- Latest available (Revised)
- Original (As enacted)
This is the original version (as it was originally enacted).
(1)Planning permission is deemed to be granted under Part 3 of the Town and Country Planning Act 1990 for the carrying out of development authorised by this Act.
This is subject to the other provisions of this Act.
(2)Where development authorised by this Act consists of the carrying out of a work which is not a scheduled work, subsection (1) does not apply if—
(a)the development is likely to have significant effects on the environment by virtue of factors such as its nature, size or location,
(b)the development is not exempt development within the meaning of the Environmental Impact Assessment Regulations, and
(c)the development is not covered by an environmental assessment in connection with the High Speed Rail (London - West Midlands) Bill.
(3)Schedule 17 imposes conditions on deemed planning permission under subsection (1).
(4)Deemed planning permission under subsection (1) is specific planning permission for the purposes of section 264(3)(a) of the Town and Country Planning Act 1990 (specific planning permission for development of statutory undertakers’ land relevant to whether the land is operational land).
(5)Development which has deemed planning permission under subsection (1) is not development of a class for which planning permission is granted by the Town and Country Planning (General Permitted Development) (England) Order 2015 (S.I. 2015/596) (or any order replacing it).
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Text created by the government department responsible for the subject matter of the Act to explain what the Act sets out to achieve and to make the Act accessible to readers who are not legally qualified. Explanatory Notes were introduced in 1999 and accompany all Public Acts except Appropriation, Consolidated Fund, Finance and Consolidation Acts.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: