Search Legislation

The Electricity Capacity (No. 1) Regulations 2019

 Help about what version

What Version

 Help about opening options

Opening Options

Status:

This is the original version (as it was originally made).

DSR unproven capacity fee

This section has no associated Explanatory Memorandum

42.  The Principal Regulations apply as if, after regulation 43ZA (termination fees: adjustment for DSR providers) there were inserted—

DSR unproven capacity fee

43ZB.(1) A capacity provider (“C”) in respect of a demand side response CMU (“CMU i”) must pay to the Settlement Body a fee (a “DSR unproven capacity fee”), by way of financial penalty, if C has in accordance with capacity market rules provided to the Delivery Body a DSR test certificate which evidences CMU i’s proven DSR capacity is an amount less than CMU i’s de-rated capacity.

(2) Where a DSR unproven capacity fee would be payable by C before the T-1 capacity agreement trigger event has occurred, this fee only becomes payable if the T-1 capacity agreement trigger event occurs.

(3) Subject to paragraph (4), the Settlement Body must, as soon as reasonably practicable after receiving notice from the Delivery Body that C has provided a DSR test certificate which gives rise to a DSR unproven capacity fee—

(a)determine the amount in pounds of the DSR unproven capacity fee that is payable (or which would be payable if the T-1 capacity agreement trigger event occurred); and

(b)issue to the capacity provider an invoice for that amount.

(4) An invoice under paragraph (3)(b) must only be issued on or after the date on which the T-1 capacity agreement trigger event occurred.

(5) The DSR unproven capacity fee payable by C in respect of CMU i is—

(a)where CMU i’s proven DSR capacity is less than 90% of CMU i’s de-rated capacity, UCF 1; and

(b)where CMU i’s proven DSR capacity is equal to or greater than 90% of CMU i’s de-rated capacity, UCF 2.

(6) In this regulation—

“UCF 1” means an amount equal to £5000 per MW of the amount of the de-rated capacity of CMU i; and

“UCF 2” means an amount calculated in accordance with the formula—

(7) In paragraph (6)—

“DC” means CMU i’s de-rated capacity; and

“PC” means CMU i’s proven DSR capacity..

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Memorandum

Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources