4.Procedure in relation to approvals etc. under requirements
19.Time limit for exercise of authority to acquire land compulsorily
21.Application of the Compulsory Purchase (Vesting Declarations) Act 1981
25.Temporary use of land for carrying out the authorised development
26.Temporary use of land for maintaining authorised development
AUTHORISED DEVELOPMENT AND REQUIREMENTS
6.(1) The authorised development must be carried out in accordance...
17.Control of noise during construction and operational phase
19.(1) No part of the authorised development may commence until...
21.Except in an emergency, the undertaker must give at least...
22.So far as reasonably practicable, steam purging may only take...
23.(1) Prior to the commencement of construction for the building...
34.(1) Work No. 2 must not be commercially operated until...
PROTECTION OF NETWORK RAIL INFRASTRUCTURE LIMITED
1.The following provisions of this Schedule shall have effect unless...
2.In this Schedule— “construction” includes execution, placing, alteration and reconstruction...
3.(1) Where under this Schedule Network Rail is required to...
4.(1) The undertaker shall not exercise the powers conferred by...
5.(1) The undertaker shall before commencing construction of any specified...
7.The undertaker shall— (a) at all times afford reasonable facilities...
8.Network Rail shall at all times afford reasonable facilities to...
9.(1) If any permanent or temporary alterations or additions to...
10.The undertaker shall repay to Network Rail all reasonable fees,...
11.(1) In this paragraph— “EMI” means, subject to sub-paragraph (2),...
13.The undertaker shall not provide any illumination or illuminated sign...
14.Any additional expenses which Network Rail may reasonably incur in...
15.(1) The undertaker shall pay to Network Rail all reasonable...
18.The undertaker and Network Rail may, subject in the case...
19.Nothing in this Order, or in any enactment incorporated with...
20.The undertaker shall give written notice to Network Rail where...