The Hornsea Two Offshore Wind Farm Order 2016

Onshore decommissioning planE+W+S

20.—(1) Within 3 months of the cessation of commercial operation of the connection works, an onshore decommissioning plan must be submitted to the local planning authority for its approval.

(2) The decommissioning plan must be implemented as approved.