- Latest available (Revised)
- Original (As made)
There are currently no known outstanding effects for the The Electricity Network Codes and Guidelines (Markets and Trading) (Amendment) (EU Exit) Regulations 2019.
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
Statutory Instruments
Exiting The European Union
Electricity
Made
15th March 2019
Coming into force in accordance with regulation 1
The Secretary of State makes these Regulations in exercise of the powers conferred by section 8(1) of, and paragraph 21 of Schedule 7 to, the European Union (Withdrawal) Act 2018 M1.
In accordance with paragraph 1(3) of Schedule 7 to that Act, a draft of this instrument has been laid before Parliament and approved by a resolution of each House of Parliament.
Marginal Citations
1.—(1) These Regulations may be cited as the Electricity Network Codes and Guidelines (Markets and Trading) (Amendment) (EU Exit) Regulations 2019 and come into force on exit day.
[F1(2) These Regulations do not extend to Northern Ireland.]
F2(3) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Textual Amendments
F1Reg. 1(2) substituted (N.I.) (15.9.2020) by The Electricity and Gas etc. (Amendment) (EU Exit) Regulations 2020 (S.I. 2020/1016), regs. 1(2), 5(2)(a)
F2Reg. 1(3) omitted (15.9.2020) by virtue of The Electricity and Gas etc. (Amendment) (EU Exit) Regulations 2020 (S.I. 2020/1016), regs. 1(2), 5(2)(b)
Commencement Information
I1Reg. 1 in force at 31.12.2020 on IP completion day (in accordance with 2020 c. 1, Sch. 5 para. 1(1)), see reg. 1(1)
2. In these Regulations—
“the ITC Regulation” means Commission Regulation (EU) No 838/2010 on laying down guidelines relating to the inter-transmission system operator compensation mechanism and a common regulatory approach to transmission charging;
“the Electricity Balancing Regulation” means Commission Regulation (EU) No 2017/2195 establishing a guideline on electricity balancing.
Commencement Information
I2Reg. 2 in force at 31.12.2020 on IP completion day (in accordance with 2020 c. 1, Sch. 5 para. 1(1)), see reg. 1(1)
3. The ITC Regulation is amended as set out in Schedule 1.
Commencement Information
I3Reg. 3 in force at 31.12.2020 on IP completion day (in accordance with 2020 c. 1, Sch. 5 para. 1(1)), see reg. 1(1)
4. The Electricity Balancing Regulation is amended as set out in Schedule 2.
Commencement Information
I4Reg. 4 in force at 31.12.2020 on IP completion day (in accordance with 2020 c. 1, Sch. 5 para. 1(1)), see reg. 1(1)
5.—(1) The following instruments are revoked—
(a)Commission Regulation (EU) No 2015/1222 establishing a guideline on capacity allocation and congestion management;
(b)Commission Regulation (EU) No 2016/1719 establishing a guideline on forward capacity allocation.
F3(2) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Textual Amendments
F3Reg. 5(2) omitted (15.9.2020) by virtue of The Electricity and Gas etc. (Amendment) (EU Exit) Regulations 2020 (S.I. 2020/1016), regs. 1(2), 5(3)
Commencement Information
I5Reg. 5 in force at 31.12.2020 on IP completion day (in accordance with 2020 c. 1, Sch. 5 para. 1(1)), see reg. 1(1)
Claire Perry
Minister of State
Department for Business, Energy and Industrial Strategy
Regulation 3
1. The ITC Regulation is amended as follows.E+W+S
Commencement Information
I6Sch. 1 para. 1 in force at 31.12.2020 on IP completion day (in accordance with 2020 c. 1, Sch. 5 para. 1(1)), see reg. 1(1)
2. Omit Article 1.E+W+S
Commencement Information
I7Sch. 1 para. 2 in force at 31.12.2020 on IP completion day (in accordance with 2020 c. 1, Sch. 5 para. 1(1)), see reg. 1(1)
3. In the text after Article 3, omit “This Regulation shall be binding in its entirety and directly applicable in all Member States.”.E+W+S
Commencement Information
I8Sch. 1 para. 3 in force at 31.12.2020 on IP completion day (in accordance with 2020 c. 1, Sch. 5 para. 1(1)), see reg. 1(1)
4. Omit Part A of the Annex.E+W+S
Commencement Information
I9Sch. 1 para. 4 in force at 31.12.2020 on IP completion day (in accordance with 2020 c. 1, Sch. 5 para. 1(1)), see reg. 1(1)
5. In Part B of the Annex—E+W+S
(a)in paragraph 1—
(i)for “each Member State” substitute “Great Britain F4...”;
(ii)for “ranges” substitute “range ”;
(b)in paragraph 2, for “a Member State” substitute “Great Britain F4...”;
(c)for paragraph 3 substitute—
“3. Average annual transmission charges paid by producers in Great Britain F4... shall be within a range of 0 to 2.5 euros per megawatt hour.”
(d)omit paragraphs 4 and 5.
Textual Amendments
F4Words in Sch. 1 para. 5 omitted (E.W.S.) (15.9.2020) by virtue of The Electricity and Gas etc. (Amendment) (EU Exit) Regulations 2020 (S.I. 2020/1016), regs. 1(2), 5(4)
Commencement Information
I10Sch. 1 para. 5 in force at 31.12.2020 on IP completion day (in accordance with 2020 c. 1, Sch. 5 para. 1(1)), see reg. 1(1)
Regulation 4
1. The Electricity Balancing Regulation is amended as follows.E+W+S
Commencement Information
I11Sch. 2 para. 1 in force at 31.12.2020 on IP completion day (in accordance with 2020 c. 1, Sch. 5 para. 1(1)), see reg. 1(1)
2.—(1) Article 1 is amended as follows.E+W+S
(2) In paragraph 2—
(a)for “regulatory authorities” substitute “ the regulatory authority ”;
(b)omit “, the Agency for the Cooperation of Energy Regulators (‘the Agency’), the European Network of Transmission System Operators for Electricity (‘ENTSO-E’)”.
(3) In paragraph 3, for “in the Union” substitute “ within the jurisdiction of Great Britain ”.
(4) In paragraph 4—
(a)for the first sentence, substitute “ This Regulation shall apply to all TSOs in Great Britain. ”;
(b)in the second sentence, for “Member States” substitute “ the Secretary of State or the regulatory authority ”.
(5) Omit paragraphs 6 and 7.
Commencement Information
I12Sch. 2 para. 2 in force at 31.12.2020 on IP completion day (in accordance with 2020 c. 1, Sch. 5 para. 1(1)), see reg. 1(1)
3.—(1) Article 2 is amended as follows.E+W+S
(2) For the first paragraph substitute—
“Except where stated in this Article, for the purposes of this Regulation, the definitions in Article 2 of [F5Regulation (EU) 2019/943 of the European Parliament and of the Council of 5 June 2019 on the internal market for electricity (recast)], Article 2 of Commission Regulation (EU) No 543/2013 M2 and Article 3 of Commission Regulation (EU) 2017/1485 M3 apply.”.
(3) In the second paragraph—
(a)omit points (18) to (21) and (23) to (25);
(b)in point (27) omit “for a standard product on a common merit order list”;
(c)omit points (28) to (32) and (34) to (45);
(d)at the end insert—
“(46) “day-ahead market gate closure time” has the meaning given in Article 2 of Commission Regulation (EU) 2015/1222, as it applied in EU law immediately before [F6IP completion day];
(47) “day-ahead market time frame” has the meaning given in Article 2 of Commission Regulation (EU) 2015/1222, as it applied in EU law immediately before [F6IP completion day];
(48) “demand facility” has the meaning given in Article 2 of Commission Regulation (EU) 2016/1388, as it applied in EU law immediately before [F6IP completion day];
F7(49) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .”
Textual Amendments
F5Words in Sch. 2 para. 3(2) substituted (15.9.2020) by The Electricity and Gas etc. (Amendment) (EU Exit) Regulations 2020 (S.I. 2020/1016), regs. 1(2), 5(5)(a)
F6Words in Sch. 2 para. 3(3)(d) substituted (15.9.2020) by The Electricity and Gas etc. (Amendment) (EU Exit) Regulations 2020 (S.I. 2020/1016), regs. 1(2), 5(5)(b)
F7Words in Sch. 2 para. 3(3)(d) omitted (16.9.2020) by virtue of The Electricity and Gas (Internal Markets and Network Codes) (Amendment etc.) (EU Exit) Regulations 2020 (S.I. 2020/1006), regs. 1(2), 2(2)
Commencement Information
I13Sch. 2 para. 3 in force at 31.12.2020 on IP completion day (in accordance with 2020 c. 1, Sch. 5 para. 1(1)), see reg. 1(1)
Marginal Citations
M2Further amendments to Commission Regulation (EU) No 543/2013 are made by S.I. 2019/534.
M3Further amendments to Commission Regulation (EU) No 2017/1485 are made by S.I. 2019/533.
4.—(1) Article 3 is amended as follows.E+W+S
(2) In paragraph 1—
(a)in point (b), omit “European and”;
(b)in point (d), omit “in the Union”;
(c)in point (e), for “distortions within the internal market in electricity” substitute “ market distortions ”;
(d)in point (g), for “support the achievement of the European Union target for the penetration of renewable generation” substitute “ supporting the achievement of any target specified in an enactment for the share of energy from renewable sources ”.
(3) In paragraph 2—
(a)in the opening words before point (a), for “Member States, relevant regulatory authorities,” substitute “ the Secretary of State, the regulatory authority ”;
(b)in point (f), for “national legislation” substitute “ any enactment ”;
(c)in point (h), omit “European”.
Commencement Information
I14Sch. 2 para. 4 in force at 31.12.2020 on IP completion day (in accordance with 2020 c. 1, Sch. 5 para. 1(1)), see reg. 1(1)
5.—(1) Article 4 is amended as follows.E+W+S
(2) In paragraph 1, for “relevant regulatory authorities in accordance with Article 37 of Directive 2009/72/EC” substitute “ regulatory authority ”.
(3) In paragraph 2—
(a)omit “, with the assistance of ENTSO-E,”;
(b)for “relevant regulatory authorities and the Agency” substitute “ regulatory authority ”.
(4) Omit paragraphs 3 to 7.
Commencement Information
I15Sch. 2 para. 5 in force at 31.12.2020 on IP completion day (in accordance with 2020 c. 1, Sch. 5 para. 1(1)), see reg. 1(1)
6.—(1) Article 5 is amended as follows.E+W+S
(2) In paragraph 1—
(a)for “Each relevant regulatory authority in accordance with Article 37 of Directive 2009/72/EC” substitute “ The regulatory authority ”;
(b)for “paragraphs 2, 3 and 4” substitute “ paragraph 4 ”.
(3) Omit paragraphs 2 and 3.
(4) In paragraph 4—
(a)in the opening words before point (a)—
(i)for “each regulatory authority” substitute “ the regulatory authority ”;
(ii)omit “of each concerned Member State”;
(b)omit points (d) and (e);
(c)after point (i), insert—
“(j)the exemption, for the geographical area in which the procurement of balancing capacity has taken place, from the requirement to allow balancing service providers to transfer their obligations to provide balancing capacity pursuant to Article 34(1);
(k)the exemption from the requirement to apply imbalance settlement periods of 15 minutes pursuant to Article 53(2);”;
(d)in the words after point (k) (as so inserted)—
(i)for “a Member State” substitute “ the Secretary of State ”;
(ii)omit “concerned”.
(5) In paragraph 5—
(a)in the second sentence—
(i)for “relevant regulatory authorities” substitute “ regulatory authority ”;
(ii)for “all relevant regulatory authorities agree” substitute “ the regulatory authority agrees ”;
(b)omit the third and fourth sentences.
(6) Omit paragraphs 6 and 7.
Commencement Information
I16Sch. 2 para. 6 in force at 31.12.2020 on IP completion day (in accordance with 2020 c. 1, Sch. 5 para. 1(1)), see reg. 1(1)
7.—(1) Article 6 is amended as follows.E+W+S
(2) In paragraph 1, in the first sentence—
(a)for “one or several regulatory authorities in accordance with Article 37 of Directive 2009/72/EC require” substitute “ the regulatory authority requires ”;
(b)for “paragraphs 2, 3 and 4” substitute “ paragraph 4 ”.
(3) In paragraph 1, for “relevant regulatory authorities” in both places that the term occurs, substitute “ regulatory authority ”.
(4) Omit paragraph 2.
(5) In paragraph 3, in the first sentence—
(a)for “regulatory authorities” substitute “ the regulatory authority ”;
(b)omit “responsible for their adoption in accordance with paragraphs 2, 3 and 4 of Article 5”.
Commencement Information
I17Sch. 2 para. 7 in force at 31.12.2020 on IP completion day (in accordance with 2020 c. 1, Sch. 5 para. 1(1)), see reg. 1(1)
8. In Article 7, for “relevant regulatory authorities” substitute “ regulatory authority ”.E+W+S
Commencement Information
I18Sch. 2 para. 8 in force at 31.12.2020 on IP completion day (in accordance with 2020 c. 1, Sch. 5 para. 1(1)), see reg. 1(1)
9.—(1) Article 8 is amended as follows.E+W+S
(2) In paragraph 1, for “relevant regulatory authorities in accordance with Article 37 of Directive 2009/72/EC” substitute “ regulatory authority ”.
(3) In paragraph 2, for “relevant regulatory authority” and “relevant regulatory authorities” substitute “ regulatory authority ” in each case.
(4) In paragraph 3, for “relevant regulatory authorities” substitute “ regulatory authority ”.
Commencement Information
I19Sch. 2 para. 9 in force at 31.12.2020 on IP completion day (in accordance with 2020 c. 1, Sch. 5 para. 1(1)), see reg. 1(1)
10. In Article 9, for “Agency, in close cooperation with ENTSO-E,” substitute “ national electricity transmission system operator ”.E+W+S
Commencement Information
I20Sch. 2 para. 10 in force at 31.12.2020 on IP completion day (in accordance with 2020 c. 1, Sch. 5 para. 1(1)), see reg. 1(1)
11.—(1) Article 10 is amended as follows.E+W+S
(2) In paragraph 1, for “relevant regulatory authorities of each Member State” substitute “ regulatory authority ”.
(3) Omit paragraphs 2 to 4.
(4) In paragraph 5—
(a)for “and (i)” substitute “ , (i), (j) and (k). ”;
(b)omit “in each concerned Member State”.
(5) In paragraph 6, for “paragraphs 2 to 5” substitute “ paragraph 5 ”.
Commencement Information
I21Sch. 2 para. 11 in force at 31.12.2020 on IP completion day (in accordance with 2020 c. 1, Sch. 5 para. 1(1)), see reg. 1(1)
12.—(1) Article 11 is amended as follows.E+W+S
(2) In paragraph 3—
(a)omit “national law,”;
(b)for “other relevant Union legislation” substitute “ any other enactment ”.
(3) In paragraph 4—
(a)for “national law or Union legislation” substitute “ any other enactment ”;
(b)for “regulatory authorities” substitute “ the regulatory authority ”.
Commencement Information
I22Sch. 2 para. 12 in force at 31.12.2020 on IP completion day (in accordance with 2020 c. 1, Sch. 5 para. 1(1)), see reg. 1(1)
13.—(1) Article 12 is amended as follows.E+W+S
(2) In paragraph 3—
(a)omit points (c) and (d);
(b)in point (e)—
(i)in subpoint (iii), omit “separately for standard and specific products”;
(ii)omit subpoint (iv);
(c)in point (g), for “relevant regulatory authority in accordance with Article 37 of Directive 2009/72/EC” substitute “ regulatory authority ”;
(d)omit points (h) to (l).
(3) In paragraph 4, for “relevant regulatory authority in accordance with Article 37 of Directive 2009/72/EC” substitute “ regulatory authority ”.
(4) In paragraph 5, omit from the words “at least through” until the end of the paragraph.
Commencement Information
I23Sch. 2 para. 13 in force at 31.12.2020 on IP completion day (in accordance with 2020 c. 1, Sch. 5 para. 1(1)), see reg. 1(1)
14.—(1) Article 13 is amended as follows.E+W+S
(2) In paragraph 1, for “relevant regulatory authorities in accordance with Article 37 of Directive 2009/72/EC” substitute “regulatory authority”.
(3) In paragraph 3, omit “relevant”.
(4) In paragraph 4—
(a)in the first sentence—
(i)after “Directive 2009/72/EC” insert “as it applied immediately before [F8IP completion day]”;
(ii)for “a Member State” substitute “the Secretary of State”;
(iii)for “a relevant” substitute “the”;
(b)omit the second sentence;
(c)in the third sentence—
(i)for “Member State” substitute “Secretary of State”;
(ii)omit “relevant”.
(5) In paragraph 5—
(a)in the first sentence, for “a Member State, or a regulatory authority” substitute “the Secretary of State or the regulatory authority”;
(b)in the second sentence, omit “relevant”.
Textual Amendments
F8Words in Sch. 2 para. 14(4)(a) substituted (15.9.2020) by The Electricity and Gas etc. (Amendment) (EU Exit) Regulations 2020 (S.I. 2020/1016), regs. 1(2), 5(5)(c)
Commencement Information
I24Sch. 2 para. 14 in force at 31.12.2020 on IP completion day (in accordance with 2020 c. 1, Sch. 5 para. 1(1)), see reg. 1(1)
15. In Article 14, in paragraph 2, omit the second and third sentences.E+W+S
Commencement Information
I25Sch. 2 para. 15 in force at 31.12.2020 on IP completion day (in accordance with 2020 c. 1, Sch. 5 para. 1(1)), see reg. 1(1)
16.—(1) Article 16 is amended as follows.E+W+S
(2) In paragraph 1, in the first sentence, omit “or, in a TSO-BSP model, by the contracting TSO”.
(3) In paragraph 4, omit “or integrated scheduling process bids”.
(4) In paragraph 5, omit “from standard products or specific products or integrated scheduling process bids”.
(5) In paragraph 6—
(a)in the first sentence, omit “or integrated scheduling process bids from standard and specific products”;
(b)in the third sentence, omit “only apply to specific products pursuant to Article 26(3)(b) and”.
(6) In paragraph 7, omit “or integrated scheduling process bids” in both places in which the term occurs;
Commencement Information
I26Sch. 2 para. 16 in force at 31.12.2020 on IP completion day (in accordance with 2020 c. 1, Sch. 5 para. 1(1)), see reg. 1(1)
17. In Article 17, omit paragraphs 3 and 4.E+W+S
Commencement Information
I27Sch. 2 para. 17 in force at 31.12.2020 on IP completion day (in accordance with 2020 c. 1, Sch. 5 para. 1(1)), see reg. 1(1)
18.—(1) Article 18 is amended as follows.E+W+S
(2) In paragraph 1—
(a)in the first subparagraph, for “and for all scheduling areas of a Member State, the TSOs of this Member State” substitute “ TSOs ”;
(b)in the second subparagraph, for “relevant regulatory authorities” substitute “ regulatory authority ”.
(3) Omit paragraph 3(b).
(4) In paragraph 5—
(a)in point (b), omit “, 33”;
(b)in point (g), for “standard product and each specific” substitute “ balancing ”.
(5) In paragraph 6(e), for “paragraphs 3 and 4” substitute “ paragraph 4 ”.
(6) In paragraph 7—
(a)omit point (a);
(b)in point (b)—
(i)omit “or integrated scheduling process bids”;
(ii)omit “or the integrated scheduling process gate closure time”.
(c)omit point (c);
(d)in point (f), omit “for specific products defined in Article 26(3)(b)”;
(e)in point (g), for the words from “based” to the end substitute “ containing the information set out in Article 52(2)(d)(i) and (ii) ”.
(7) Omit paragraph 8.
Commencement Information
I28Sch. 2 para. 18 in force at 31.12.2020 on IP completion day (in accordance with 2020 c. 1, Sch. 5 para. 1(1)), see reg. 1(1)
19. Before Article 19, for the heading of Chapter 2 of Title II, substitute “ Failure of the procurement of balancing services ”.E+W+S
Commencement Information
I29Sch. 2 para. 19 in force at 31.12.2020 on IP completion day (in accordance with 2020 c. 1, Sch. 5 para. 1(1)), see reg. 1(1)
20. Omit Articles 19 to 27.E+W+S
Commencement Information
I30Sch. 2 para. 20 in force at 31.12.2020 on IP completion day (in accordance with 2020 c. 1, Sch. 5 para. 1(1)), see reg. 1(1)
21.—(1) Article 28 is amended as follows.E+W+S
(2) In paragraph 1, for “the procedures referred to in paragraphs 2 and 3 fail” substitute “ the procedure referred to in paragraph 2 fails ”.
(3) Omit paragraph 3.
Commencement Information
I31Sch. 2 para. 21 in force at 31.12.2020 on IP completion day (in accordance with 2020 c. 1, Sch. 5 para. 1(1)), see reg. 1(1)
22. Omit Chapter 1 of Title III.E+W+S
Commencement Information
I32Sch. 2 para. 22 in force at 31.12.2020 on IP completion day (in accordance with 2020 c. 1, Sch. 5 para. 1(1)), see reg. 1(1)
23.—(1) Article 32 is amended as follows.E+W+S
(2) In paragraph 1—
(a)in point (a), omit “and exchange of balancing capacity with neighbouring TSOs”;
(b)in point (c)—
(i)omit “both”;
(ii)omit the words from “and within” to the end of the sentence.
(3) In paragraph 3—
(a)in the second sentence, for “relevant regulatory authority in accordance with Article 37 of Directive 2009/72/EC” substitute “ regulatory authority ”;
(b)in point (c), for “balancing resources pursuant to Article 25(6)(b)” substitute “ demand facility owners, third parties and owners of power generating facilities from renewable energy sources as well as owners of energy storage units ”.
Commencement Information
I33Sch. 2 para. 23 in force at 31.12.2020 on IP completion day (in accordance with 2020 c. 1, Sch. 5 para. 1(1)), see reg. 1(1)
24. Omit Article 33.E+W+S
Commencement Information
I34Sch. 2 para. 24 in force at 31.12.2020 on IP completion day (in accordance with 2020 c. 1, Sch. 5 para. 1(1)), see reg. 1(1)
25.—(1) Article 34 is amended as follows.E+W+S
(2) In paragraph 3(c), for “Chapters 1 and 2” substitute “ Chapter 1 ”.
(3) Omit paragraph 4.
Commencement Information
I35Sch. 2 para. 25 in force at 31.12.2020 on IP completion day (in accordance with 2020 c. 1, Sch. 5 para. 1(1)), see reg. 1(1)
26. Omit Chapter 3 of Title III.E+W+S
Commencement Information
I36Sch. 2 para. 26 in force at 31.12.2020 on IP completion day (in accordance with 2020 c. 1, Sch. 5 para. 1(1)), see reg. 1(1)
27. Omit Title IV.E+W+S
Commencement Information
I37Sch. 2 para. 27 in force at 31.12.2020 on IP completion day (in accordance with 2020 c. 1, Sch. 5 para. 1(1)), see reg. 1(1)
28.—(1) Article 44 is amended as follows.E+W+S
(2) Omit paragraph 1(d).
(3) In paragraph 2—
(a)for “Each relevant regulatory authority in accordance with Article 37 of Directive 2009/72/EC”, substitute “ The regulatory authority ”;
(b)for “the relevant regulatory authority” substitute “ the regulatory authority ”;
(c)for “Chapters 2, 3 and 4”, in each place that it occurs, substitute “ Chapters 2 and 4 ”.
(4) In paragraph 3, in the last sentence, omit “relevant”.
(5) In paragraph 4, omit “Chapter 3 or”.
Commencement Information
I38Sch. 2 para. 28 in force at 31.12.2020 on IP completion day (in accordance with 2020 c. 1, Sch. 5 para. 1(1)), see reg. 1(1)
29. In Article 47, in paragraph 2, omit “pursuant to Article 30”.E+W+S
Commencement Information
I39Sch. 2 para. 29 in force at 31.12.2020 on IP completion day (in accordance with 2020 c. 1, Sch. 5 para. 1(1)), see reg. 1(1)
30. In Article 48, in paragraph 2, omit “pursuant to Article 30”.E+W+S
Commencement Information
I40Sch. 2 para. 30 in force at 31.12.2020 on IP completion day (in accordance with 2020 c. 1, Sch. 5 para. 1(1)), see reg. 1(1)
31. Omit Chapter 3 of Title V.E+W+S
Commencement Information
I41Sch. 2 para. 31 in force at 31.12.2020 on IP completion day (in accordance with 2020 c. 1, Sch. 5 para. 1(1)), see reg. 1(1)
32.—(1) Article 52 is amended as follows.E+W+S
(2) In paragraph 2—
(a)in the opening words before point (a), omit “and harmonise”;
(b)in point (d)(i)—
(i)for “its relevant” substitute “ the ”;
(ii)omit “in accordance with Article 37 of Directive 2009/72/EC”.
(3) Omit paragraph 3.
(4) In paragraph 4, for “all relevant regulatory authorities in accordance with Article 5(2)” substitute “ the regulatory authority ”.
Commencement Information
I42Sch. 2 para. 32 in force at 31.12.2020 on IP completion day (in accordance with 2020 c. 1, Sch. 5 para. 1(1)), see reg. 1(1)
33.—(1) Article 53 is amended as follows.E+W+S
(2) In paragraph 2, for “a” substitute “ the GB ”.
(3) For paragraph 3, substitute—
“3. The regulatory authority may grant an exemption from the requirement laid down in paragraph 1—
(a)upon a request under paragraph 2; or
(b)on its own initiative.”
Commencement Information
I43Sch. 2 para. 33 in force at 31.12.2020 on IP completion day (in accordance with 2020 c. 1, Sch. 5 para. 1(1)), see reg. 1(1)
34.—(1) Article 54 is amended as follows.E+W+S
(2) In paragraph 2, omit from the words “, except in case” until the end of the sentence.
(3) In paragraph 3, omit point (c).
Commencement Information
I44Sch. 2 para. 34 in force at 31.12.2020 on IP completion day (in accordance with 2020 c. 1, Sch. 5 para. 1(1)), see reg. 1(1)
35. Omit Article 57.E+W+S
Commencement Information
I45Sch. 2 para. 35 in force at 31.12.2020 on IP completion day (in accordance with 2020 c. 1, Sch. 5 para. 1(1)), see reg. 1(1)
36. Omit Title VI.E+W+S
Commencement Information
I46Sch. 2 para. 36 in force at 31.12.2020 on IP completion day (in accordance with 2020 c. 1, Sch. 5 para. 1(1)), see reg. 1(1)
37. Omit Article 59.E+W+S
Commencement Information
I47Sch. 2 para. 37 in force at 31.12.2020 on IP completion day (in accordance with 2020 c. 1, Sch. 5 para. 1(1)), see reg. 1(1)
38.—(1) Article 60 is amended as follows.E+W+S
(2) In paragraph 2, omit points (a), (d), (e), (f) and (g).
(3) Omit paragraph 3.
(4) In paragraph 4, for “relevant regulatory authority in accordance with Article 37 of Directive 2009/72/EC” substitute “ regulatory authority ”.
Commencement Information
I48Sch. 2 para. 38 in force at 31.12.2020 on IP completion day (in accordance with 2020 c. 1, Sch. 5 para. 1(1)), see reg. 1(1)
39.—(1) Article 61 is amended as follows.E+W+S
(2) In paragraph 1—
(a)in the first sentence, for “relevant regulatory authorities in accordance with Article 37 of Directive 2009/72/EC” substitute “ regulatory authority ”;
(b)in the second sentence—
(i)omit “relevant”;
(ii)omit “jointly”.
(3) In paragraph 2—
(a)in point (e), omit “European and national”;
(b)in point (f), omit “European”.
(4) In paragraph 3, for “all relevant regulatory authorities” substitute “ the regulatory authority ”.
Commencement Information
I49Sch. 2 para. 39 in force at 31.12.2020 on IP completion day (in accordance with 2020 c. 1, Sch. 5 para. 1(1)), see reg. 1(1)
40.—(1) Article 62 is amended as follows.E+W+S
(2) In paragraph 1, for “A relevant regulatory authority in accordance with Article 37 of Directive 2009/72/EC” substitute “ The regulatory authority ”.
(3) In paragraph 2—
(a)omit points (a) to (c);
(b)in point (d), for “harmonisation” substitute “ application ”;
(c)in point (e), omit “50, 51,”.
(4) In paragraphs 4, 6, 7, 8 and 9, omit “relevant” in each place that it occurs.
(5) In paragraph 5, omit points (d) and (e).
(6) In paragraph 8—
(a)in point (d), omit “European”;
(b)omit point (f).
(7) In paragraph 9, in the final sentence, for “derogations in paragraph 2(c) and 2(d)” substitute “ derogation in paragraph 2(d) ”.
(8) In paragraph 10, for the first sentence, substitute “ The regulatory authority shall notify its decision to the TSO and the Secretary of State. ”
(9) In paragraph 11—
(a)for “relevant regulatory authorities” substitute “ regulatory authority ”;
(b)for “Agency” substitute “ Secretary of State ”;
(c)omit “, a copy of which shall be given to ENTSO-E”.
Commencement Information
I50Sch. 2 para. 40 in force at 31.12.2020 on IP completion day (in accordance with 2020 c. 1, Sch. 5 para. 1(1)), see reg. 1(1)
41. Omit Article 63.E+W+S
Commencement Information
I51Sch. 2 para. 41 in force at 31.12.2020 on IP completion day (in accordance with 2020 c. 1, Sch. 5 para. 1(1)), see reg. 1(1)
42. In the heading of Title X, omit “Transitional and”.E+W+S
Commencement Information
I52Sch. 2 para. 42 in force at 31.12.2020 on IP completion day (in accordance with 2020 c. 1, Sch. 5 para. 1(1)), see reg. 1(1)
43. Omit Article 64.E+W+S
Commencement Information
I53Sch. 2 para. 43 in force at 31.12.2020 on IP completion day (in accordance with 2020 c. 1, Sch. 5 para. 1(1)), see reg. 1(1)
44. In the words after Article 65, omit “This Regulation shall be binding in its entirety and directly applicable in all Member States.”.E+W+S
Commencement Information
I54Sch. 2 para. 44 in force at 31.12.2020 on IP completion day (in accordance with 2020 c. 1, Sch. 5 para. 1(1)), see reg. 1(1)
(This note is not part of the Regulations)
These Regulations are made in exercise of the powers in section 8(1) of the European Union (Withdrawal) Act 2018 (c. 16) in order to address failures of retained EU law to operate effectively and other deficiencies (in particular under section 8(2)(a) to (e) and (g) of that Act) arising from the withdrawal of the United Kingdom from the European Union.
These Regulations amend Commission Regulation (EU) No 838/2010 on laying down guidelines relating to the inter-transmission system operator compensation mechanism and a common regulatory approach to transmission charging, and Commission Regulation (EU) No 2017/2195 establishing a guideline on electricity balancing which form part of the domestic law of the United Kingdom on and after exit day by virtue of section 3 of the European Union (Withdrawal) Act 2018.
These Regulations also revoke Commission Regulations (EU) No 2015/1222 and 2016/1719.
An impact assessment has not been produced for this instrument as no, or no significant, impact on the private or voluntary sector is foreseen.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including:
The data on this page is available in the alternative data formats listed: