5.  The authorised development must be constructed within the following parameters—

(1) Works No. 1a (Drawing C_0003 Rev 01 of the works plans)—

DescriptionWorks No.Length (m)Width (m)Height (m)Height (m AOD)
Tipping hallWorks No. 1a (a)(i)487431.5+44.0 AOD
Waste bunker and waste handling equipmentWorks No. 1a (a)(ii)42.38544.5+57.0 AOD
Two process lines consisting of a moving grate, furnace, boiler and flue gas treatment plant and steam turbinesWorks No. 1a (a)(iii) and (v)130.77456.5+69.0 AOD
Facilities for the recovery of incinerator bottom ash and air pollution control residueWorks No. 1a (a)(iv)Below ground only
Control room containing operational and environmental control and monitoring systems and officesWorks No. 1a (a)(vi)65.62144.5+57 AOD
Stack containing flues for flue gas exhaustWorks No. 1a (c)2412.5105+117.5 AOD
Cooling equipmentWorks No. 1a (d)602428.7+41.2 AOD
Observation platform enclosureWorks No.1a (e)17136 (above +44.0 AOD)+50 AOD

(2) Works No. 1b (Drawing C_0002 Rev 01 of the works plans)—

DescriptionWorks No.Height (m)Height (m AOD)
Wastewater treatment facility, water pre-treatment plant, external stores and workshops, fuelling area and fuel storage, vehicle wash, transport offices and staff facilities, toilets, natural gas intake and management compound, fire control water tanks and electrical substationsWorks No. 1b1830.5

(3) Works No. 2 (Drawing C_0005 Rev 01 of the works plans)—

DescriptionWorks No.Length (m)Width (m)Height (m)Height (m AOD)
Resource recovery facilityWorks No. 2 (a), (b) and (c)12718020+30.5 AOD
Maximum dimensions based on dimensions of enclosing rectangle oriented north-south.

(4) Works No. 3 (Drawing C_0007 Rev 01 of the works plans)—

DescriptionWorks No.Length (m)Width (m)Height (m)Height (m AOD)
Visitor, community and education facilities, office accommodation and boat canopyWorks No. 34116.714+24.6 AOD

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources