- Latest available (Revised)
- Point in Time (15/10/2020)
- Original (As made)
There are currently no known outstanding effects for the The Great Yarmouth Third River Crossing Development Consent Order 2020.
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
SCHEDULES
PERMANENT STOPPING UP OF STREETS AND PRIVATE MEANS OF ACCESS
In relating this Schedule to the corresponding street plans, the...
PART 1 STREETS FOR WHICH A SUBSTITUTE IS TO BE PROVIDED AND OTHER NEW STREETS TO BE PROVIDED
PART 2 STREET TO BE STOPPED UP FOR WHICH NO SUBSTITUTE IS TO BE PROVIDED
PART 4 PRIVATE MEANS OF ACCESS TO BE STOPPED UP FOR WHICH NO SUBSTITUTE IS TO BE PROVIDED
MODIFICATION OF COMPENSATION AND COMPULSORY PURCHASE ENACTMENTS FOR CREATION OF NEW RIGHTS
TREES SUBJECT TO TREE PRESERVATION ORDERS AND WITHIN CONSERVATION AREAS
PART 1 FOR THE PROTECTION OF ELECTRICITY, GAS, WATER AND SEWERAGE UNDERTAKERS
1.The provisions of this Part of this Schedule have effect...
2.In this Part of this Schedule— “alternative apparatus” means alternative...
4.(1) Regardless of the temporary stopping up, alteration or diversion...
5.Despite any provision in this Order or anything shown on...
7.(1) Where, in accordance with the provisions of this Part...
9.(1) Subject to the following provisions of this paragraph, the...
10.(1) Subject to sub-paragraphs (2) and (3), if by reason...
11.If in consequence of the exercise of the powers conferred...
PART 2 FOR THE PROTECTION OF OPERATORS OF ELECTRONIC COMMUNICATIONS CODE NETWORKS
PART 3 FOR THE PROTECTION OF ANGLIAN WATER
17.For the protection of Anglian Water, the provisions of this...
18.In this Part of this Schedule— “alternative apparatus” means alternative...
19.The undertaker must not interfere with, build over or near...
20.The alteration, extension, removal or re-location of any apparatus must...
21.In the situation, where in exercise of the powers conferred...
22.Regardless of any provision in this Order or anything shown...
23.If in consequence of the exercise of the powers conferred...
24.If in consequence of the exercise of the powers conferred...
25.If for any reason or in consequence of the construction...
26.Nothing in paragraph 25 above imposes any liability on the...
27.Any difference or dispute arising between the undertaker and Anglian...
PART 4 FOR THE PROTECTION OF THE ENVIRONMENT AGENCY
28.(1) The following provisions of this Part of this Schedule...
29.(1) Before beginning to construct any specified work, the undertaker...
30.Without limiting paragraph 29, the requirements which the Agency may...
31.Subject to sub-paragraph (2), any specified work, and all protective...
32.(1) Subject to sub-paragraph (5) the undertaker must from the...
34.If by reason of construction of the specified work the...
36.(1) The undertaker must indemnify the Agency in respect of...
37.(1) The undertaker is responsible for and must indemnify the...
38.Any dispute arising between the undertaker and the Agency under...
PART 5 FOR THE PROTECTION OF THE WAVENEY, LOWER YARE AND LOTHINGLAND INTERNAL DRAINAGE BOARD
39.The provisions of this Part of this Schedule have effect...
41.(1) The undertaker must notify the Board of the intended...
42.The undertaker must permit any officer of the Board to...
43.In constructing and operating the outfall pipe, the undertaker must...
44.If a specified work requires a relevant water course to...
45.Where the undertaker culverts a relevant watercourse in carrying out...
47.(1) The undertaker must at its expense maintain all elements...
48.Any agreement or approval under this Part of this Schedule...
49.(1) Save as provided by sub-paragraph (2) or other provision...
50.Any difference or dispute arising between the undertaker and the...
PART 6 FOR THE PROTECTION OF THE GREAT YARMOUTH PORT AUTHORITY
51.For the protection of the GYPA the following provisions of...
52.In this Part of this Schedule the following definitions apply—...
53.(1) Subject to sub-paragraph (2), nothing in this Order authorises...
54.The undertaker must not commence the operation of any element...
55.Any navigation simulations required to be carried out by the...
57.(1) The undertaker must comply with any special direction given...
59.(1) The undertaker must not in the course of constructing...
61.(1) Prior to commencement of the works, a baseline hydrographic...
62.(1) In the event that the further surveys or assessment...
63.(1) The undertaker must at all reasonable times on being...
64.The undertaker must provide and maintain at its own expense...
65.(1) The undertaker must, upon completion of any part of...
66.(1) The undertaker must, before placing any temporary structure or...
68.Within 3 months of completion of the specified works and...
69.The undertaker must keep such elements of the specified works...
70.The undertaker must, so far as practicable, keep the new...
71.The undertaker must publish and maintain in a prominent position...
72.Before providing any illumination or illuminated traffic sign on or...
73.The undertaker is responsible for the development, implementation and ongoing...
74.Any reasonable and proper additional expenses not otherwise provided for...
75.(1) Subject to the provisions of this paragraph, the undertaker...
76.Except as provided by this Order, nothing in this Order...
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including:
The data on this page is available in the alternative data formats listed: