Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
5.—(1) A network provider may make a request to an infrastructure operator for an on-site survey of elements of the operator's physical infrastructure provided the request—
(a)is in writing;
(b)specifies the elements of the operator's infrastructure to which the request relates; and
(c)is made with a view to deploying elements of a high-speed electronic communications network to which the elements to be surveyed are relevant.
(2) Subject to paragraphs (3) to (5) and regulation 10(1) (national security), the infrastructure operator must, within a period of one month beginning with the date of receipt of the request, agree to grant a survey on proportionate, non-discriminatory and transparent terms.
(3) The infrastructure operator may refuse to grant a survey if, or to the extent, the relevant infrastructure is of a description set out in Schedule 1.
(4) The infrastructure operator may refuse to grant a survey if, or to the extent, compliance would, or would be likely to, prejudice—
(a)the security or integrity of any network;
(b)a duty of confidentiality owed by the infrastructure operator to another person;
(c)operating or business secrets of any person; or
(d)safety or public health.
(5) Without prejudice to paragraphs (3) and (4), the infrastructure operator may refuse to grant a survey if, or to the extent, the request cannot reasonably be met.
(6) If the infrastructure operator refuses to any extent a request, it must, within the time for complying with paragraph (2), give the network provider a notice which—
(a)indicates that the request has been refused or sets out the extent of the refusal; and
(b)provides the grounds for refusing and the reasons those grounds apply.
(7) The grounds and reasons need not be given to the extent giving them would, or would be likely to, prejudice those grounds or reasons (but regulation 10(8) applies to the extent the refusal is on national security grounds).
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: