- Latest available (Revised)
- Original (As made)
There are currently no known outstanding effects for the The Reinforcement to the North Shropshire Electricity Distribution Network Order 2020.
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
You searched for provisions that are applicable to England. The matching provisions are highlighted below. Where no highlighting is shown the matching result may be contained within a footnote.
PART 5 POWERS OF ACQUISITIONPrevious MatchNext Match
17.Compulsory acquisition of rights: incorporation of the mineral codePrevious MatchNext Match
19.Statutory authority to override easements and other rightsPrevious MatchNext Match
20.Time limit for exercise of authority to acquire rights compulsorilyPrevious MatchNext Match
23.Acquisition of subsoil or airspace onlyPrevious MatchNext Match
24.Modification of Part 1 of the 1965 ActPrevious MatchNext Match
26.Temporary use of land for carrying out the authorised developmentPrevious MatchNext Match
27.Temporary use of land for maintaining the authorised developmentPrevious MatchNext Match
30.Recovery of costs of new connectionsPrevious MatchNext Match
SCHEDULE 1Previous MatchNext Match
AUTHORISED DEVELOPMENTPrevious MatchNext Match
A nationally significant infrastructure project, as defined in sections 14(1)(b)...Previous MatchNext Match
OSWESTRY SUBSTATION (Associated Development) Work No. 1 Works at Oswestry...Previous MatchNext Match
132kV UNDERGROUND CABLE (Associated Development) Work No. 2 the construction...Previous MatchNext Match
132kV OVERHEAD LINE (Nationally Significant Infrastructure Project) Work No. 3...Previous MatchNext Match
LOWER VOLTAGE DIVERSIONS (Associated Development) Work No.4A the removal of...Previous MatchNext Match
WEM SUBSTATION (Associated Development) Work No.5 —Works at Wem substation...Previous MatchNext Match
SCHEDULE 2Previous MatchNext Match
SCHEDULE 4Previous MatchNext Match
MODIFICATION OF THE COMPENSATION AND COMPULSORY PURCHASE ENACTMENTS FOR CREATION OF NEW RIGHTSPrevious MatchNext Match
SCHEDULE 5Previous MatchNext Match
LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKENPrevious MatchNext Match
SCHEDULE 6Previous MatchNext Match
PROTECTIVE PROVISIONSPrevious MatchNext Match
PART 1 FOR THE PROTECTION OF OPERATORS OF ELECTRONIC COMMUNICATIONS CODE NETWORKSPrevious MatchNext Match
1.(1) For the protection of any operator, the following provisions...Previous MatchNext Match
2.The exercise of the powers of article 29 (statutory undertakers)...Previous MatchNext Match
3.(1) Subject to sub-paragraphs (2) to (4), if as the...Previous MatchNext Match
4.This Part of this Schedule does not apply to— Previous MatchNext Match
5.Nothing in this Part of this Schedule affects the provisions...Previous MatchNext Match
PART 2 FOR THE PROTECTION OF ELECTRICITY, GAS, WATER AND SEWERAGE UNDERTAKERSPrevious MatchNext Match
6.For the protection of the statutory undertakers referred to in...Previous MatchNext Match
7.In this Part of this Schedule— “alternative apparatus” means alternative...Previous MatchNext Match
8.This Part of this Schedule does not apply to apparatus...Previous MatchNext Match
9.Regardless of any provision in this Order or anything shown...Previous MatchNext Match
10.(1) If, in the exercise of the powers conferred by...Previous MatchNext Match
11.(1) Not less than 28 days before starting the execution...Previous MatchNext Match
12.(1) Subject to the following provisions of this paragraph, the...Previous MatchNext Match
PART 3 FOR THE PROTECTION OF NETWORK RAILPrevious MatchNext Match
13.The following provisions of this Part have effect, unless otherwise...Previous MatchNext Match
14.In this Part— “construction” includes execution, placing, alteration and reconstruction...Previous MatchNext Match
15.(1) Where under this Part Network Rail is required to...Previous MatchNext Match
16.(1) The undertaker must not exercise the powers conferred by...Previous MatchNext Match
17.(1) The undertaker must before commencing construction of any specified...Previous MatchNext Match
18.(1) Any specified work and any protective works to be...Previous MatchNext Match
19.The undertaker must— (a) at all times afford reasonable facilities...Previous MatchNext Match
20.Network Rail must at all times afford reasonable facilities to...Previous MatchNext Match
21.(1) If any permanent or temporary alterations or additions to...Previous MatchNext Match
22.The undertaker must repay to Network Rail all reasonable fees,...Previous MatchNext Match
23.(1) In this paragraph— “EMI” means, subject to sub-paragraph (2),...Previous MatchNext Match
24.If at any time after the completion of a specified...Previous MatchNext Match
25.The undertaker must not provide any illumination or illuminated sign...Previous MatchNext Match
26.Any additional expenses which Network Rail may reasonably incur in...Previous MatchNext Match
27.(1) The undertaker must pay to Network Rail all reasonable...Previous MatchNext Match
28.Network Rail must, on receipt of a request from the...Previous MatchNext Match
29.In the assessment of any sums payable to Network Rail...Previous MatchNext Match
30.The undertaker and Network Rail may, subject in the case...Previous MatchNext Match
31.Nothing in this Order, or in any enactment incorporated with...Previous MatchNext Match
32.The undertaker must give written notice to Network Rail if...Previous MatchNext Match
33.The undertaker must no later than 28 days from the...Previous MatchNext Match
PART 4 FOR THE PROTECTION OF CANAL & RIVER TRUSTPrevious MatchNext Match
35.Powers requiring the Trust's consentPrevious MatchNext Match
36.Approval of plans, protective works etc.Previous MatchNext Match
41.Access to work – provision of informationPrevious MatchNext Match
44.Repayment of the Trust's fees, etc.Previous MatchNext Match
45.Making good of detriment; compensation and indemnity, etc.Previous MatchNext Match
PART 5 FOR THE PROTECTION OF NATIONAL GRID AS ELECTRICITY UNDERTAKERPrevious MatchNext Match
PART 6 FOR THE PROTECTION OF HIGHWAYS ENGLANDPrevious MatchNext Match
SCHEDULE 7Previous MatchNext Match
PROCEDURE FOR DISCHARGE OF REQUIREMENTSPrevious MatchNext Match
SCHEDULE 9Previous MatchNext Match
DOCUMENTS TO BE CERTIFIEDPrevious MatchNext Match
The Book of Reference listed below— Table 5 (1) Application...Previous MatchNext Match
The Land Plans listed below— Table 6 (1) Application document...Previous MatchNext Match
The Works Plans listed below— Table 7 (1) Application documents...Previous MatchNext Match
The Access and Rights of Way Plans listed below— Table...Previous MatchNext Match
The Plans of Important Hedgerows Affected Table 9 (1) Application...Previous MatchNext Match
The additional documents listed below— Table 10 (1) Application documents...Previous MatchNext Match
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: