36.10—(1) If a person makes an offer to settle before proceedings are begun which complies with the provisions of this rule, the court will take that offer into account when making any order as to costs.
(2) The offer must—
(a)be expressed to be open for at least 21 days after the date it was made;
(b)if made by a person who would be a defendant were proceedings commenced, include an offer to pay the costs of the offeree incurred up to the date 21 days after the date it was made; and
(c)otherwise comply with this Part.
(3) If the offeror is a defendant to a money claim—
(a)he must make a Part 36 payment within 14 days of service of the claim form; and
(b)the amount of the payment must be not less than the sum offered before proceedings began.
(4) An offeree may not, after proceedings have begun, accept—
(a)an offer made under paragraph (2); or
(b)a Part 36 payment made under paragraph (3),
without the permission of the court.
(5) An offer under this rule is made when it is received by the offeree.
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument without Schedules you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include: