Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.
(1)Where the calculation is for the purposes of section 30, the calculation date is—
(a)where the employee’s contract has been varied, or a new contract entered into, in connection with a period of short-time working, the last day on which the original contract was in force, and
(b)otherwise, the day in respect of which the guarantee payment is payable.
(2)Where the calculation is for the purposes of section 53 or 54, the calculation date is the day on which the employer’s notice was given.
(3)Where the calculation is for the purposes of section 56, the calculation date is the day of the appointment.
[F1(3A)Where the calculation is for the purposes of section 57ZF, the calculation date is the day of the appointment.]
[F2(3B)Where the calculation is for the purposes of section 57ZK or 57ZM, the calculation date is the day of the appointment.]
(4)Where the calculation is for the purposes of section 62, the calculation date is the day on which the time off was taken or on which it is alleged the time off should have been permitted.
[F3(4A)Where the calculation is for the purposes of section 63B, the calculation date is the day on which the time off was taken or on which it is alleged the time off should have been permitted.]
[F4(4B)Where the calculation is for the purposes of section 63J, the calculation date is the day on which the section 63D application was made.]
(5)Where the calculation is for the purposes of section 69—
(a)in the case of an employee suspended on medical grounds, the calculation date is the day before that on which the suspension begins, and
(b)in the case of an employee suspended on maternity grounds, the calculation date is—
[F5(i)where the day before that on which the suspension begins falls during a period of ordinary or additional maternity leave, the day before the beginning of that period,]
(ii)otherwise, the day before that on which the suspension begins.
[F6(6)Where the calculation is for the purposes of section 80I, the calculation date is the day on which the application under section 80F was made.]
Textual Amendments
F1S. 225(3A) inserted (1.10.2014) by Children and Families Act 2014 (c. 6), ss. 127(2)(c), 139(6); S.I. 2014/1640, art. 4(a)
F2S. 225(3B) inserted (5.4.2015) by Children and Families Act 2014 (c. 6), ss. 128(2)(d), 139(6); S.I. 2014/1640, art. 6(d)
F3S. 225(4A) inserted (1.9.1999) by 1998 c. 30, s. 44(1), Sch. 3 para. 14 (with s. 42(8)); S.I. 1999/987, art. 2
F4S. 225(4B) inserted (6.4.2010 for certain purposes and otherwise prosp.) by Apprenticeships, Skills, Children and Learning Act 2009 (c. 22), ss. 40, 269(4), Sch. 1 para. 8; S.I. 2010/303, art. 4, Sch. 3 (with arts. 8-14) (as amended by S.I. 2010/1151, art. 22)
F5S. 225(5)(b)(i) substituted (15.12.1999) by 1999 c. 26, s. 9, Sch. 4 Pt. III para. 39; S.I. 1999/2830, art. 2(2), Sch. 1 Pt. II (with Sch. 3 paras. 10, 11)
F6S. 225(6) inserted (6.4.2003) by Employment Act 2002 (c. 22), s. 53, Sch. 7 para. 45; S.I. 2002/2866, art. 2(3), Sch. 1 Pt. 3
Modifications etc. (not altering text)
C1Ss. 220-228 applied (6.4.2006 with application in accordance with reg. 21(1) of the amending S.I.) by The Transfer of Undertakings (Protection of Employment) Regulations 2006 (S.I. 2006/246), regs. 1(2), 16(4) (with reg. 21(5))
(1)Where the calculation is for the purposes of section 88 or 89, the calculation date is the day immediately preceding the first day of the period of notice required by section 86(1) or (2).
(2)Where the calculation is for the purposes of section 93, 117 or 125, the calculation date is—
(a)if the dismissal was with notice, the date on which the employer’s notice was given, and
(b)otherwise, the effective date of termination.
(3)Where the calculation is for the purposes of section [F7112, 119, 120 [F8, 121 or 124]] , the calculation date is—
F9(a). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
(b)if by virtue of subsection (2) or (4) of section 97 a date later than the effective date of termination as defined in subsection (1) of that section is to be treated for certain purposes as the effective date of termination, the effective date of termination as so defined, and
(c)otherwise, the date specified in subsection (6).
(4)Where the calculation is for the purposes of section 147(2), the calculation date is the day immediately preceding the first of the four, or six, weeks referred to in section 148(2).
(5)Where the calculation is for the purposes of section 162, the calculation date is—
F9(a). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
(b)if by virtue of subsection (5) of section 145 a date is to be treated for certain purposes as the relevant date which is later than the relevant date as defined by the previous provisions of that section, the relevant date as so defined, and
(c)otherwise, the date specified in subsection (6).
(6)The date referred to in subsections (3)(c) and (5)(c) is the date on which notice would have been given had—
(a)the contract been terminable by notice and been terminated by the employer giving such notice as is required by section 86 to terminate the contract, and
(b)the notice expired on the effective date of termination, or the relevant date,
(whether or not those conditions were in fact fulfilled).
Textual Amendments
F7Words in s. 226(3) substituted (1.10.2004) by Employment Act 2002 (c. 22), ss. 53, 55(2), Sch. 7 para. 46; S.I. 2004/2185, art. 2
F8Words in s. 226(3) substituted (29.7.2013) by The Unfair Dismissal (Variation of the Limit of Compensatory Award) Order 2013 (S.I. 2013/1949), arts. 1, 3 (with art. 4)
F9S. 226(3)(a)(5)(a) repealed (15.12.1999) by 1999 c. 26, ss. 9, 44, Sch. 4 Pt. III para. 40, Sch. 9(2); S.I. 1999/2830, art. 2(2)(3), Sch. 1 Pt. II, Sch. 2 Pt. II (with Sch. 3 paras. 10, 11)
Modifications etc. (not altering text)
C2Ss. 226-229 applied (with modifications) (4.3.1998) by S.I. 1998/192, reg. 37(1)
C3Ss. 220-228 applied (6.4.2006 with application in accordance with reg. 21(1) of the amending S.I.) by The Transfer of Undertakings (Protection of Employment) Regulations 2006 (S.I. 2006/246), regs. 1(2), 16(4) (with reg. 21(5))
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: