The Landfill (England and Wales) Regulations 2002

Status:

This is the original version (as it was originally made).

Regulations 14(2) and 15(5)(c)

SCHEDULE 3MINIMUM MONITORING PROCEDURES FOR LANDFILLS

1.  This Schedule sets out minimum procedures for monitoring to be carried out to check—

(a)that waste has been accepted for disposal only if it fulfils the relevant waste acceptance criteria;

(b)that the processes within the landfill proceed as desired;

(c)that environmental protections systems are functioning fully as intended; and

(d)that the conditions of the landfill permit are fulfilled.

2.—(1) Samples of leachate or surface water (if present) must be collected at representative points.

(2) Sampling and measuring of the volume and composition of any leachate must be performed separately at each point at which leachate is discharged from the site.

(3) Monitoring of surface water (if present) shall take place at at least two points, one upstream from the landfill and one downstream.

(4) Gas monitoring must be carried out for each section of the landfill and representative samples must be collected and analysed in accordance with Table 1.

(5) A representative sample of leachate and water shall be taken for monitoring purposes in accordance with Table 1.

TABLE 1

Operational phaseAfter-care phase1

Notes to Table 1

1

Longer intervals may be allowed if the evaluation of data indicates that they would be equally effective. For leachates, the conductivity must always be measured at least once a year.

2

These do not apply where leachate collection is not required under paragraph 2(1)(c) of Schedule 2.

3

The frequency of sampling may be adapted on the basis of the morphology of the landfill waste (in tumulus, buried, etc) (but only if the Environment Agency considers that the conditions of the landfill permit should allow for it).

4

The parameters to be measured and substances to be analysed vary according to the composition of the waste deposited. They must be specified in the conditions of the landfill permit and reflect the leaching characteristics of the wastes.

5

On the basis of the characteristics of the landfill site, the Environment Agency may determine that these measurements are not required.

6

These measurements are related mainly to the content of the organic material in the waste.

7

CH4, CO2, O2 regularly, other gases as required, according to the composition of the waste deposited, with a view to reflecting its leaching properties.

8

Efficiency of the gas extraction system must be checked regularly.

Leachate volume2Monthly1, 3Every six months
Leachate composition2, 4Quarterly1Every six months
Volume and composition of surface water5Quarterly1Every six months
Potential gas emissions and atmospheric pressure6 (CH4, CO2, O2, H2S, H2 etc)Monthly1, 7Every six months8

3.—(1) The sampling measurements taken must be sufficient to provide information on groundwater likely to be affected by the discharge from the landfill, with at least one measuring point in the groundwater inflow region and two in the outflow region.

(2) The number of measurements referred to sub-paragraph (1) may be increased on the basis of a specific hydrogeological survey or the need for an early identification of accidental leachate release in the groundwater.

(3) Sampling must be carried out in at least three locations before filling operations in order to establish reference values for future sampling.

4.—(1) The monitoring of groundwater shall be carried out in accordance with Table 2.

(2) The parameters to be analysed in the samples taken must be derived from the expected composition of the leachate and the groundwater quality in the area.

(3) In selecting the parameters for analysis, the mobility in the groundwater zone must be taken into account.

(4) Parameters may include indicator parameters in order to ensure an early recognition of change in water quality (the recommended parameters are pH, TOC, phenols, heavy metals, fluoride, As, oil/hydrocarbons).

TABLE 2

Operational phaseAfter-care phase

Notes to Table 2

1

If there are fluctuating groundwater levels, the frequency must be increased.

2

The frequency must be based on the possibility for remedial action between two samplings if a trigger level is reached, i.e. the frequency must be determined on the basis of knowledge and the evaluation of the velocity of groundwater flow.

3

When a trigger level is reached (see paragraph 5), verification is necessary by repeating the sampling. When the level has been confirmed, a contingency plan set out in the landfill permit conditions must be followed.

Level of groundwaterEvery six months1Every six months1
Groundwater compositionSite-specific frequency2, 3Site-specific frequency2, 3

5.—(1) Significant adverse environmental effects, as referred to in regulations 14(3) and 15(5)(b), should be considered to have occurred in the case of groundwater when an analysis of a groundwater sample shows a significant change in water quality.

(2) The level at which the effects referred to in sub-paragraph (1) are considered to have occurred (“the trigger level”) must be determined taking account of the specific hydrogeological formations in the location of the landfill and groundwater quality.

(3) The trigger level must be set out in the conditions of the landfill permit whenever possible.

(4) The observations must be evaluated by means of control charts with established control rules and levels for each downgradient well.

(5) The control levels must be determined from local variations in groundwater quality.

6.  The topography of the site and settling behaviour of the landfill body shall be monitored in accordance with Table 3.

TABLE 3

Operational phaseAfter-care phase

Note to Table 3

1

Data for the status plan of the relevant landfill: surface occupied by waste, volume and composition of waste, methods of depositing, time and duration of depositing, calculation of the remaining capacity still available at the landfill.

Structure and composition of landfill body1Yearly
Settling behaviour of the level of the landfill bodyYearlyYearly reading

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources