supported, carried or suspended in association with, any such line;

  • [F3“the Electricity Directive” means Directive 2009/72/EC of the European Parliament and of the Council of 13 July 2009 concerning common rules for the internal market in electricity and repealing Directive 2003/54/EC;]

  • [F9electricity distributorF10... and “electricity supplier” have the meanings given by section 6(9);]

  • [F11electricity interconnector” has the meaning given by section 4(3E);]

  • [F3“the Electricity Regulation” means Regulation 2009/714/EC of the European Parliament and of the Council of 13 July 2009 on conditions for access to the network for cross-border exchanges in electricity and repealing Regulation 2003/1228/EC[F12, as amended by the 2013 Amending Regulation];]

  • [F3“electricity undertaking” has the meaning given by section 10O;]

  • [F3“exempt distribution system” means a distribution system operated or controlled by a distribution exemption holder who is covered by an exemption granted to it in relation to that system;]

  • exemption” means an exemption under section 5 above;

  • extension”, in relation to a generating station, has the meaning given by section 36(8) above and “extend” shall be construed accordingly;

  • final order” and “provisional order” have the meanings given by section 25(8) above;

  • [F13generate”, in relation to electricity, has the meaning given by section 4(4) above, and cognate expressions shall be construed accordingly;]

  • generating station”, in relation to a generating station wholly or mainly driven by water, includes all structures and works for holding or channelling water for a purpose directly related to the generation of electricity by that station;

  • [F14high voltage line” means an electric line which—

    (a)

    if it is in Scotland or is a relevant offshore line (as defined in subsection (1A)), is of a nominal voltage of 132 kilovolts or more; and

    (b)

    in any other case, is of a nominal voltage of more than 132 kilovolts,

    and “low voltage line” shall be construed accordingly;]

  • information” includes accounts, estimates and returns;

  • licence” means a licence under section 6 above and “licence holder” shall be construed accordingly;

  • [F15licensable activity” means an activity which, if carried on without the authority of a licence or exemption, constitutes an offence under section 4(1);]

  • line” means any wire, cable, tube, pipe or any other similar thing (including its casing or coating) which is designed or adapted for use in carrying electricity;

  • F16. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

  • notice” means notice in writing;

  • premises” includes any land, building or structure;

  • prescribed”, [F17means prescribed by regulations made, unless the context otherwise requires,] by the Secretary of State;

  • F18. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

  • F18. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

  • [F19providing a smart meter communication service” has the meaning given in section 4(3G) above, and cognate expressions shall be construed accordingly;]

  • [F3“regulated person” has the meaning given by section 25(8);]

  • relevant condition”and “relevant requirement” have the meanings given by section 25(8) above;

  • [F3“relevant producer or supplier” has the meaning given by section 10O;]

  • [F20renewable energy installation” and “Renewable Energy Zone” have the same meanings as in Chapter 2 of Part 2 of the Energy Act 2004;]

  • [F3“senior officer” means—

    (a)

    in relation to a company, a director;

    (b)

    in relation to a partnership, a partner;

    (c)

    in any other case, a person holding a position equivalent to that of a director or partner;]

  • [F21special connection agreement” means a special agreement under section 22;]

  • supply”, in relation to electricity, has the meaning given by section 4(4) above, and cognate expressions shall be construed accordingly;

  • [F3“supply exemption holder” means a person who—

    (a)

    is carrying on the activity mentioned in section 4(1)(c); and

    (b)

    is authorised to do so by an exemption;]

  • F18. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

  • [F22transmission”, in relation to electricity, has the meaning given by section 4(4) above;

  • transmission system” has the same meaning given by section 4(4) above;]

  • working day” means any day other than a Saturday, a Sunday, Christmas Day, Good Friday or a day which is a bank holiday within the meaning of the M3 Banking and Financial Dealings Act 1971.

[F23(1A)An electric line is a relevant offshore line for the purposes of the definition in subsection (1) of “high voltage line” if—

(a)it is wholly or partly in an area of GB internal waters, an area of the territorial sea adjacent to the United Kingdom or an area designated under section 1(7) of the Continental Shelf Act 1964, and

(b)it is—

(i)used to convey electricity to a place in Scotland, or

(ii)constructed wholly or mainly for the purpose of conveying, to any other place, electricity generated by a generating station situated in an area mentioned in paragraph (a).

(1AA)In subsection (1A)(a) “GB internal waters” means waters in or adjacent to Great Britain which are between the mean low water mark and the seaward limits of the territorial sea adjacent to Great Britain, but do not form part of that territorial sea.]

[F24(1B)In this Part, references to participation, in relation to the transmission of electricity, are to be construed in accordance with section 4(3A) and (3B) above [F25 and section 6F].]

(2)The provision of section 3 of the M4 Administration of Justice (Scotland) Act 1972 (power of arbiter to state case to Court of Session) shall not apply in relation to any determination under this Part made by an arbiter.

Textual Amendments

F2Words in s. 64(1) repealed (1.9.2004) by Energy Act 2004 (c. 20), s. 198(2), Sch. 23 Pt. 1; S.I. 2004/2184, art. 2(2), Sch. 2

F4S. 64(1): definitions of “authorised distributor” and “distribute” inserted (1.10.2001) by 2000 c. 27, s. 108, Sch. 6 Pt. II para. 38(2); S.I. 2001/3266, art. 2, Sch. (subject to transitional provisions in arts. 3-20)

F5S. 64(1): definition of “authorised supplier” inserted (7.11.2000 for specified purposes and otherwise 1.10.2001) by 2000 c. 27, s. 108, Sch. 6 Pt. II para. 38(2); S.I. 2000/2974, art. 2, Sch. (subject to transitional provisions in arts. 3-12); S.I. 2001/3266, art. 2, Sch. (subject to transitional provisions in arts. 3-20)

F7Words in s. 64(1) inserted (5.10.2004) by Energy Act 2004 (c. 20), ss. 102(4)(a), 198(2); S.I. 2004/2575, art. 2(1), Sch. 1

F8S. 64(1): words in definition of “electrical plant” inserted (1.10.2001) by 2000 c. 27, s. 108, Sch. 6 Pt. II para. 38(3); S.I. 2001/3266, art. 2, Sch. (subject to transitional provisions in arts. 3-20)

F9S. 64(1): definitions of “electricity distributor” and “electricity supplier” inserted (1.10.2001) by 2000 c. 27, s. 108, Sch. 6 Pt. II para. 38(4); S.I. 2001/3266, art. 2, Sch. (subject to transitional provisions in arts. 3-20)

F10Words in s. 64(1) omitted (6.4.2014) by virtue of Energy Act 2011 (c. 16), s. 121(5)(c), Sch. 1 para. 6

F11Words in s. 64(1) inserted (1.12.2004) by Energy Act 2004 (c. 20), ss. 147(7), 198(2); S.I. 2004/2575, art. 2(2), Sch. 2

F13Words in s. 64(1) inserted (1.3.2005 for specified purposes, 29.7.2010 for specified purposes, 10.6.2014 in so far as not already in force) by Energy Act 2004 (c. 20), ss. 89(4), 198(2); S.I. 2005/442, art. 2(1), Sch. 1; S.I. 2010/1889, art. 2; S.I. 2014/1460, art. 2

F14Words in s. 64(1) substituted (29.7.2010 for specified purposes, 10.6.2014 in so far as not already in force) by Energy Act 2004 (c. 20), ss. 180(1), 198(2); S.I. 2010/1889, art. 2; S.I. 2014/1460, art. 2

F15S. 64(1): definition of “licensable activity” inserted (1.10.2001) by 2000 c. 27, s. 108, Sch. 6 Pt. II para. 38(5); S.I. 2001/3266, art. 2, Sch. (subject to transitional provisions in arts. 3-20)

F16S. 64(1): definition of “Monopolies Commission” repealed (1.4.1999) by S.I. 1999/506, art. 24(c)

F17S. 64(1): words in definition of “prescribed” substituted (1.10.2001) by 2000 c. 27, s. 108, Sch. 6 Pt. II para. 38(6); S.I. 2001/3266, art. 2, Sch. (subject to transitional provisions in arts. 3-20)

F18S. 64(1): definitions of “private electricity supplier”, “public electricity supplier” and “tariff customer” repealed (1.10.2001) by 2000 c. 27, s. 108, Sch. 6 Pt. II para. 38(8), Sch. 8; S.I. 2001/3266, art. 2, Sch. (subject to transitional provisions in arts. 3-20)

F20Words in s. 64(1) inserted (5.10.2004) by Energy Act 2004 (c. 20), ss. 102(4)(b), 198(2); S.I. 2004/2575, art. 2(1), Sch. 1

F21S. 64(1): definition of “special connection agreement” inserted (1.10.2001) by 2000 c. 27, s. 108, Sch. 6 Pt. II para. 38(7); S.I. 2001/3266, art. 2, Sch. (subject to transitional provisions in arts. 3-20)

F23S. 64(1A)(1AA) inserted (29.7.2010 for specified purposes, 10.6.2014 in so far as not already in force) by Energy Act 2008 (c. 32), ss. 44(3), 110(2); S.I. 2010/1888, art. 2(1); S.I. 2014/1461, art. 2(a)

F25Words in s. 64(1B) inserted (18.2.2014) by Energy Act 2013 (c. 32), ss. 147(4), 156(2)

Modifications etc. (not altering text)

Marginal Citations

Back to top

Options/Help

Print Options

You have chosen to open The Whole Act

The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Act as a PDF

The Whole Act you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open The Whole Act without Schedules

The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Act without Schedules as a PDF

The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Act

The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open the Whole Act without Schedules

The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Impact Assessments

Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:

  • Why the government is proposing to intervene;
  • The main options the government is considering, and which one is preferred;
  • How and to what extent new policies may impact on them; and,
  • The estimated costs and benefits of proposed measures.
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources