Flood and Water Management Act 2010

 Help about what version

What Version

 Help about advanced features

Advanced Features

Changes over time for: Cross Heading: Land Drainage Act 1991

 Help about opening options

Version Superseded: 01/10/2011

Status:

Point in time view as at 19/07/2011. This version of this cross heading contains provisions that are not valid for this point in time. Help about Status

Close

Status

Not valid for this point in time generally means that a provision was not in force for the point in time you have selected to view it on.

Changes to legislation:

There are currently no known outstanding effects for the Flood and Water Management Act 2010, Cross Heading: Land Drainage Act 1991. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

Land Drainage Act 1991E+W

25E+WThe Land Drainage Act 1991 is amended as follows.

Commencement Information

I1Sch. 2 para. 25 in force at 1.10.2010 by S.I. 2010/2169, art. 4, Sch.

Valid from 06/04/2012

26E+WSection 8 (concurrent powers of the Environment Agency) is repealed.

Valid from 06/04/2012

27E+WIn section 9(1) (default powers of the Agency)—

(a)omit “but without prejudice to section 8 above”, and

(b)omit “flooding or”.

28E+WAt the end of section 11 (arrangements between drainage authorities) add—

(5)Two internal drainage boards may agree that one is to provide administrative, professional or technical services for the other.

Commencement Information

I2Sch. 2 para. 28 in force at 1.10.2010 by S.I. 2010/2169, art. 4, Sch.

29(1)After section 14 (general drainage powers of boards and local authorities) insert—E+W

14AGeneral powers: flood risk management works

(1)A lead local flood authority may carry out flood risk management work if Conditions 1 and 2 are satisfied.

(2)An authority listed in subsection (3) may carry out flood risk management work if—

(a)Conditions 1 and 3 are satisfied, or

(b)Conditions 1 and 4 are satisfied.

(3)The authorities are—

(a)an internal drainage board,

(b)a district council, and

(c)a lead local flood authority for an area for which there is no district council.

(4)Condition 1 is that the authority considers the work desirable having regard to the local flood risk management strategy for its area under section 9 or 10 of the Flood and Water Management Act 2010.

(5)Condition 2 is that the purpose of the work is to manage a flood risk in the authority's area from—

(a)surface runoff, or

(b)groundwater.

(6)Condition 3 is that the purpose of the work is to manage a flood risk in the authority's area from an ordinary watercourse.

(7)In subsection (6) the reference to an ordinary watercourse includes a reference to a lake, pond or other area of water which flows into an ordinary watercourse.

(8)Condition 4 is that the purpose of the work is to manage a flood risk in the authority's area from the sea and either—

(a)the work is within subsection (9)(a), (b) or (f), or

(b)the Environment Agency has consented to the work.

(9)In this section “flood risk management work” means anything done—

(a)to maintain existing works (including buildings and structures) including cleansing, repairing or otherwise maintaining the efficiency of an existing watercourse or drainage work;

(b)to operate existing works (such as sluicegates or pumps);

(c)to improve existing works (including buildings or structures) including anything done to deepen, widen, straighten or otherwise improve an existing watercourse, to remove or alter mill dams, weirs or other obstructions to watercourses, or to raise, widen or otherwise improve a drainage work;

(d)to construct or repair new works (including buildings, structures, watercourses, drainage works and machinery);

(e)for the purpose of maintaining or restoring natural processes;

(f)to monitor, investigate or survey a location or a natural process;

(g)to reduce or increase the level of water in a place;

(h)to alter or remove works.

(10)Nothing in this section authorises a person to enter land except for the purpose of maintaining existing works.

(11)Section 14(5) and (6) applies in relation to the exercise by any authority of powers under this section as to the exercise of powers under section 14.

(12)The powers under section 62 and 64 are available to an authority for a purpose in connection with the exercise of powers under this section.

(13)In this section the following terms have the meaning given by Part 1 of the Flood and Water Management Act 2010—

(a)flood risk,

(b)lead local flood authority,

(c)surface runoff, and

(d)groundwater.

(2)In section 14(1)(b)—

(a)omit “either”, and

(b)omit sub-paragraph (ii) (and the “or” before it).

(3)Omit section 14(4)(b) (and the “or” before it).

Commencement Information

I3Sch. 2 para. 29 in force at 19.7.2011 for E. by S.I. 2011/1770, art. 3(e)

30E+WSection 17 (supervision by the Agency: works) is repealed.

Commencement Information

I4Sch. 2 para. 30 in force at 19.7.2011 for E. by S.I. 2011/1770, art. 3(e) (with art. 4(2))

Valid from 06/04/2012

31(1)Section 21 (enforcement of obligations to repair watercourses and bridges) is amended as follows.E+W

(2)For subsection (6)(b) substitute—

(b)in relation to any watercourse, bridge or drainage works in an area outside an internal drainage district, are references to the lead local flood authority for the area.

(3)After subsection (6) add—

(7)Lead local flood authority” has the meaning given by section 6 of the Flood and Water Management Act 2010.

Prospective

32(1)Section 23 (prohibitions on obstructions) is amended as follows.E+W

(2)For subsection (1)(b) substitute—

(b)erect a culvert in an ordinary watercourse, or

(c)alter a culvert in a manner that would be likely to affect the flow of an ordinary watercourse,.

(3)After subsection (1) insert—

(1A)Consent under this section may be given subject to reasonable conditions.

(1B)An internal drainage board or lead local flood authority must consult the Environment Agency before carrying out work within subsection (1)(a), (b) or (c) if the board or authority is “the drainage board concerned” for the purposes of this section.

(1C)The drainage board concerned must have regard to any guidance issued by the Environment Agency about the exercise of the board's functions under this section.

(4)In subsection (2) for “and the amount of that fee shall be £50 or such other sum as may be prescribed” substitute “ and the amount of the fee shall be determined in accordance with a prescribed charging scheme. ”

(5)In subsection (8) for “section 24” substitute “ sections 24 and 25 ”.

(6)For subsection (8)(b) substitute—

(b)in relation to a watercourse in an area outside an internal drainage district, are references to the lead local flood authority for the area.

(7)After subsection (8) add—

(9)Lead local flood authority” has the meaning given by section 6 of the Flood and Water Management Act 2010.

Commencement Information

I5S. 32(1)(2)(3)(5)(6)(7) in force at 6.4.2012 by S.I. 2012/879, art. 3(b)

Valid from 06/04/2012

33(1)Section 25 (powers to require works for maintaining the flow of watercourse) is amended as follows.E+W

(2)In subsection (1)—

(a)omit “Subject to section 26 below”, and

(b)omit “or local authority”.

(3)Omit subsection (2).

(4)In subsections (6)(a), (7) and (8) omit “or local authority”.

Valid from 06/04/2012

34E+WSection 26 (competing jurisdictions under section 25) is repealed.

35(1)Section 33 (commutation of obligations) is amended as follows.E+W

(2)In subsection (1) for “Agency or the drainage board for the internal drainage district” substitute “ relevant authority for the area ”.

(3)In subsection (2)—

(a)for “Agency or an internal drainage board propose” substitute “ relevant authority proposes ”, and

(b)for “Agency or board” substitute “ authority ”.

(4)In subsection (3) for “Agency or board”, in each place, substitute “ relevant authority ”.

(5)After subsection (5) insert—

(5A)In this section and section 34, references to the relevant authority for an area—

(a)in relation to work in an area which forms part of an internal drainage district, are references to the drainage board for the district, and

(b)in relation to work in any other area, are references to the lead local flood authority for the area.

(5B)Lead local flood authority” has the meaning given by section 6 of the Flood and Water Management Act 2010.

(6)For subsection (6)(a) substitute—

(a)in relation to a lead local flood authority for an area in England, means the Secretary of State,

(aa)in relation to a lead local flood authority for an area in Wales, means the Welsh Ministers, and.

Commencement Information

I6Sch. 2 para. 35 in force at 19.7.2011 for E. by S.I. 2011/1770, art. 3(e)

36(1)Section 34 (financial consequences of commutation) is amended as follows.E+W

(2)In subsection (2) for “Agency or internal drainage board” substitute “ relevant authority ”.

(3)In subsection (4)—

(a)for “Agency or internal drainage board” substitute “ relevant authority ”, and

(b)for “Agency or, as the case may be, that board” substitute “ relevant authority ”.

(4)In subsection (5) for “Agency or, as the case may be, the internal drainage board” substitute “ relevant authority ”.

(5)In subsection (6)—

(a)for “Agency or an internal drainage board” substitute “ relevant authority ”, and

(b)for “Agency or board” substitute “ authority ”.

(6)In subsections (7) and (9) for “Agency or internal drainage board” substitute “ relevant authority ”.

Commencement Information

I7Sch. 2 para. 36 in force at 19.7.2011 for E. by S.I. 2011/1770, art. 3(e)

37E+WIn section 59 (grants) omit subsection (4)(c).

Commencement Information

I8Sch. 2 para. 37 in force at 6.4.2011 by S.I. 2011/694, art. 4(1)(i)

38(1)Section 66 (byelaws) is amended as follows.E+W

(2)For subsection (1) substitute—

(1)An internal drainage board may make byelaws for Purpose 1, 2 or 3.

(1A)A local authority, except an English county council, may make byelaws for Purpose 1, 2, 3 or 4.

(1B)An English county council which is a lead local flood authority may make byelaws for Purpose 3 or 4.

(1C)Purpose 1 is to secure the efficient working of a drainage system in the authority's district or area.

(1D)Purpose 2 is to regulate the effects on the environment in the authority's district or area of a drainage system.

(1E)Purpose 3 is to secure the effectiveness of flood risk management work within the meaning of section 14A.

(1F)Purpose 4 is to secure the effectiveness of works done in reliance on section 38 or 39 of the Flood and Water Management Act 2010 (incidental flooding or coastal erosion).

(3)In subsection (2) for “Without prejudice to the generality of subsection (1) above but subject as aforesaid, an internal drainage board or local authority, other than an English county council, may, in particular, make byelaws for any of the following purposes, that is to say” substitute “ Byelaws may, in particular, have the purpose of ”.

(4)For subsection (3) substitute—

(3)An internal drainage board may not rely on this section to do anything in connection with a main river, the banks of a main river or any drainage works in connection with a main river.

Commencement Information

I9Sch. 2 para. 38 in force at 19.7.2011 for E. by S.I. 2011/1770, art. 3(e)

39E+WIn section 72 (interpretation) in subsection (1) after the definition of “conservancy authority” insert—

culvert” means a covered channel or pipe which prevents the obstruction of a watercourse or drainage path by an artificial construction.

Commencement Information

I10Sch. 2 para. 39 in force at 19.7.2011 for E. by S.I. 2011/1770, art. 3(e)

Back to top

Options/Help

Print Options

You have chosen to open The Whole Act

The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Act as a PDF

The Whole Act you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Act

The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Notes

Text created by the government department responsible for the subject matter of the Act to explain what the Act sets out to achieve and to make the Act accessible to readers who are not legally qualified. Explanatory Notes were introduced in 1999 and accompany all Public Acts except Appropriation, Consolidated Fund, Finance and Consolidation Acts.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources