The Building Regulations 2010

Sound insulation testingE

This section has no associated Explanatory Memorandum

41.—(1) Subject to paragraph (4) below, this regulation applies to—

(a)building work in relation to which paragraph E1 of Schedule 1 imposes a requirement; and

(b)work which is required to be carried out to a building to ensure that it complies with paragraph E1 of Schedule 1 by virtue of regulation 6(1)(f) or 6(2)(b).

(2) Where this regulation applies, the person carrying out the work shall, for the purpose of ensuring compliance with paragraph E1 of Schedule 1—

(a)ensure that appropriate sound insulation testing is carried out in accordance with a procedure approved by the Secretary of State; and

(b)give a copy of the results of the testing referred to in sub-paragraph (a) to the [F1building control authority].

(3) The results of the testing referred to in paragraph (2)(a) shall be—

(a)recorded in a manner approved by the Secretary of State; and

[F2(b)given—

(i)in the case where the building work is higher-risk building work, to the regulator with the application for a completion certificate in relation to the work;

(ii)in any other case, to the building control authority not later than the date on which the notice required by regulation 16(4) is given.]

[F3(3A) Where the regulator is the building control authority by virtue of section 91ZB of the Act (the regulator: building control authority for other work), it must send a copy of [F4the results of the testing] it receives under this regulation in relation to a building to the local authority for the area in which the building is situated.]

(4) [F5Where building work consists of the erection of a dwelling-house or a building containing flats, this regulation does not apply to any part of the building in relation to which the person carrying out the building work notifies the building control authority—

(i)in the case of building work which is higher-risk building work, not later than the date on which the application for building control approval for the work is submitted,

(ii)in any other case, not later than the date on which notice of intention to start work is given under regulation 16(1),

that, for the purposes of achieving compliance of the work with paragraph E1 of Schedule 1, the person is using one or more design details approved by Robust Details Limited, provided that—]

(a)the notification specifies—

(i)the part or parts of the building in respect of which the person is using the design detail;

(ii)the design detail concerned; and

(iii)the unique number issued by Robust Details Limited in respect of the specified use of that design detail; and

(b)the building work carried out in respect of the part or parts of the building identified in the notification is in accordance with the design detail specified in the notification.

Extent Information

E1This version of this provision applies to England only; a separate version has been created for Wales only

Textual Amendments

Modifications etc. (not altering text)

Sound insulation testingW

41.—(1) Subject to paragraph (4) below, this regulation applies to—

(a)building work in relation to which paragraph E1 of Schedule 1 imposes a requirement; and

(b)work which is required to be carried out to a building to ensure that it complies with paragraph E1 of Schedule 1 by virtue of regulation 6(1)(f) or 6(2)(b).

(2) Where this regulation applies, the person carrying out the work shall, for the purpose of ensuring compliance with paragraph E1 of Schedule 1—

(a)ensure that appropriate sound insulation testing is carried out in accordance with a procedure approved by the Secretary of State; and

(b)give a copy of the results of the testing referred to in sub-paragraph (a) to the local authority.

(3) The results of the testing referred to in paragraph (2)(a) shall be—

(a)recorded in a manner approved by the Secretary of State; and

(b)given to the local authority in accordance with paragraph (2)(b) not later than the date on which the notice required by regulation 16(4) is given.

(4) Where building work consists of the erection of a dwelling-house or a building containing flats, this regulation does not apply to any part of the building in relation to which the person carrying out the building work notifies the local authority, not later than the date on which notice of commencement of the work is given under regulation 16(1), that, for the purpose of achieving compliance of the work with paragraph E1 of Schedule 1, the person is using one or more design details approved by Robust Details Limited, provided that—

(a)the notification specifies—

(i)the part or parts of the building in respect of which the person is using the design detail;

(ii)the design detail concerned; and

(iii)the unique number issued by Robust Details Limited in respect of the specified use of that design detail; and

(b)the building work carried out in respect of the part or parts of the building identified in the notification is in accordance with the design detail specified in the notification.

Extent Information

E2This version of this provision applies to Wales only; a separate version has been created for England only

Modifications etc. (not altering text)

C4Reg. 41 applied (with modifications) (1.10.2010) by The Building (Approved Inspectors etc.) Regulations 2010 (S.I. 2010/2215), regs. 1, 20(1)(5) (as amended as amended (W.) (25.4.2024) by S.I. 2024/447, regs. 1(1), 3(h)(i) (with reg. 6))