Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
22(1)To the extent that development consists of any operation or work mentioned in the left-hand column of the table in sub-paragraph (4) below, it shall be carried out in accordance with plans and specifications for the time being approved by the county planning authority at the request of the nominated undertaker.U.K.
(2)The county planning authority may, on approving a plan or specification for the purposes of this paragraph, specify any respect in which it requires additional details of the development to be submitted for approval.
(3)Where the county planning authority exercises the power conferred by sub-paragraph (2) above, the plans and specifications in accordance with which the development is required under sub-paragraph (1) above to be carried out shall, as regards the specified respect, include a plan or specification showing the additional details.
(4)The only ground on which the county planning authority may refuse to approve for the purposes of this paragraph plans or specifications of any operation or work mentioned in the following table is a ground specified in relation to it in the right-hand column of that table.
Operation or work | Grounds |
---|---|
1.Highway access The formation, laying out or alteration of any means of access to a highway used, or proposed highway proposed to be used, by vehicular traffic. | That the development ought to be modified to prevent or reduce prejudicial effects on road safety or on the free flow of traffic in the local area, and is reasonably capable of being so modified. |
2.Waste and spoil disposal The disposal of waste or spoil. | That— (a) the design or external appearance of disposal sites on land within the relevant limits, (b) the methods by which such sites are worked, or (c) the noise, dust, vibration or screening arrangements during the operation of such sites, ought to be modified and are reasonably capable of being modified. That— (a) to preserve the local environment or local amenity, (b) to prevent or reduce prejudicial effects on road safety or on the free flow of traffic in the local area, or (c) to preserve a site of archaeological or historic interest or nature conservation value, the development ought to be carried out on land elsewhere within the relevant limits, and is reasonably capable of being so carried out. |
3.Borrow pits The excavation of bulk materials from borrow pits. | That— (a) the design or external appearance of borrow pits on land within the relevant limits, (b) the methods by which such pits are worked, or (c) the noise, dust, vibration or screening arrangements during the operation of such pits, ought to be modified and are reasonably capable of being modified. That— (a) to preserve the local environment or local amenity, (b) to prevent or reduce prejudicial effects on road safety or on the free flow of traffic in the local area, or (c) to preserve a site of archaeological or historic interest or nature conservation value, the development ought to be carried out on land elsewhere within the relevant limits, and is reasonably capable of being so carried out. |
Note: In the case of items 2 and 3, the second of the grounds specified does not apply in relation to development which—
(a)is within the limits of deviation for the scheduled works, or
(b)consists of the use of land specified in columns (1) and (2) of Part I of Schedule 4 for a purpose specified in relation to the land in column (3) of that Part.
(5)Sub-paragraph (4) above shall apply in relation to the imposition of conditions on approval as it applies in relation to the refusal of approval.
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: