Search Legislation

The Great Yarmouth Third River Crossing Development Consent Order 2020

 Help about what version

What Version

 Help about advanced features

Advanced Features

 Help about opening options

Opening OptionsExpand opening options

Changes over time for: Paragraph 58

 Help about opening options

Alternative versions:

Status:

Point in time view as at 15/10/2020.

Changes to legislation:

There are currently no known outstanding effects for the The Great Yarmouth Third River Crossing Development Consent Order 2020, Paragraph 58. Help about Changes to Legislation

58.  Any specified work must, when commenced be constructed—E+W+S

(a)without unnecessary delay;

(b)in such a manner as to cause as little adverse effects as is reasonably practicable to the river;

(c)in such a manner as to cause no material adverse effects to the integrity of the walls or banks of the river; and

(d)in such a manner as to cause as little inconvenience as is reasonably practicable to the GYPA.

Commencement Information

I1Sch. 14 para. 58 in force at 15.10.2020, see art. 1