3. Every—
(a)dam the construction of which commenced on or after 1st January 1995,
(b)mill dam constructed after 28th July 1865, and
(c)portion, of any other mill dam, renewed or repaired at any time after 28th July 1865,
shall be made and maintained watertight by the operator so that no water, which can reasonably be prevented, shall run through it except when necessary to maintain the stability of the dam.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include: