32.—(1) The authorised development must not be commissioned until a written operational traffic routing and management plan has been submitted to and, after consultation with the relevant highway authorities, approved by the planning authority.
(2) The plan submitted and approved must be in accordance with the principles set out in chapter 7 of the environmental statement and the operational travel plan framework contained in Appendix 7C to the environmental statement.
(3) The plan submitted and approved must include details of the routes to be used for the transport of fuel, consumables and combustion by-products to and from the authorised development.
(4) The plan must be implemented as approved.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: