5.—(1) During the construction of the works the Council may take from the said Kilduskland Reservoir such water as they may require for such construction.
(2) After completion of the works the Council–
(a)shall not in any one day take from the said Kilduskland Reservoir a quantity of water greater than 2,900 cubic metres as measured through or over an approved gauge (part of Work No. 2); and
(b)shall discharge as a compensation flow into the Kilduskland Burn from the reservoir in a uniform and continuous flow a quantity of water not less than 90 cubic metres per day as measured through or over an approved gauge (part of Work No. 3), which gauge the Council shall instal before taking any water from the said reservoir.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include: