The Water Resources (Environmental Impact Assessment) (England and Wales) Regulations 2003

Changes over time for: The Water Resources (Environmental Impact Assessment) (England and Wales) Regulations 2003 (without Schedules)

 Help about opening options

Version Superseded: 30/11/2017

Status:

Point in time view as at 16/05/2017.

Changes to legislation:

There are currently no known outstanding effects for the The Water Resources (Environmental Impact Assessment) (England and Wales) Regulations 2003. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

PART IU.K.GENERAL

Citation, commencement and extentU.K.

1.—(1) These Regulations may be cited as the Water Resources (Environmental Impact Assessment) (England and Wales) Regulations 2003 and shall come into force on 1st April 2003.

(2) These Regulations extend to England and Wales only.

InterpretationU.K.

2.[F1(1)]  In these Regulations, expressions which are used in the EIA Directive have the same meaning as in that Directive, and—

“the 1991 Act” means the Water Resources Act 1991(1);

“abstraction or impounding licence” means a licence under Chapter II of Part II of the 1991 Act;

F2...

[F3“appropriate authority” means—

(a)

the Environment Agency in relation to a project in England;

(b)

the Natural Resources Body for Wales in relation to a project in Wales;]

“appropriate Minister” means—

(a)

[F4in relation to a project in Wales, the Welsh Ministers;]

(b)

in any other case, the Secretary of State

“authorisation” means—

(i)

an abstraction or impounding licence, or

(ii)

a consent under Part III of these Regulations;

“consultation bodies” means—

(a)

the local planning authority within the meaning of Part I of the Town and Country Planning Act 1990(3) within whose area the project is to be carried out;

(b)

in relation to a project to be carried out in England, [F5Natural England] and English Heritage;F6...

(c)

in relation to a project to be carried out in Wales, [F7the Natural Resources Body for Wales] and the [F8Welsh Ministers for the] exercise of functions in the field of ancient monuments and historic buildings(4); [F9and]

(d)

[F10other bodies designated by statutory provision as having specific environmental responsibilities [F11or local or regional competences] which [F12the appropriate authority] or the appropriate Minister, as the case may be, considers likely to have an interest in the application;]

[F13“the EIA Directive” means Directive 2011/92/EU of the European Parliament and of the Council on the assessment of the effects of certain public and private projects on the environment, as amended by Directive 2014/52/EU of the European Parliament and of the Council;]

[F14“environmental impact assessment” means—

(a)

the preparation of an environmental statement under regulation 5;

(b)

the carrying out of consultations under regulation 7;

(c)

the consideration of the environmental statement and other information under regulation 7A(1);

(d)

reaching a conclusion about the likely significant environmental effects of the project under regulation 7A(2); and

(e)

the consideration of that conclusion in the decision of whether or not to grant an authorisation for, or for the variation of an authorisation relating to, a relevant project under regulation 8(2);]

[F14“environmental statement” has the meaning given in regulation 5;]

[F14EU environmental assessment” means an assessment carried out—

(a)

under an obligation to which section 2(1) of the European Communities Act 1972 applies (other than the EIA Directive); or

(b)

under the law of any part of the United Kingdom implementing an EU obligation other than an obligation arising under the EIA Directive,

of the effect of anything on the environment;;]

[F14“the Habitats Directive” means Council Directive 92/43/EEC on the conservation of natural habitats and of wild fauna and flora as last amended by Council Directive 2013/17/EU(1);]

“relevant project” has the meaning given by regulation 3 [F15and]

[F16“the restriction on abstraction” means the restriction imposed by section 24(1) of the 1991 Act(1).]

[F14UK environmental assessment” means an assessment carried out in accordance with an obligation under the law of any part of the United Kingdom of the effect of anything on the environment;]

[F14“the Wild Birds Directive” means Directive 2009/147/EC of the European Parliament and of the Council on the conservation of wild birds(2), as amended by Council Directive 2013/17/EU;]

[F17(2) In these Regulations, any reference to the likely significant effects, or the likely significant adverse effects, of a relevant project, or a project which may be a relevant project, on the environment includes a reference to the effects of that project on the environment once any construction, installation or other intervention is completed and in operation.

(3) In paragraph (2) each reference to the environment includes a reference to the matters referred to in regulation 7A(2)(a) to (e).]

Textual Amendments

Requirement for an environmental impact assessmentU.K.

3.—(1) An environmental impact assessment shall be carried out in accordance with these Regulations in relation to a relevant project.

(2) A project is a relevant project if—

(a)it is a water management project for agriculture, including an irrigation project;

(b)in the case of a project involving water abstraction, [F18the abstraction is one which does not fall within the exception provided in section 27(1) of the 1991 Act in relation to the restriction on abstraction] ; and

(c)it would be likely to have significant effects on the environment by virtue inter alia of its nature, size or location.

[F19(3) A project is not a relevant project if it—

(a)involves development within the meaning of section 55 of the Town and Country Planning Act 1990;

(b)involves improvement works within the meaning of the Environmental Impact Assessment (Land Drainage Improvement Works) Regulations 1999; or

(c)is exempt in accordance with a direction under regulation 3A(1) or (2) or 3B(1).]

[F20Defence and civil emergenciesU.K.

3A.(1) The Secretary of State may direct that a relevant project, or a project which may be a relevant project, is exempt where—

(a)the project has national defence as its sole purpose; and

(b)the Secretary of State considers that an environmental impact assessment in respect of the project would have an adverse effect on the fulfilment of that purpose.

(2) The appropriate Minister may direct that a relevant project, or a project which may be a relevant project, is exempt where—

(a)the project has the response to a civil emergency as its sole purpose; and

(b)the appropriate Minister considers that an environmental impact assessment in respect of the project would have an adverse effect on the fulfilment of that purpose.

(3) Following a direction under paragraph (1) or (2), the person who gave the direction must send notice in writing of the direction to the relevant appropriate authority.

(4) Following a direction under paragraph (1) in respect of a project in Wales, the Secretary of State must send notice in writing of the direction to the Welsh Ministers.

Exceptional circumstancesU.K.

3B.(1) The appropriate Minister may direct that a relevant project, or a project which may be a relevant project, is exempt where the circumstances are exceptional and the appropriate Minister considers that—

(a)an environmental impact assessment would have an adverse effect on the fulfilment of the project’s purpose; and

(b)the objectives of the EIA Directive will be met even though such an assessment is not carried out.

(2) Where the appropriate Minister gives a direction that a relevant project, or a project which may be a relevant project, is exempt under paragraph (1), the appropriate Minister must—

(a)consider whether another form of assessment of the likely significant effects on the environment of the project is appropriate; and

(b)make available to the public concerned—

(i)the direction including an explanation of the reasons for it; and

(ii)the information obtained under any other assessment referred to in sub-paragraph (a).

CoordinationU.K.

3C.  Where, in respect of a relevant project, there is a requirement to carry out an environmental impact assessment and a requirement to carry out an assessment under regulation 21 or 61 of the Conservation of Habitats and Species Regulations 2010, the appropriate Minister must, where appropriate, ensure that the environmental impact assessment and the other assessment, or assessments, are coordinated.]

PART IIU.K.ASSESSMENT OF RELEVANT PROJECTS

Determination whether a project is a relevant projectU.K.

4.—(1) Any person (“the applicant”) who proposes to apply for, or for the variation of, an authorisation in relation to a project which may be a relevant project, may in writing request the [F21appropriate authority] to make a determination whether the project is a relevant project.

[F22(2) The request shall contain—

(a)a description of the project, including in particular a description—

(i)of the physical characteristics of the whole project and, where relevant, of demolition works; and

(ii)of the location of the project, with particular regard to the environmental sensitivity of geographical areas likely to be affected;

(b)a description of the aspects of the environment likely to be significantly affected by the project;

(c)a description of any likely significant effects, to the extent of the information available on such effects, of the project on the environment resulting from—

(i)the expected residues and emissions and the production of waste, where relevant; and

(ii)the use of natural resources, in particular soil, land, water and biodiversity; and

(d)if the applicant elects to provide it, a description of any measure proposed to be taken to avoid or prevent any likely significant adverse effects on the environment.

(2A) When compiling the information referred to in paragraph (2), the applicant shall take into account—

(a)the selection criteria set out in Schedule 1; and

(b)the results of any relevant EU environmental assessment which are reasonably available to the applicant.]

(3) Where the [F21appropriate authority]considers that it has insufficient information to determine the request, it shall by notice in writing inform the applicant and specify what further information it requires.

[F23(4) In determining whether a project is a relevant project the appropriate authority shall take into account—

(a)the selection criteria set out in Schedule 1; and

(b)the results of any relevant EU environmental assessment which are reasonably available to the applicant.]

(5) The [F21appropriate authority] shall give the applicant written notice of its determination before the expiry of—

(a)a period of three weeks beginning with—

(i)the date on which the request is received; or

(ii)where the [F21appropriate authority] has served a notice under paragraph (3), the date on which the further information specified is given to the [F21appropriate authority]; or

[F24(b)where agreed in writing with the applicant, any other period of not more than 90 days beginning with—

(i)the date on which the request is received; or

(ii)where the appropriate authority has served a notice under paragraph (3), the date on which the further information is given to the appropriate authority.]

[F25(5A) The appropriate authority—

(a)may extend the period referred to in paragraph (5) in exceptional cases (such as where the nature, complexity, location or size of the works demands a longer period for determination); and

(b)where it does so, shall inform the applicant in writing of the reasons for the extension and of the date on which its determination under paragraph (1) is expected.]

(6) Where—

(a)the [F21appropriate authority] fails to make a determination before the expiry of the period specified in paragraph (5); or

(b)the applicant is dissatisfied with [F21appropriate authority's] determination that the proposed abstraction or impounding would amount to or form part of a relevant project,

the applicant may apply to the appropriate Minister for a determination on the matter by notice in writing not later than twenty-eight days after the expiry of that period or, as the case may be, after the date of the determination of the [F21appropriate authority].

(7) Where an application is made to the appropriate Minister under paragraph (6), the appropriate Minister shall send a copy of the application to the [F21appropriate authority].

(8) The appropriate Minister shall by notice in writing given to the applicant and the [F21appropriate authority]

(a)uphold the determination of the [F21appropriate authority]; or

(b)substitute his own determination.

[F26(9) A determination under this regulation shall be accompanied by a written statement—

(a)of the reasons for the determination with reference to such of the selection criteria set out in Schedule 1 as are relevant; and

(b)if the determination under paragraph (1) is that the project is not a relevant project, describing any measure disclosed under paragraph (2)(d).]

(10) The [F21appropriate authority] or, as the case may be, the appropriate Minister shall take such steps as are considered appropriate to make a determination under this regulation available to the public.

(11) The applicant shall include a copy of any determination made under this regulation when he subsequently applies for, or for a variation of, an authorisation in relation to the project in question.

Environmental statement to be provided in relation to an application for authorisationU.K.

5.  [F27A written statement (an “environmental statement”)] which complies with regulation 6 shall be provided in relation to an application F28... for, or for the variation of, an authorisation in connection with a relevant project.

Environmental statement, and opinions of the [F29appropriate authority] on the contents of an environmental statementU.K.

6.[F30(1) The environmental statement shall be prepared by a competent person and shall—

(a)include—

(i)the information specified in paragraph (1A); and

(ii)any additional information which, taking into account current knowledge and methods of assessment, may reasonably be required by the appropriate authority to reach a conclusion about the likely significant environmental effects of the relevant project;

(b)be based on any opinion given under paragraph (2) in respect of the relevant project;

(c)take into account the results of any relevant UK environmental assessment which are reasonably available to the applicant; and

(d)state the relevant expertise and qualifications of the competent person.

(1A) The specified information is—

(a)a description of the relevant project comprising information on its site, design, size and other relevant features;

(b)a description of the likely significant effects of the relevant project on the environment;

(c)a description of the features of the relevant project or measures to avoid, prevent, reduce or offset any likely significant adverse effects of the relevant project on the environment;

(d)a description of the reasonable alternatives studied by the applicant, which are relevant to the relevant project and its specific characteristics, and an indication of the main reasons for the applicant’s choice, taking into account the environmental effects;

(e)a non-technical summary of the information referred to in sub-paragraphs (a) to (d); and

(f)any additional information referred to in Schedule 2 relevant to the specific characteristics of the relevant project and to the environmental features likely to be affected.]

(2) If a person so requests before making an application for, or for the variation of, an authorisation, the [F29appropriate authority] shall, having consulted the person making the request and the consultation bodies, give an opinion on the [F31scope and level of detail of] information which should be contained in an environmental statement accompanying such an application.

[F32(2A) The request for an opinion under paragraph (2) shall be in writing and include—

(a)a plan sufficient to identify the land;

(b)a brief description of the nature and purpose of the relevant project, including its location and technical capacity;

(c)an explanation of the likely significant effects of the relevant project on the environment; and

(d)any other information the person wishes to provide.]

(3) The fact that the [F29appropriate authority] has given an opinion under paragraph (2) shall not preclude it from subsequently requiring the person making the request to provide further information.

(4) The [F29appropriate authority] and [F33, if different,] the consultation bodies shall, if requested by a person proposing to make an application for which an environmental statement is required, enter into consultation with him to determine whether they have in their possession any information which may be relevant to the preparation of an environmental statement and, if they have, they shall make it available to him.

(5) Paragraph (4) shall not require the disclosure of information which is capable of being treated as confidential or must be so treated under [F34regulations 12(1) or 13(1) of the Environmental Information Regulations 2004] .

(6) Any body which provides information to a person under paragraph (4) may require him to pay a charge which reflects the cost of making that information available.

(7) If [F29appropriate authority] considers that an environmental statement does not contain all the information required by paragraph (1), it shall by notice in writing—

(a)inform the applicant, and

(b)specify what further information the [F29appropriate authority] requires,

and the applicant shall provide that information to the [F29appropriate authority].

[F35Publicity for environmental statement and related informationU.K.

7.(1) Where an environmental statement is provided in accordance with regulation 5 including where any further information is provided in accordance with regulation 6(7), the [F36appropriate authority] shall publish, on its website and in at least one newspaper circulating in the locality of the relevant project, a notice—

(a)stating—

(i)the applicant’s name;

(ii)that he has made an application to which these Regulations apply; and

(iii)that he has provided the[F36appropriate authority]with an environmental statement in accordance with regulation 5 and, where it is the case, that he has provided further information in accordance with regulation 6(7);

(b)stating a place and times where, during a period of [F37thirty] days beginning on the date on which the notice is published, copies of the application, the environmental statement, any information provided to the [F36appropriate authority] in response to its consultation under regulation 6(2), and any further information provided in accordance with regulation 6(7) may be inspected, and that such inspection is free of charge;

(c)specifying an address from which copies of the application, the environmental statement, any information provided to the [F36appropriate authority] in response to its consultation under regulation 6(2), and any further information provided in accordance with regulation 6(7) may be obtained from the [F36appropriate authority]and, if a charge is to be made for a copy, the amount (not exceeding a reasonable charge for copying) of the charge;

(d)specifying the other arrangements, if any, that have been made by the [F36appropriate authority] for informing the public of the application and for consulting them in relation to it; and

(e)stating that any person wishing to make representations in relation to the application should make them in writing addressed to the[F36appropriate authority] at an address specified in the notice within a period of [F38thirty] days beginning on the date on which the notice is published in accordance with this paragraph.

(2) The [F36appropriate authority] shall make available to the public as indicated in paragraphs (1)(b) and (c)—

(a)the application and the environmental statement provided in accordance with regulation 5; and

(b)any information provided to the [F36appropriate authority] in response to its consultation under regulation 6(2), or any further information provided in accordance with regulation 6(7), which was in the possession of the [F36appropriate authority] on the date on which the notice was published in accordance with paragraph (1).

(3) In relation to information which is relevant to the determination under regulation 8 and which becomes available to the [F36appropriate authority], whether as a result of a request by the[F36appropriate authority] or otherwise, after the date on which the notice was published in accordance with paragraph (1), the [F36appropriate authority] shall, on its website—

(a)state a place and times where, during a period of [F39thirty] days beginning on the day fourteen days after which the information becomes available to the [F36appropriate authority], a copy of the information may be inspected, and that inspection is free of charge; and

(b)specify an address from which a copy of the information may be obtained from the [F36appropriate authority]and, if a charge is to be made for a copy, the amount (not exceeding a reasonable charge for copying) of the charge.

(4) Not later than the date on which the notice in paragraph (1) is published, the[F36appropriate authority] shall send a copy of it and the environmental statement and any further information provided in accordance with regulation 6(7), to—

(a)the consultation bodies,

(b)the appropriate Minister, and

(c)such other persons as the appropriate Minister may direct,

under cover of a letter stating that any representations in relation to the application should be made in writing to the [F36appropriate authority] within a period of [F40thirty] days beginning on the date of the letter.

(5) A notice of an environmental statement under paragraph (1) may be combined with any notice required under any other enactment for the purpose of publicising the application in question.]

[F41Conclusion about environmental impactU.K.

7A.(1) The appropriate authority must consider (ensuring that in doing so it has or has access to any expertise it considers necessary)—

(a)the environmental statement;

(b)any further information given under regulation 6(3) or (7);

(c)any representations made under regulation 7(1)(e) or (4); and

(d)any features of the relevant project or measures to avoid, prevent, reduce or offset any likely significant adverse effects of the relevant project on the environment.

(2) Following that consideration, the appropriate authority must reach a conclusion about the likely significant effects (including the expected effects deriving from the vulnerability of the relevant project to risks of major accidents or disasters) of the relevant project on—

(a)population and human health;

(b)biodiversity, with particular attention to species and habitats protected under the Habitats Directive and the Wild Birds Directive;

(c)land, soil, water, air and climate;

(d)material assets, cultural heritage and the landscape;

(e)the interaction between the factors referred to in sub-paragraphs (a) to (d).]

Determination of application and notice of determinationU.K.

8.—(1) The [F36appropriate authority] shall not determine an application for, or for the variation of, an authorisation relating to a relevant project before the latest date allowed under these Regulations for making representations or concluding any consultation.

(2) In determining the application the [F36appropriate authority] shall take into consideration [F42(ensuring that in doing so it has, or has access to, any expertise it considers necessary)—

(a)the conclusion reached under regulation 7A(2);

(b)whether it is appropriate to require the applicant to monitor the significant adverse effects of the relevant project on the environment, and if so—

(i)whether the authorisation should contain provisions to ensure that the applicant is under such a duty; and

(ii)whether the authorisation should contain provisions to require remedial action to be taken in circumstances described in the authorisation; and

(c)whether, having regard to the likely significant environmental effects of the relevant project, the authorisation should contain provisions for any other purpose.]

[F43(2A) The appropriate authority may grant the authorisation only if satisfied that the conclusion reached under regulation 7A(2) in respect of the relevant project and the reasons for it address the likely significant environmental effects of the relevant project.]

[F44(3) Within a period of twenty-eight days beginning with the date of the determination of the application the appropriate authority shall—

(a)give notice in writing to the applicant and consultation bodies; and

(b)publish a notice on its website and in the newspaper or newspapers in which the notice was published under regulation 7(1),

stating that the appropriate authority has granted or refused the application and stating a place and times where any person may inspect the information referred to in paragraph (3A).

(3A) The information is—

(a)any relevant authorisation or variation;

(b)a document containing the determination and the reasons for it, including a summary of—

(i)the environmental statement;

(ii)the results of any representations the appropriate authority receives under regulation 7(1)(e) or (4); and

(iii)how the information referred to in sub-paragraphs (i) and (ii) has been taken into account;

(c)a description, where necessary, of any features of the relevant project or measures to avoid, reduce or offset any likely significant adverse effect of the relevant project on the environment; and

(d)information about any right to challenge the determination and the procedures for doing so.]

(4) No appeal shall be brought under section 43 of the 1991 Act (appeals to the Secretary of State) on the grounds that the [F36appropriate authority] has failed to give notice as required by subsection (1)(b) of that section before the expiry of a period of four months commencing with—

(a)the date on which an environmental statement is furnished in accordance with regulation 6(1), or

(b)the date on which any further information requested by the [F36appropriate authority] is provided in accordance with regulation 6(7),

whichever is the later.

PART IIIU.K.RELEVANT PROJECTS WHICH REQUIRE CONSENT UNDER THESE REGULATIONS

Restriction on abstracting or impounding waterU.K.

9.—(1) Subject to paragraphs (2) and (3), no person shall—

(a)begin a relevant project except in pursuance of a consent granted under regulation 10 by the [F36appropriate authority], or

(b)carry it out except in accordance with the provisions of that consent.

(2) Consent under regulation 10 is not needed in relation to a project if an abstraction or impounding licence is required.

(3) A person may rely on a consent granted under regulation 10 even though he is not the person to whom the consent was granted.

(4) A person who contravenes paragraph (1) shall be guilty of an offence and liable—

(a)on summary conviction, to a fine not exceeding the statutory maximum;

(b)on conviction on indictment, to a fine.

Textual Amendments

[F45Civil sanctionsE

9A.(1) The [F36appropriate authority] may impose a variable monetary penalty, restoration notice, compliance notice or stop notice, or accept an enforcement undertaking, in relation to an offence under regulation 9(4) as if it were an offence under a provision specified in relation to that sanction in Schedule 5 to the Environmental Civil Sanctions (England) Order 2010.

(2) The terms used in this regulation have the same meaning as in that Order.

(3) The provisions of that Order in relation to those sanctions apply as if they were provisions of these Regulations.

(4) This regulation applies only in England.]

The [F46appropriate authority's] decision on an application for consentU.K.

10.  On an application made in writing to the [F46appropriate authority] for a consent for the purposes of regulation 9, the [F46appropriate authority] may, subject to the requirements of Part II—

(a)grant a consent containing such provisions as it considers appropriate; or

(b)refuse consent,

taking into account any significant effects the relevant project is likely to have on the environment.

Textual Amendments

Appeals in relation to consentsU.K.

11.—(1) Subject to the following provisions of this regulation, where an application has been made to the [F46appropriate authority] for a consent under regulation 10, the applicant may by notice in writing appeal to the appropriate Minister if—

(a)the applicant is dissatisfied with the decision of the [F46appropriate authority] on the application; or

(b)the [F46appropriate authority] fails to give notice to the applicant of the [F46appropriate authority's] decision within a period of three months from the date of receipt of the application or within such extended period as may be agreed in writing between the applicant and the [F46appropriate authority].

(2) A notice of appeal under paragraph (1) shall be served within a period of twenty-eight days from—

(a)the date on which the decision to which it relates was notified to the applicant; or

(b)the end of the period referred to in paragraph (1)(b),

whichever is the later.

(3) The applicant shall serve a copy of the notice of appeal on the [F46appropriate authority] before the expiry of the period of twenty-eight days referred to in paragraph (2).

(4) Where any representations in writing with respect to the application were made within the period specified in accordance with [F47regulation 7(1)(e)] , the [F46appropriate authority] shall serve a copy of the notice of appeal on each of the persons who made those representations; and any person so served with a copy of the notice of appeal may make further representations to the appropriate Minister in writing within a period of twenty-one days from the date on which the copy of the notice is served on him.

(5) No appeal shall be brought by virtue of paragraph (1)(b) before the expiry of a period of four months commencing with—

(a)the date on which an environmental statement is furnished in accordance with regulation 6(1), or

(b)the date on which any further information requested by the [F46appropriate authority] is provided in accordance with regulation 6(7),

whichever is the later.

(6) The appropriate Minister—

(a)may allow or dismiss the appeal or reverse or vary any part of the decision of the [F46appropriate authority], whether the appeal relates to that part of the decision or not; and

(b)may deal with the application as if it had been made to the appropriate Minister in the first instance.

(7) Before determining the appeal, the appropriate Minister may—

(a)cause a local inquiry to be held; or

(b)afford to the applicant and the [F46appropriate authority] an opportunity of appearing before, and being heard by, a person appointed by the appropriate Minister for the purpose;

and the appropriate Minister shall act as mentioned in sub-paragraph (a) or (b) if so requested by the applicant or the [F46appropriate authority].

(8) Subsections (2) to (5) of section 250 of the Local Government Act 1972(5) (local inquiries, evidence and costs) apply in relation to inquiries or other hearings under this regulation as they apply to inquiries under that section, but as if—

(a)the references to the Minister were references to the appropriate Minister; and

(b)the reference in subsection (4) of that section to a local authority were a reference to the [F46appropriate authority].

(9) The appropriate Minister, in determining the appeal, shall take into account—

(a)any further representations in writing received by the appropriate Minister from the persons and within the period referred to in paragraph (4);

(b)the requirements of the applicant, in so far as they appear to the appropriate Minister to be reasonable requirements.

(10) Where the decision on the appeal is that a consent is to be granted, the decision shall include a direction to the [F46appropriate authority] to grant a consent containing such provisions as may be specified in the direction.

Validity of decisions of appropriate MinisterU.K.

12.—(1) Except as provided by the following provisions of this regulation, the validity of a decision of the appropriate Minister on any appeal under regulation 11 shall not be questioned in any legal proceedings whatsoever,

(2) If the [F46appropriate authority] or the applicant desires to question the validity of the decision of the appropriate Minister on the grounds—

(a)that the decision is not within the powers of these Regulations; or

(b)that any of the requirements of these Regulations which are applicable to the appeal have not been complied with,

the [F46appropriate authority] or, as the case may be, the applicant may, at any time within the period of six weeks beginning with the date on which the decision is made, make an application to the High Court under this regulation.

(3) On any application under paragraph (2), the High Court may by interim order suspend the operation of the decision to which the application relates until the final determination of the proceedings.

(4) If the High Court is satisfied, on an application under paragraph (2)—

(a)that the decision to which the application relates is not within the powers of these Regulations; or

(b)that the interests of the person making the application under this regulation have been substantially prejudiced by a failure to comply with any of the requirements mentioned in paragraph (2)(b) above,

the High Court may quash the decision.

Textual Amendments

PART IVU.K.MODIFICATION OF PART II FOR PARTICULAR CASES

Called-in applications in relation to abstraction or impounding licencesU.K.

13.  The provisions of regulations 6(7) [F48, 7A] and 8 shall apply in relation to any called-in application within the meaning of section 42 of the 1991 Act (consideration of called-in applications) as if any reference in those provisions to the [F46appropriate authority] were a reference to the appropriate Minister.

Variation of abstraction or impounding licence at instance of [F46appropriate authority] or Secretary of StateU.K.

14.—(1) Where proposals are formulated under section 52(1) of the 1991 Act (proposals for modification at the instance of the [F46appropriate authority] or Secretary of State) for the variation of an abstraction or impounding licence, the [F46appropriate authority] shall determine whether those proposals would amount to or form part of a relevant project; and in making that determination the [F46appropriate authority] shall take into account such of the selection criteria set out in Schedule 1 as are relevant.

(2) The [F46appropriate authority] shall give written notice of its determination to the licence holder and to the appropriate Minister.

(3) The appropriate Minister may review the determination of the [F46appropriate authority], by giving notice to the [F46appropriate authority] not later than four weeks after the receipt of a notice under paragraph (2); and where he does so, having taken into account such of the selection criteria set out in Schedule 1 as are relevant, he shall by notice in writing given to the licence holder and the [F46appropriate authority]

(a)uphold the determination of the [F46appropriate authority]; or

(b)substitute his own determination.

(4) The notice required by section 52(4) of the 1991 Act (notice of proposals formulated under that section)—

(a)in the case of a review under paragraph (3), shall not be served before notice is given to the [F46appropriate authority] under that paragraph; and

(b)shall include notice of the determination under this regulation.

Textual Amendments

Modifications where regulation 14 appliesU.K.

15.—(1) This regulation applies where it is determined under regulation 14 that the proposals would amount to or form part of a relevant project.

(2) The [F46appropriate authority] shall prepare an environmental statement in accordance with regulation 6(1).

(3) Regulations 6(2) to (7), 7 and 8 shall not apply.

(4) Section 52(4) to [F49(7)] (notice of proposals under that section) shall apply as if the environmental statement were part of the proposals formulated by the [F46appropriate authority] .

[F50(4A) Where a notice is published in accordance with section 52(4) of the 1991 Act in respect of proposals in relation to which this regulation applies, the notice shall specify any other arrangements that have been made for informing the public of the proposals and for consulting them in relation to them.]

(5) The [F46appropriate authority] shall, not later than the date of publication of the notice for the purposes of section 52(4) of the 1991 Act, send to the appropriate Minister and the consultation bodies a copy of the proposals and the environmental statement under cover of a letter stating that any representations on the proposals should be made in writing to the [F46appropriate authority]within a period of twenty-eight days beginning on the date of that notice.

(6) The [F46appropriate authority]or, as the case may be, the appropriate Minister shall not determine an application for, or for the variation of, an authorisation relating to a relevant project before the latest date allowed under these Regulations for making representations or concluding any consultation.

(7) In determining whether a licence should be varied, the [F46appropriate authority] or, as the case may be, the appropriate Minister shall have regard to the environmental statement and any representations relating to the environmental effects of the project made to the [F46appropriate authority] or the appropriate Minister within the period referred to in paragraph (5).

(8) Where a licence is varied in pursuance of proposals to which this regulation applies, the [F46appropriate authority] shall, within twenty-eight days of the variation, publish in those newspapers in which a notice was published under section 52(4) of the 1991 Act a notice stating that the [F46appropriate authority] has varied the licence, and stating a place where any person may inspect—

(a)the document by which the determination was made;

(b)written notice of the main reasons and considerations on which the determination is based [F51, and information about the public participation process that has taken place;]

(c)[F52where necessary,] a description of the main measures to avoid, reduce and if possible offset the major adverse effects of the project [F53; and]

[F54(d)information regarding any right to challenge the validity of the decision and the procedures for doing so.]

PART VU.K.REGISTERS [F55AND REVIEW]

Register of environmental statements and further informationU.K.

16.[F56(1)]  The Agency shall keep in the register maintained under section 189 of the 1991 Act (register of abstraction and impounding licences)—

[F57(a)any determination under regulation 4 or 14;

(b)any environmental statement or further information furnished under regulation 6;

(c)any documents, other than the environmental statement prepared in accordance with regulations 5 and 6, which have been provided to the [F46appropriate authority and are relevant to the determination under regulation 14; and

(d)any further information which is relevant to the determination under regulation 14 and which becomes available to the[F46appropriate authority] after the time that the public was given notice in accordance with section 52(4) of the 1991 Act.]

[F58(2) In respect of a determination under regulation 4, the information kept in the register shall include—

(a)the main reasons for the determination with reference to the relevant criteria listed in Schedule 1; and

(b)in the case of a determination that an environmental impact assessment is not required, any features of the relevant project or measures envisaged to avoid or prevent what might otherwise have been significant adverse effects on the environment.]

[F59ReviewU.K.

17.(1) In relation to England, the Secretary of State must, from time to time—

(a)carry out a review of the regulatory provision contained in these Regulations; and

(b)publish a report setting out the conclusions of the review.

(2) The first report must be published before 16th May 2022.

(3) Subsequent reports must be published at intervals not exceeding 5 years.

(4) Section 30(3) of the Small Business, Enterprise and Employment Act 2015 requires that a review carried out under this regulation must, so far as is reasonable, have regard to how the EIA Directive is implemented in other member States.

(5) Section 30(4) of the Small Business, Enterprise and Employment Act 2015 requires that a report published under this regulation must, in particular—

(a)set out the objectives intended to be achieved by the regulatory provision referred to in paragraph (1)(a);

(b)assess the extent to which those objectives are achieved;

(c)assess whether those objectives remain appropriate; and

(d)if those objectives remain appropriate, assess the extent to which they could be achieved in another way which involves less onerous regulatory provision.

(6) In this regulation, “regulatory provision” has the same meaning as in sections 28 to 32 of the Small Business, Enterprise and Employment Act 2015 (see section 32 of that Act).]

Signed by authority of the Secretary of State

Elliot Morley

Parliamentary Under-Secretary of State,

Department for Environment, Food and Rural Affairs]

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Impact Assessments

Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:

  • Why the government is proposing to intervene;
  • The main options the government is considering, and which one is preferred;
  • How and to what extent new policies may impact on them; and,
  • The estimated costs and benefits of proposed measures.
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources