Onshore decommissioning planE+W+S

20.—(1) Within 3 months of the cessation of commercial operation of the connection works, an onshore decommissioning plan must be submitted to the local planning authority for its approval.

(2) The decommissioning plan must be implemented as approved.

Commencement Information

I1Sch. 1 para. 20 in force at 7.9.2016, see art. 1(2)

Back to top