Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
16. In this Part, “return” means a submission by the licence holder for approval by the MMO of any method statement or plan under conditions 119, 121 and 123.
Commencement Information
I1Sch. 13 para. 16 in force at 15.10.2020, see art. 1
17.—(1) The MMO may request in writing such further information from the licence holder as is necessary to enable the MMO to consider the return.
(2) If the MMO does not make a request under sub-paragraph (1) within 30 business days of the day immediately following that on which the return is received by the MMO, it is deemed to have sufficient information to consider the return and is not entitled to request further information after this date without the prior agreement of the licence holder.
Commencement Information
I2Sch. 13 para. 17 in force at 15.10.2020, see art. 1
18.—(1) In determining the return, the MMO may have regard to—
(a)the return and any supporting information or documentation;
(b)any further information provided by the licence holder in accordance with paragraph 131; and
(c)such other matters as the MMO thinks relevant.
(2) Having considered the return, the MMO must—
(a)grant the return unconditionally; or
(b)grant the return subject to the conditions the MMO thinks fit; or
(c)refuse the return.
(3) In determining return, the MMO may discharge its obligations under sub-paragraph (2)(a), (b), or (c) separately in respect of a part of the return only, where it is reasonable to do so.
Commencement Information
I3Sch. 13 para. 18 in force at 15.10.2020, see art. 1
19.—(1) Subject to sub-paragraphs (2) and (3), the MMO must give notice to the licence holder of the determination of the return within 13 weeks from the day immediately following that on which the return is received by the MMO, or as soon as reasonably practicable after that date.
(2) Where the MMO has made a request under paragraph 131, the MMO must give notice to the licence holder of the determination of the return within 13 weeks from the day immediately following that on which the further information is received by the MMO, or as soon as reasonably practicable after that date.
(3) Where the MMO determines it is not reasonably practicable to make a determination pursuant to sub-paragraph (1) or (2) in 13 weeks, it must notify the licence holder as soon as reasonably practicable and provide confirmation in writing of the intended determination date.
(4) Where the MMO refuses the return the refusal notice must state the reasons for the refusal.
Commencement Information
I4Sch. 13 para. 19 in force at 15.10.2020, see art. 1
20. Unless otherwise agreed in writing with the MMO, this licence does not permit any subsidiary works and operations to be carried out under article 49(1)(b) (subsidiary works and operations in the river Yare) of the Order.
Commencement Information
I5Sch. 13 para. 20 in force at 15.10.2020, see art. 1
21. If before the coming into force of this Order the licence holder or any other person has taken any steps that were intended to be steps towards the discharge of any condition in Part 2 of this Schedule, those steps may be taken into account for the purposes of determining compliance with that condition if they would have been valid steps for that purpose had they been taken after this Order came into force.
Commencement Information
I6Sch. 13 para. 21 in force at 15.10.2020, see art. 1
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: