Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
23(1)Development shall be carried out in accordance with arrangements approved by the county planning authority at the request of the nominated undertaker with respect to the matters mentioned in the left-hand column of the table in sub-paragraph (2) below.U.K.
(2)The only ground on which the county planning authority may refuse to approve for the purposes of this paragraph arrangements with respect to a matter mentioned in the following table is—
(a)that the arrangements relate to development which, for the purposes of regulating the matter in question, ought to and can reasonably be considered in conjunction with other permitted development which is to be carried out in the authority’s area, or
(b)the ground specified in relation to the matter in the right-hand column of the table.
Matters | Grounds |
---|---|
1.Handling of re-usable spoil and top soil Handling during removal, storage, and re-use of any spoil or top soil removed during the course of carrying out the development. | That the arrangements ought to be modified to ensure that the spoil or top soil remains in good condition and are reasonably capable of being so modified. |
2. Storage sites Sites on land within the relevant limits at which— (a) minerals, aggregates or other construction materials required for the development, or (b) spoil or top soil, are to be stored until used or re-used in carrying out the development or disposed of as waste. | That the arrangements ought to be modified— (a) to preserve the local environment, local amenity or a site of archaeological or historic interest or nature conservation value, or (b) to prevent or reduce prejudicial effects on road safety or on the free flow of traffic in the local area, and are reasonably capable of being so modified. |
3.Construction camps Sites on land within the relevant limits which are to be used for the residential accommodation of persons engaged in carrying out the development. | As item 2. |
4.Screening Provision where necessary on land within the relevant limits of any screening for working sites on such land required for the purpose of carrying out the development. | As item 2. |
5.Hours of working The hours and days of the week during which work on the development on land within the relevant limits is to be carried out. | That the arrangements ought to be modified to preserve the local environment or local amenity, and are reasonably capable of being so modified. |
6.Artificial lighting The use of artificial lighting on land within the relevant limits for the purpose of carrying out the development. | As item 5. |
7.Suppression of noise, dust and vibration The suppression of noise, dust and vibration caused by construction operations carried on on land within the relevant limits for the purpose of carrying out the development. | As item 5. |
8.Mud on highway Measures to be taken on land within the relevant limits to prevent mud being carried onto any public highway as a result of carrying on the development. | That the arrangements ought to be modified— (a) to preserve the local environment or local amenity, or (b) to prevent or reduce prejudicial effects on road safety or on the free flow of traffic in the local area, and are reasonably capable of being so modified. |
9.Highway access The formation, laying out or alteration of any means of access to any highway used, or proposed highway proposed to be used, on a temporary basis by vehicular traffic to serve a working site or camp. | That the arrangements ought to be modified to prevent or reduce prejudicial effects on road safety or on the free flow of traffic in the local area, and are reasonably capable of being so modified. |
(3)The county planning authority may only impose conditions on approval for the purposes of this paragraph with the agreement of the nominated undertaker.
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: