- Latest available (Revised)
- Original (As made)
There are multiple versions of this provision on screen. These apply to different geographical extents.
The term provision is used to describe a definable element in a piece of legislation that has legislative effect – such as a Part, Chapter or section.
Sometimes the text of a provision is changed, but the change(s) only apply to a particular geographical area. In some limited cases where this happens, the editorial team create a version for each different geographical area. Multiple versions are only created in this way where the change in question is a substitution so that there are different versions of the text for the different extents. Insertions and repeals of text do not give rise to such multiple versions.
There are currently no known outstanding effects for the The Building Regulations 2010, Section 41.
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
41.—(1) Subject to paragraph (4) below, this regulation applies to—
(a)building work in relation to which paragraph E1 of Schedule 1 imposes a requirement; and
(b)work which is required to be carried out to a building to ensure that it complies with paragraph E1 of Schedule 1 by virtue of regulation 6(1)(f) or 6(2)(b).
(2) Where this regulation applies, the person carrying out the work shall, for the purpose of ensuring compliance with paragraph E1 of Schedule 1—
(a)ensure that appropriate sound insulation testing is carried out in accordance with a procedure approved by the Secretary of State; and
(b)give a copy of the results of the testing referred to in sub-paragraph (a) to the [F1building control authority].
(3) The results of the testing referred to in paragraph (2)(a) shall be—
(a)recorded in a manner approved by the Secretary of State; and
[F2(b)given—
(i)in the case where the building work is higher-risk building work, to the regulator with the application for a completion certificate in relation to the work;
(ii)in any other case, to the building control authority not later than the date on which the notice required by regulation 16(4) is given.]
[F3(3A) Where the regulator is the building control authority by virtue of section 91ZB of the Act (the regulator: building control authority for other work), it must send a copy of [F4the results of the testing] it receives under this regulation in relation to a building to the local authority for the area in which the building is situated.]
(4) [F5Where building work consists of the erection of a dwelling-house or a building containing flats, this regulation does not apply to any part of the building in relation to which the person carrying out the building work notifies the building control authority—
(i)in the case of building work which is higher-risk building work, not later than the date on which the application for building control approval for the work is submitted,
(ii)in any other case, not later than the date on which notice of intention to start work is given under regulation 16(1),
that, for the purposes of achieving compliance of the work with paragraph E1 of Schedule 1, the person is using one or more design details approved by Robust Details Limited, provided that—]
(a)the notification specifies—
(i)the part or parts of the building in respect of which the person is using the design detail;
(ii)the design detail concerned; and
(iii)the unique number issued by Robust Details Limited in respect of the specified use of that design detail; and
(b)the building work carried out in respect of the part or parts of the building identified in the notification is in accordance with the design detail specified in the notification.
Extent Information
E1This version of this provision applies to England only; a separate version has been created for Wales only
Textual Amendments
F1Words in reg. 41(2)(b) (E.) substituted (1.10.2023) by The Building Regulations etc. (Amendment) (England) Regulations 2023 (S.I. 2023/911), regs. 1(2), 7(16)(a) (with regs. 22-24)
F2Reg. 41(3)(b) substituted (E.) (1.10.2023) by The Building Regulations etc. (Amendment) (England) Regulations 2023 (S.I. 2023/911), regs. 1(2), 7(16)(b) (with regs. 22-24)
F3Reg. 41(3A) inserted (E.) (1.10.2023) by The Building Regulations etc. (Amendment) (England) Regulations 2023 (S.I. 2023/911), regs. 1(2), 7(16)(c) (with regs. 22-24)
F4Words in reg. 41(3A) substituted (6.4.2024) by The Building (Registered Building Control Approvers etc.) (England) Regulations 2024 (S.I. 2024/110), regs. 1(3), 38(5)
F5Words in reg. 41(4) substituted (E.) (1.10.2023) by The Building Regulations etc. (Amendment) (England) Regulations 2023 (S.I. 2023/911), regs. 1(2), 7(16)(d) (with regs. 22-24)
Modifications etc. (not altering text)
C1Reg. 41 modified (1.10.2010) by The Building (Approved Inspectors etc.) Regulations 2010 (S.I. 2010/2215), regs. 1, 20(5) (as amended (1.10.2023) by S.I. 2023/906, regs. 1(2), 13(1)(d))
C2Reg. 41 applied (with modifications) (1.10.2010) by The Building (Approved Inspectors etc.) Regulations 2010 (S.I. 2010/2215), regs. 1, 20(1)(5)
C3Reg. 41 modified (E.) (6.4.2024) by The Building (Registered Building Control Approvers etc.) (England) Regulations 2024 (S.I. 2024/110), regs. 1(3), 5(9) (with regs. 44-47)
41.—(1) Subject to paragraph (4) below, this regulation applies to—
(a)building work in relation to which paragraph E1 of Schedule 1 imposes a requirement; and
(b)work which is required to be carried out to a building to ensure that it complies with paragraph E1 of Schedule 1 by virtue of regulation 6(1)(f) or 6(2)(b).
(2) Where this regulation applies, the person carrying out the work shall, for the purpose of ensuring compliance with paragraph E1 of Schedule 1—
(a)ensure that appropriate sound insulation testing is carried out in accordance with a procedure approved by the Secretary of State; and
(b)give a copy of the results of the testing referred to in sub-paragraph (a) to the local authority.
(3) The results of the testing referred to in paragraph (2)(a) shall be—
(a)recorded in a manner approved by the Secretary of State; and
(b)given to the local authority in accordance with paragraph (2)(b) not later than the date on which the notice required by regulation 16(4) is given.
(4) Where building work consists of the erection of a dwelling-house or a building containing flats, this regulation does not apply to any part of the building in relation to which the person carrying out the building work notifies the local authority, not later than the date on which notice of commencement of the work is given under regulation 16(1), that, for the purpose of achieving compliance of the work with paragraph E1 of Schedule 1, the person is using one or more design details approved by Robust Details Limited, provided that—
(a)the notification specifies—
(i)the part or parts of the building in respect of which the person is using the design detail;
(ii)the design detail concerned; and
(iii)the unique number issued by Robust Details Limited in respect of the specified use of that design detail; and
(b)the building work carried out in respect of the part or parts of the building identified in the notification is in accordance with the design detail specified in the notification.
Extent Information
E2This version of this provision applies to Wales only; a separate version has been created for England only
Modifications etc. (not altering text)
C4Reg. 41 applied (with modifications) (1.10.2010) by The Building (Approved Inspectors etc.) Regulations 2010 (S.I. 2010/2215), regs. 1, 20(1)(5) (as amended as amended (W.) (25.4.2024) by S.I. 2024/447, regs. 1(1), 3(h)(i) (with reg. 6))
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: