18.—(1) Subject to paragraph (2), Network Rail must not stop up the footpath and cycleway on the north bank of the River Gipping until the temporary structure referred to in paragraph (j) of Part 1 of this Schedule (“the temporary structure”) is available for use by the public.
(2) Network Rail is not obliged to comply with paragraph (1) in circumstances where it considers that for reasons of health and safety compliance is not practically possible.
(3) Before submitting plans of the temporary structure to the Environment Agency in accordance with Part 3 of Schedule 7 (protective provisions), Network Rail must consult the highway authority.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: