Print Options
PrintThe Whole
Instrument
PrintThe Whole
Schedule
PrintThe Whole
Part
PrintThis
Section
only
Changes over time for: Paragraph 41


Timeline of Changes
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Status:
Point in time view as at 15/10/2020.
Changes to legislation:
There are currently no known outstanding effects for the The Great Yarmouth Third River Crossing Development Consent Order 2020, Paragraph 41.

Changes to Legislation
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
41.—(1) The undertaker must notify the Board of the intended commencement and anticipated duration of any specified work.E+W+S
(2) The notification given under sub-paragraph (1) must be given 14 working days prior to commencement of the relevant specified work.
(3) The requirements of sub-paragraphs (1) and (2) have effect in addition to any other requirement of this Part of this Schedule which must be complied with by the undertaker prior to the commencement of any specified work.