- Latest available (Revised)
- Point in Time (01/10/2005)
- Original (As made)
Version Superseded: 06/04/2007
Point in time view as at 01/10/2005. This version of this provision has been superseded.
You are viewing this legislation item as it stood at a particular point in time. A later version of this or provision, including subsequent changes and effects, supersedes this version.
Note the term provision is used to describe a definable element in a piece of legislation that has legislative effect – such as a Part, Chapter or section.
There are currently no known outstanding effects for the The Civil Procedure Rules 1998, Section 44.3.
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
44.3—(1) The court has discretion as to—
(a)whether costs are payable by one party to another;
(b)the amount of those costs; and
(c)when they are to be paid.
(2) If the court decides to make an order about costs—
(a)the general rule is that the unsuccessful party will be ordered to pay the costs of the successful party; but
(b)the court may make a different order.
(3) The general rule does not apply to the following proceedings—
(a)proceedings in the Court of Appeal on an application or appeal made in connection with proceedings in the Family Division; or
(b)proceedings in the Court of Appeal from a judgment, direction, decision or order given or made in probate proceedings or family proceedings.
(4) In deciding what order (if any) to make about costs, the court must have regard to all the circumstances, including—
(a)the conduct of all the parties;
(b)whether a party has succeeded on part of his case, even if he has not been wholly successful; and
(c)any payment into court or admissible offer to settle made by a party which is drawn to the court’s attention (whether or not made in accordance with Part 36).
(Part 36 contains further provisions about how the court’s discretion is to be exercised where a payment into court or an offer to settle is made under that Part)
(5) The conduct of the parties includes—
(a)conduct before, as well as during, the proceedings and in particular the extent to which the parties followed any relevant pre-action protocol;
(b)whether it was reasonable for a party to raise, pursue or contest a particular allegation or issue;
(c)the manner in which a party has pursued or defended his case or a particular allegation or issue; and
(d)whether a claimant who has succeeded in his claim, in whole or in part, exaggerated his claim.
(6) The orders which the court may make under this rule include an order that a party must pay—
(a)a proportion of another party’s costs;
(b)a stated amount in respect of another party’s costs;
(c)costs from or until a certain date only;
(d)costs incurred before proceedings have begun;
(e)costs relating to particular steps taken in the proceedings;
(f)costs relating only to a distinct part of the proceedings; and
(g)interest on costs from or until a certain date, including a date before judgment.
(7) Where the court would otherwise consider making an order under paragraph (6)(f), it must instead, if practicable, make an order under paragraph (6)(a) or (c).
(8) Where the court has ordered a party to pay costs, it may order an amount to be paid on account before the costs are assessed.
(9) Where a party entitled to costs is also liable to pay costs the court may assess the costs which that party is liable to pay and either—
(a)set off the amount assessed against the amount the party is entitled to be paid and direct him to pay any balance; or
(b)delay the issue of a certificate for the costs to which the party is entitled until he has paid the amount which he is liable to pay.
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument without Schedules you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.