xmlns:atom="http://www.w3.org/2005/Atom"
  1. Introductory Text

  2. PART 1 Preliminary

    1. 1.Citation and commencement

    2. 2.Interpretation

  3. PART 2 Principal Powers

    1. 3.Development consent etc. granted by the Order

    2. 4.Maintenance of authorised development

  4. PART 3 Operations

    1. 5.Operation of generating station

    2. 6.Limits of deviation

    3. 7.Benefit of Order

    4. 8.Defence to proceedings in respect of statutory nuisance

  5. PART 4 Streets

    1. 9.Temporary prohibition or restriction of use of streets

    2. 10.Agreements with street authorities

  6. PART 5 Supplemental powers

    1. 11.Discharge of water

  7. PART 6 Miscellaneous and General

    1. 12.Application of landlord and tenant law

    2. 13.Operational land for purposes of the 1990 Act

    3. 14.Felling or lopping of trees

    4. 15.Protective provisions

    5. 16.Certification of plans etc.

    6. 17.Procedure in relation to certain approvals etc.

    7. 18.Arbitration

  8. Signature

  9. SCHEDULES

    1. SCHEDULE 1

      AUTHORISED DEVELOPMENT

    2. SCHEDULE 2

      REQUIREMENTS

      1. 1.Interpretation

      2. 2.Commencement of the authorised development

      3. 3.Notice of commencement and completion of commissioning

      4. 4.Notice of commencement of commercial use

      5. 5.Detailed design

      6. 6.Landscaping and biodiversity management and enhancement

      7. 7.External lighting

      8. 8.Means of enclosure

      9. 9.Surface water drainage

      10. 10.Foul water drainage

      11. 11.Flood risk mitigation

      12. 12.Contaminated land and groundwater

      13. 13.Unexpected contamination

      14. 14.Archaeology

      15. 15.Protected species

      16. 16.Construction environmental management plan

      17. 17.Protection of highway surfaces

      18. 18.Construction traffic management plan

      19. 19.Travel plan - construction staff

      20. 20.Construction hours

      21. 21.Control of noise - construction

      22. 22.Control of noise - operation

      23. 23.Piling and penetrative foundation design

      24. 24.Restoration of land used temporarily for construction

      25. 25.Local liaison committee

      26. 26.Employment, skills and training plan

      27. 27.Decommissioning

      28. 28.Consultation on requirements

    3. SCHEDULE 3

      PROCEDURE FOR DISCHARGE OF REQUIREMENTS

      1. 1.Applications made under Requirements

      2. 2.Further information

      3. 3.Fees

      4. 4.Appeals

    4. SCHEDULE 4

      STREETS SUBJECT TO TEMPORARY PROHIBITION OR RESTRICTION OF USE

    5. SCHEDULE 5

      PROTECTIVE PROVISIONS

      1. PART 1 Protection for operators of electronic communications code networks

        1. 1.The provisions of this Part have effect for the protection...

        2. 2.In this Part— “the 2003 Act” means the Communications Act...

        3. 3.(1) Subject to sub-paragraphs (2) to (4), if as the...

        4. 4.This Part does not apply to— (a) any apparatus in...

        5. 5.Nothing in this Part effects the provisions of any enactment...

  10. Explanatory Note