17.—(1) Before completing the reconstruction of bridge 404 over the River Gipping, Network Rail must, after consultation with the highway authority, submit to the relevant planning authority for approval a street lighting scheme for the footpath under bridge 404.
(2) Network Rail must implement the approved street lighting scheme.
(3) Upon completion of the reconstruction of bridge 404, Network Rail must transfer ownership of the installed lighting equipment to the highway authority.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: