- Latest available (Revised)
- Point in Time (28/06/2013)
- Original (As made)
Version Superseded: 18/04/2016
Point in time view as at 28/06/2013.
There are currently no known outstanding effects for the The Water Industry (Specified Infrastructure Projects) (English Undertakers) Regulations 2013, SCHEDULE 2.
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
Regulation 6
Provision applied | Modification |
---|---|
regulation 2 (interpretation) and Schedules 2 (activities constituting works) and 4 (extension to non-member States). | These provisions apply only to the extent that they are relevant to the provisions referred to in this Schedule. |
regulation 4 and Schedule 4 (extension to non-member States). | |
regulation 12 (technical specifications in contract documents). | |
regulation 13 (variants). | |
regulation 14 (the open, restricted and negotiated procedures). | |
regulation 16 (call for competition). | Paragraphs (2)(a)(i), (3) and (4) do not apply. |
regulation 17 (award without call for competition). | Only paragraph (1)(i) applies. |
regulation 18 (framework agreements). | |
regulation 21 (central purchasing bodies). | |
regulation 22 (time limits). | Paragraph (3) does not apply. |
regulation 23 (general provisions in relation to qualification and selection of economic operators). | |
regulation 24 (mutual recognition concerning administrative, technical or financial conditions). | |
regulation 25 (qualification systems). | |
regulation 26 (criteria for rejection of economic operators). | The incumbent undertaker is bound by paragraph (1) as if it were a contracting authority. Paragraph (3) does not apply. |
regulation 27 (criteria for selection of economic operators). | |
regulation 28 (consortia). | Paragraph (2) applies as if the references to being admitted to a dynamic purchasing system were omitted. |
regulation 29 (corporations). | Paragraph (1) applies as if the reference to being admitted to a dynamic purchasing system were omitted. |
regulation 29A (notification). | Paragraph (4) does not apply. |
regulation 30 (criteria for the award of a contract). | Paragraph (9) applies as if the reference to “the Minister” were a reference to “the Secretary of State” and as if the words “for onward transmission to the Commission” were omitted. |
regulation 33 (information about contract award procedures). | Paragraph (6A) does not apply; paragraph (7) applies as if “or a dynamic purchasing system” were omitted; paragraph (9) applies as if sub-paragraph (b)(ii) were omitted; paragraph (11) applies as if sub-paragraph (b) were omitted; and paragraph (15) applies as if the words after “expired” in sub-paragraph (b)(ii) were omitted. |
regulation 33A (standstill period). | |
regulation 35 (obligations relating to taxes, environmental protection, employment protection and working conditions). | |
regulation 36 (conditions for performance of contracts). | |
regulation 37 (preservation of records). | Paragraphs (1)(b) and (2) do not apply |
regulation 40 (publication of notices). | Paragraphs (5) and (7) do not apply. |
regulation 41 (confidentiality of information). | |
regulation 42 (means of communication). | |
regulation 43 (sub-contracting). | |
Part 9 (applications to the Court) |
45.—(1) The obligation on an incumbent undertaker to comply with the provisions of these Regulations, other than regulation 30(9), is a duty owed to an economic operator.
(2) A breach of the duty owed in accordance with paragraph (1) is actionable by any economic operator which in consequence suffers, or risks suffering, loss or damage and those proceedings shall be in the High Court.
(3) Subject to paragraphs (4) to (6), such proceedings must be started within 30 days beginning with the date on which the economic operator first knew or ought to have known that grounds for starting proceedings had arisen.
(4) Paragraph (3) does not require proceedings to be started before the end of any of the following periods—
(a)where the proceedings relate to a decision which is sent to the economic operator by facsimile or electronic means, 10 days beginning with—
(i)the day after the date on which the decision is sent, if the decision is accompanied by a summary of the reasons for the decision; or
(ii)if the decision is not so accompanied, the day after the date on which the economic operator is informed of a summary of those reasons;
(b)where the proceedings relate to a decision which is sent to the economic operator by other means, whichever of the following periods ends first—
(i)15 days beginning with the day after the date on which the decision is sent, if the decision is accompanied by a summary of the reasons for the decision; or
(ii)10 days beginning with—
(aa)the day after the date on which the decision is received, if the decision is accompanied by a summary of the reasons for the decision; or
(bb)if the decision is not so accompanied, the day after the date on which the economic operator is informed of a summary of those reasons; and
(c)where sub-paragraphs (a) and (b) do not apply but the decision is published, 10 days beginning with the day on which the decision is published.
(5) Subject to paragraph (6), the Court may extend the time limit imposed by paragraph (3) where the Court considers that there is good reason for doing so.
(6) The Court must not exercise its power under paragraph (5) so as to permit proceedings to be started more than 3 months after the date when the economic operator first knew or ought to have known that grounds for starting the proceedings had arisen.
(7) For the purposes of this regulation, proceedings are to be regarded as started when the claim form is issued.
(8) Subject to paragraph (9), but otherwise without prejudice to any other powers of the Court in proceedings brought under this regulation, the Court may—
(a)by interim order—
(i)suspend the procedure leading to the award of the contract or the procedure leading to the determination of a design contest in relation to the award of a contract of which the breach of duty owed in accordance with paragraph (1) is alleged; or
(ii)suspend the implementation of any decision or action taken by the incumbent undertaker in the course of following such a procedure; and
(b)if satisfied that a decision or action taken by an incumbent undertaker was a breach of the duty owed in accordance with paragraph (1)—
(i)order the setting aside of that decision or action, or order the incumbent undertaker to amend any document;
(ii)award damages to an economic operator which has suffered loss or damage as a consequence of the breach; or
(iii)do both of those things.
(9) In proceedings under this regulation the Court does not have power to order any remedy other than an award of damages in respect of a breach of the duty owed in accordance with paragraph (1) if the contract in relation to which the breach occurred has been entered into.
(10) Where, in proceedings under this regulation, the Court is satisfied that an economic operator would have had a real chance of being awarded a contract or winning a design contest if that chance had not been adversely affected by a breach of the duty owed to it by the incumbent undertaker in accordance with paragraph (1), the economic operator shall be entitled to damages amounting to its costs in preparing its tender and in participating in the procedure leading to the award of the contract or its costs of participating in the procedure leading to the determination of the design contest.
(11) Paragraph (10) does not affect a claim by an economic operator that it has suffered other loss or damage or that it is entitled to relief other than damages, and is without prejudice to the matters on which an economic operator may be required to satisfy the Court in respect of any other such claim.”
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: