The Hornsea Two Offshore Wind Farm Order 2016

North Coates airfieldE+W+S

21.  No part of the authorised development may be commenced within half a mile of the perimeter of the North Coates airfield until a plan to secure its safe operation during the construction and operation of the authorised development has been submitted to and approved by the Secretary of State following consultation with the operator of North Coates airfield and the Civil Aviation Authority.

Commencement Information

I1Sch. 1 para. 21 in force at 7.9.2016, see art. 1(2)