Rail SupportU.K.

38.  The undertaker must appoint a rail freight co-ordinator at least 3 months prior to the submission of the application for approval of GRIP 3 referred to in paragraph (1) of requirement 40 (rail provision milestones) who must report to the local planning authority no less than once a quarter on—

(a)the progress towards meeting the rail provision milestones;

(b)the progress of the rail terminal works; and

(c)the operation of the rail terminal when open including—

(i)the appointment of a rail operator to operate the rail terminal;

(ii)the amount of rail freight usage of the rail terminal;

(iii)the number of trains using the rail terminal;

(iv)the warehousing receiving or sending goods through the rail terminal; and

(v)the amount of goods being received or sent through the rail terminal by freight handlers not occupying the warehousing.