Search Legislation

The Electricity (Connection Standards of Performance) Regulations 2015

 Help about what version

What Version

 Help about advanced features

Advanced Features

Changes over time for: The Electricity (Connection Standards of Performance) Regulations 2015 (Schedules only)

 Help about opening options

Alternative versions:

Changes to legislation:

There are outstanding changes not yet made by the legislation.gov.uk editorial team to The Electricity (Connection Standards of Performance) Regulations 2015. Any changes that have already been made by the team appear in the content and are referenced with annotations. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the legislation in the affected provisions. Use the ‘more’ link to open the changes and effects relevant to the provision you are viewing.

View outstanding changes

Changes and effects yet to be applied to :

Changes and effects yet to be applied to the whole Instrument associated Parts and Chapters:

Whole provisions yet to be inserted into this Instrument (including any effects on those provisions):

Regulation 2(1)

SCHEDULE 1E+W+SData for the Purpose of Calculating Payments

Prescribed periods and prescribed sums applicable to all electricity distributorsE+W+S

(1)

Regulation

(2)

Prescribed Period

(3)

Prescribed Sum

(4)

Payment Date

4(2)10 working days£65

the working day on which the budget estimate should have been dispatched

4(3)20 working days£65

the working day on which the budget estimate should have been dispatched

5(2)5 working days

£15 for each working day after the end of the prescribed period up to and including the day on which the quotation is dispatched

the working day on which the quotation is dispatched
5(3)15 working days

£15 for each working day after the end of the prescribed period up to and including the day on which the quotation is dispatched

the working day on which the quotation is dispatched
6(2)25 working days

£65 for each working day after the end of the prescribed period up to and including the day on which the quotation is dispatched

the working day on which the quotation is dispatched
6(3)35 working days

£135 for each working day after the end of the prescribed period up to and including the day on which the quotation is dispatched

the working day on which the quotation is dispatched
6(4)65 working days

£200 for each working day after the end of the prescribed period up to and including the day on which the quotation is dispatched

the working day on which the quotation is dispatched
7(3)not applicable£335

the working day on which the quotation is found, in accordance with the quotation accuracy scheme, to have been inaccurate or incomplete

7(4)not applicable£670

the working day on which the quotation is found, in accordance with the quotation accuracy scheme, to have been inaccurate or incomplete

8(2)7 working days

£15 for each working day after the end of the prescribed period up to and including the day on which contact occurs

the working day on which contact occurs
8(3)the agreed date

£35 for each working day after the agreed date up to and including the day on which the works are completed

the working day on which the works are completed
9(2)7 working days

£65 for each working day after the end of the prescribed period up to and including the day on which contact occurs

the working day on which contact occurs
9(3)10 working days£135 for each working day after the end of the prescribed period up to and including the day on which contact occursthe working day on which contact occurs
9(4)15 working days

£200 for each working day after the end of the prescribed period up to and including the day on which contact occurs

the working day on which contact occurs
9(5)the agreed date

£25 for each working day after the agreed date up to and including the day on which the works at the premises are commenced

the working day on which the works at the premises are commenced
9(6)the agreed date

£135 for each working day after the agreed date up to and including the day on which the works are completed

the working day on which the works are completed
9(7)the agreed date

£200 for each working day after the agreed date up to and including the day on which the works are completed

the working day on which the works are completed
9(8)the agreed date

£270 for each working day after the agreed date up to and including the day on which the works are completed

the working day on which the works are completed
9(9)the agreed date

£135 for each working day after the agreed date up to and including the day on which energisation occurs

the working day on which energisation occurs
9(10)the agreed date

£200 for each working day after the agreed date up to and including the day on which energisation occurs

the working day on which energisation occurs
9(11)the agreed date

£270 for each working day after the agreed date up to and including the day on which energisation occurs

the working day on which energisation occurs
10(2)2 hours£65

the working day after the day on which the emergency attendance should have taken place

10(3)2 calendar days

£15 for each working day after the end of the prescribed period up to and including the day on which the fault rectification works are completed

the working day on which the fault rectification works are completed
10(4)10 working days

£15 for each working day after the end of the prescribed period up to and including the day on which the fault rectification works are completed

the working day on which the fault rectification works are completed
10(5)20 working days

£15 for each working day after the end of the prescribed period up to and including the day on which the fault rectification works are completed

the working day on which the fault rectification works are completed
10(6)25 working days

£15 for each working day after the end of the prescribed period up to and including the day on which the fault rectification works are completed

the working day on which the fault rectification works are completed
11(2)25 working days

£15 for each working day after the end of the prescribed period up to and including the day the quotation is dispatched

the working day on which the quotation is dispatched
12(2)the agreed date

£15 for each working day after the agreed date up to and including the day on which the works are completed

the working day on which the works are completed
12(3)35 working days

£15 for each working day after the end of the prescribed period up to and including the day on which the works are completed

the working day on which the works are completed
14(1)10 working days£65not applicable

Regulation 13

SCHEDULE 2E+W+SPractice and Procedure for Determinations

Determination of disputesE+W+S

1.—(1) This Schedule applies where a dispute to which regulation 13 applies has arisen under any provision of these Regulations between an electricity distributor and a customer or relevant authority (as applicable).E+W+S

(2) A dispute to which this Schedule applies—

(a)may be referred to the Authority by any party or, with the agreement of any party, by a consumer advocacy body; and

(b)on such reference, is to be determined by order made by the Authority.

(3) In making an order under this Schedule, the Authority must include in the order the reasons for reaching its decision with respect to a dispute.

Commencement Information

I1Sch. 2 para. 1 in force at 1.4.2015, see reg. 1(1)

Timetable for the determination of individual disputesE+W+S

2.—(1) The Authority must determine a dispute to which this Schedule applies before the end of eighty working days from the date when the dispute was referred to the Authority.E+W+S

(2) If the Authority is satisfied that there are good reasons for departing from the requirements of sub-paragraph (1), the period in which a dispute may be determined may be extended with the consent of the referring party or parties.

Commencement Information

I2Sch. 2 para. 2 in force at 1.4.2015, see reg. 1(1)

Procedure for the determination of individual disputesE+W+S

3.—(1) Where an individual dispute is referred to the Authority, the Authority must, at the outset, send to the parties a notice of procedure for the determination of individual disputes.E+W+S

(2) The notice under sub-paragraph (1) must—

(a)set out a timetable by which each part of the procedure for the determination of individual disputes under this Schedule is to take place;

(b)provide a list of any documentation or other evidence that the Authority has received in connection with the dispute and inform the parties that such documentation or other evidence may be disclosed to other parties to the dispute unless it is specifically classed as confidential by the party to whom it belongs before the date expressly stated in the notice;

(c)inform the parties of any specific information that the Authority is requesting as part of the written statement prepared in accordance with paragraph 7; and

(d)explain the manner in which the Authority intends to publish the determination decision.

(3) Upon receipt of a notice under sub-paragraph (1), the parties to the dispute must provide the Authority with—

(a)the information specified in sub-paragraph (2)(c);

(b)any other information that they consider relevant to the dispute.

(4) If the Authority decides it is necessary to obtain third party advice in relation to technical issues or any other issues that may arise during the determination, it must inform the parties to the dispute of its request for such advice and indicate to them in writing how that request will affect the timetable outlined in the notice issued under sub-paragraph (1).

(5) At any time after receiving a written statement the Authority may, if it considers it appropriate to do so, request an oral hearing in accordance with paragraph 9.

(6) If the Authority is satisfied that it has sufficient information to determine a dispute, it must prepare a draft determination statement containing the submissions of the parties and then send that statement to the parties for comment.

(7) When the Authority has received comments from the parties, and is satisfied that it has sufficient information to make the determination decision, it must prepare and then issue to the parties a final determination statement.

(8) The parties must, within one week of receiving a final determination statement, notify the Authority of any issue or information within that statement that should be excluded because such issue or information is of a confidential nature.

(9) The Authority shall, upon receipt of any notification under sub-paragraph (8), make the necessary adjustments to the final determination statement and then publish that statement on its website in accordance with sub-paragraph (2)(d).

Commencement Information

I3Sch. 2 para. 3 in force at 1.4.2015, see reg. 1(1)

Determination of multiple disputesE+W+S

4.—(1) The Authority may, if it considers it appropriate to do so, consolidate into one or more categories (in each case a “consolidated group”) similar or related disputes for the purposes of determining those disputes.E+W+S

(2) A determination made by the Authority for one or more consolidated groups must apply, in respect of each consolidated group, to each individual dispute within that group.

Commencement Information

I4Sch. 2 para. 4 in force at 1.4.2015, see reg. 1(1)

Timetable for determination of multiple disputesE+W+S

5.—(1) The Authority, when determining disputes falling within a consolidated group, must determine those disputes before the end of six months from the date when they were consolidated into that group by the Authority under paragraph 4.E+W+S

(2) If the Authority is satisfied that there are good reasons for departing from the requirements of sub-paragraph (1), the period in which disputes falling within a consolidated group may be determined may be extended by notice to the representatives of any such group nominated under paragraph 10.

Commencement Information

I5Sch. 2 para. 5 in force at 1.4.2015, see reg. 1(1)

Procedure for the determination of multiple disputesE+W+S

6.—(1) Where the Authority considers it appropriate to consolidate disputes under paragraph 4, it must send to the parties a notice of procedure for the determination of those disputes.E+W+S

(2) The notices under sub-paragraph (1) must—

(a)set out a timetable by which each part of the procedure for the determination of multiple disputes under this Schedule is to take place;

(b)provide a list of any documentation or other evidence that the Authority has received in connection with the dispute and inform the parties that such documentation or other evidence may be disclosed to other parties to the dispute unless it is specifically classed as confidential by the party to whom it belongs before the date expressly stated in the notice;

(c)inform the parties of any specific information that the Authority is requesting in accordance with paragraph 11; and

(d)explain the manner in which the Authority intends to publish the determination decision.

(3) Upon receipt of a notice under sub-paragraph (1), the parties to the dispute must provide the Authority with—

(a)the information specified in sub-paragraph (2)(c); and

(b)any other information that they consider relevant to the dispute.

(4) Upon receipt of the information provided in accordance with sub-paragraph (3), the Authority may, if it considers it fitting to do so, prepare a list of consolidated groups and then consult as to whether those consolidated groups are appropriate.

(5) When consulting under sub-paragraph (4), the Authority must—

(a)publish and explain its proposals in a manner which it believes will bring them to the attention of persons most likely to be affected; and

(b)invite those persons to comment to the Authority within a period of time specified in the publication of the proposals.

(6) Upon receipt of responses to the consultation under sub-paragraph (5), the Authority must have regard to those responses before finalising the consolidated groups.

(7) When the Authority has decided on the consolidated groups for the purpose of determining multiple disputes, it must appoint customer representatives as required by paragraph 10.

(8) Following the appointment of the customer representatives for the consolidated groups, those customer representatives and the electricity distributors must prepare a written statement.

(9) Upon receipt of the written statements, the Authority may decide that it is necessary to obtain third party advice in relation to technical issues or any other issues that may arise during the determination. If third party advice is requested, then the Authority must inform the customer representatives and the electricity distributors of that request and indicate in writing how this request will affect the timetable outlined in the notice issued under sub-paragraph (1).

(10) At any time after receiving the written statement the Authority may request an oral hearing in accordance with paragraph 9.

(11) If the Authority is satisfied that it has the necessary information, it must prepare a draft determination statement containing the submissions of the customer representatives and the electricity distributors and then send that statement to the customer representatives and the electricity distributors for comment.

(12) When the Authority has received comments from the customer representatives and the electricity distributors, and is satisfied that it has sufficient information to make the determination decision, it must issue a final determination statement for a consolidated group or for each consolidated group where there is more than one.

(13) The customer representatives and the electricity distributors must within one week of receiving a final determination statement notify the Authority of any issue or information within that statement that should be excluded because it is of a confidential nature.

(14) The Authority must, upon receipt of any notification under sub-paragraph (13), make the necessary adjustments to the final determination statement and then publish that statement on its website in accordance with sub-paragraph (2)(d).

Commencement Information

I6Sch. 2 para. 6 in force at 1.4.2015, see reg. 1(1)

Written statementsE+W+S

7.—(1) The Authority may, by notice, ask any party to a dispute to produce a written statement with respect to a matter specified in the notice.E+W+S

(2) The power to ask for the production of a written statement includes power to specify the time and place at which it is to be produced.

(3) No person is to be compelled under this paragraph to produce a written statement with respect to any matter about which he could not be compelled to give evidence in civil proceedings in the High Court or Court of Session.

(4) The Authority may make copies of a document produced to it under this paragraph.

Commencement Information

I7Sch. 2 para. 7 in force at 1.4.2015, see reg. 1(1)

Production of documents and other evidenceE+W+S

8.—(1) The Authority may, by notice, ask a party to a dispute to produce such documentation (including other evidence), in such form and at such time as it directs, as the Authority may reasonably require to enable it to make the determination decision.E+W+S

(2) The power to ask for the production of a document is a power to ask for its production—

(a)at the time and place specified in the notice; and

(b)in a legible form.

(3) No person is to be compelled under this paragraph to produce a document that he could not be compelled to produce in civil proceedings in the High Court or Court of Session.

(4) The Authority may make copies of a document produced to it under this paragraph.

Commencement Information

I8Sch. 2 para. 8 in force at 1.4.2015, see reg. 1(1)

Oral hearingsE+W+S

9.—(1) For the purposes of this Schedule, an oral hearing may be held, and evidence may be heard at such a hearing from any party to a dispute.E+W+S

(2) The Authority may, by notice, request any party to a dispute—

(a)to attend at a time and place specified in the notice; and

(b)at that time and place, to give evidence to any person appointed by the Authority to conduct the oral hearing.

(3) At any oral hearing, the Authority may request the customer or a person attending the hearing as a representative of the electricity distributor to give evidence or make representations or observations.

(4) If any party fails to attend a hearing to be subjected to a requirement under sub-paragraph (3), the Authority may determine the dispute without hearing his evidence, representations, or observations.

(5) No person is to be compelled under this paragraph to give evidence that he could not be compelled to give in civil proceedings in the High Court or Court of Session.

Commencement Information

I9Sch. 2 para. 9 in force at 1.4.2015, see reg. 1(1)

Customer representatives for multiple disputesE+W+S

10.—(1) Where disputes are consolidated into categories under paragraph 4, the Authority must nominate one or more customers to be representatives of each consolidated group.E+W+S

(2) A customer nominated to be a representative of a consolidated group under this paragraph is only to become a representative if he consents to do so.

Commencement Information

I10Sch. 2 para. 10 in force at 1.4.2015, see reg. 1(1)

Collection of information in multiple disputesE+W+S

11.—(1) The Authority may by notice ask any customer or relevant authority (as applicable) who is a party to a dispute falling within a consolidated group to produce such information with respect to a matter specified in the notice as the Authority may reasonably require to enable it to make the determination decision.E+W+S

(2) The power to require the production of information under this paragraph includes the power to specify the time and place at which it is to be produced.

(3) No person is to be compelled under this paragraph to produce information with respect to any matter about which he could not be compelled to give evidence in civil proceedings in the High Court or Court of Session.

Commencement Information

I11Sch. 2 para. 11 in force at 1.4.2015, see reg. 1(1)

Payment to customersE+W+S

12.  An order determining a dispute does not (where there is more than one customer at the premises) determine who is beneficially entitled to any payment required to be made by the order.E+W+S

Commencement Information

I12Sch. 2 para. 12 in force at 1.4.2015, see reg. 1(1)

Set-offE+W+S

13.  Where a dispute is determined by an order requiring an electricity distributor to make a payment to the customer or the relevant authority (as applicable) and the electricity distributor fails to make that payment, the customer may set off the amount so ordered to be paid against any charges that are owed by the customer to the electricity distributor.E+W+S

Commencement Information

I13Sch. 2 para. 13 in force at 1.4.2015, see reg. 1(1)

CostsE+W+S

14.—(1) An order determining a dispute may include a provision requiring the electricity distributor or the customer or the relevant authority (as applicable) to pay a sum in respect of the costs or expenses incurred by the Authority.E+W+S

(2) In including in an order under sub-paragraph (1) any such provision as to costs, the Authority must have regard to the conduct and means of the parties and any other relevant circumstances.

Commencement Information

I14Sch. 2 para. 14 in force at 1.4.2015, see reg. 1(1)

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources