- Latest available (Revised)
- Original (As made)
This is the original version (as it was originally made). This item of legislation is currently only available in its original format.
Article 3
In the County of Kent a nationally significant infrastructure project as defined in sections 14(1)(a) and 15 of the 2008 Act and associated development within the meaning of s115(2) of the 2008 Act—
Work No. 1- An electricity generating station (the K3 Generating Station) with a gross installed generating capacity of up to 75MW and capacity to process up to 657,000 tonnes of waste per annum, comprising the following works—
(a)tipping hall;
(b)waste fuel bunker;
(c)boiler hall;
(d)flue gas treatment building;
(e)turbine hall housing steam turbine and generator;
(f)air cooled condenser;
(g)stack and associated emissions monitoring system;
(h)electricity substation;
(i)stores and utilities;
(j)administration office;
(k)fire water tanks;
(l)stores;
(m)weighbridges, gatehouses, fuel tank, raw water tank, vehicle ramps, diesel generators.
Work No. 1A – Installation of grid connection for Work No 1.
Work No. 1B – Installation of steam connection for Work No 1.
Associated development within the meaning of section 115(2) of the 2008 Act in connection with those works including—
Work No. 1C - Alteration of existing private access road to construct, use and maintain Work No 1.
Work No. 1D - Creation of a temporary construction compound and laydown area for the construction of Work No 1.
Work No. 1E - Construction and operation of a surface water outfall for Work No. 1.
In connection with and in addition to Work No. 1 to the extent that it does not otherwise form part of that work, further associated development including—
(a)pipe racks and pipe runs;
(b)external lighting;
(c)fencing, boundary treatment and other means of enclosure;
(d)signage;
(e)CCTV and other security measures;
(f)surface and foul water drainage facilities;
(g)potable water supply;
(h)new telecommunications and utilities apparatus and connections;
(i)hard and soft landscaping;
(j)biodiversity enhancement measures;
(k)works to permanently alter the position of existing telecommunications and utilities apparatus and connections;
(l)works for the protection of buildings and land affected by the authorised development;
(m)site establishment and preparation works, including site clearance (including temporary fencing and vegetation removal), earthworks (including soil stripping and storage and site levelling) and excavations, the creation of temporary construction access points and the temporary alteration of the position of services and utilities apparatus and connections;
(n)establishment of temporary construction compounds, vehicle parking areas, materials storage and laydown areas, construction related buildings, structures, plant and machinery, lighting and fencing, internal haul routes and wheel wash facilities;
and, to the extent that it does not form part of such works, further associated development comprising such other works as (i) may be necessary or expedient for the purposes of or in connection with the relevant part of the authorised development and (ii) fall within the scope of the works assessed in the environmental statement.
Article 3
1.—(1) In this Schedule—
“approved Landscape Masterplan” means the K3 Generating Station approved Landscape Masterplan listed in Part 2 of Schedule 2;
“approved plans” means any approved plans or other plans, details, schemes or other documents which require approval by the relevant planning authority pursuant to any requirement or which are already approved and listed in Part 2 of Schedule 2;
“commencement” means beginning to carry out any material operation, as defined in section 155 of the 2008 Act (which explains when development begins), other than permitted preliminary works, comprised in or carried out for the purposes of the authorised development; and “commence” and other cognate expressions are to be construed accordingly;
“Kemsley Paper Mill” means the paper mill on the land immediately adjacent to the Order land at Sittingbourne, Kent operated by DS Smith Limited;
“means of enclosure” means fencing, walls or other means of boundary treatment and enclosure;
“permitted preliminary works” means site clearance work, survey work, the erection of any temporary means of enclosure, the preparation of facilities for the use of the contractor, the temporary display of site notices and advertisements and the provision of site security, and archaeological field work, investigations for the purpose of assessing ground conditions, remedial work in respect of any contamination or other adverse ground conditions, and the diversion and laying of services, provided that no permitted preliminary works will give rise to any materially new or materially different effects from those assessed in the environmental statement;
“rail and water transportation strategy” means the rail and water transportation strategy certified by the Secretary of State under article 16.
(2) A reference in this Schedule to an agreement, approval, consent, notice, report, scheme, submission or any other form of communication is a reference to that form of communication in writing.
(3) A reference in this Schedule to details, a method statement, a plan, a programme, a scheme or any other document approved by the planning authority is a reference to that document including any amendments subsequently approved by the relevant planning authority.
2. The authorised development must commence within five years of the date on which this Order comes into force.
3.—(1) Notice of commencement of commissioning of Work No 1 must be given to the relevant planning authority within 7 days of the date on which commissioning is commenced.
(2) Notice of completion of commissioning of Work No 1 must be given to the relevant planning authority within 7 days of the date on which commissioning is completed.
4.—(1) Within six months after it notifies the relevant planning authority that it intends to decommission the K3 Generating Station, the undertaker must submit to the relevant planning authority for its approval a written decommissioning environmental management plan for that generating station.
(2) Decommissioning works must not be carried out until the relevant planning authority has approved the scheme.
(3) The decommissioning environmental management plan submitted and approved must include details of—
(a)the buildings to be demolished;
(b)the means of removal of the materials resulting from the decommissioning works;
(c)the phasing of the demolition and removal works;
(d)all measures necessary for the protection from the potential environmental effects pursuant to decommissioning;
(e)any restoration works to restore the Order land to a condition agreed with the relevant planning authority;
(f)the phasing of any restoration works;
(g)a timetable for the implementation of the scheme.
(4) The undertaker must implement the scheme as approved and is responsible for the costs of the decommissioning works.
5.—(1) All fuels, oils and other liquids with the potential to contaminate the Order land shall be stored in a secure bonded area in order to prevent any accidental or unauthorised discharge to the ground.
(2) The area for storage shall not drain to any surface water system.
(3) Where it is proposed to store more than 200 litres of any type of oil must be stored in accordance with the provisions of the Control of Pollution (Oil Storage) (England) Regulations 2001(1).
(4) Where a drum or barrel has a capacity less than 200 litres a drip tray capable of retaining 25% of the maximum capacity of the drum or barrel may be used in lieu of storing the drum or barrel in the secure bonded area.
6. The K3 Generating Station must be operated in accordance with the approved K3 rail and water transportation strategy.
7.—(1) With respect to any approved plans, the undertaker may submit to the relevant planning authority for approval any amendments to the approved plans and following any such approval by the relevant planning authority the approved plans are to be taken to include the amendments approved pursuant to this paragraph.
(2) Approval under sub-paragraph (1) for any amendments to the parameters must not be given except where it has been demonstrated to the satisfaction of the relevant planning authority that the subject-matter of the approval sought does not give rise to any materially new or materially different environmental effects in comparison with the authorised development as approved (as identified in the environmental statement).
8.—(1) No work involving excavations shall take place within 3 metres of gas apparatus belonging to Southern Gas Networks PLC unless the undertaker has first obtained written consent from Southern Gas Networks PLC for those works to proceed.
(2) The undertaker shall provide such information as Southern Gas Networks PLC may reasonably require in order for it to respond to a request for consent under sub-paragraph (1).
9. The authorised development must be carried out in accordance with the K3 Generation Station approved plans and documents as listed in Part 2 of this Schedule.
10.—(1) The number of Heavy Goods Vehicle Movements to and from the K3 Generating Station shall not exceed 348 movements per day until the following have been submitted to and, after consultation with the relevant highway authority, approved by the relevant planning authority:
(a)a written operational traffic routing and management plan; and,
(b)a written travel plan for operational staff.
(2) The plan submitted and approved under sub-paragraph (1)(a) must be in accordance with the draft K3 operational traffic routing and management plan certified by the Secretary of State under article 16.
(3) The plan submitted and approved under sub-paragraph (1)(b) must be in accordance with the draft K3 travel plan certified by the Secretary of State under article 16.
(4) The plans referred to in sub-paragraphs (1)(a) and (1)(b) must be implemented as approved.
(5) Subject to paragraph (1), the total maximum number of Heavy Goods Vehicle Movements to and from the K3 Generating Station shall not exceed a combined total of 416 movements per day subject to any prior written variation as approved by the relevant planning authority
(6) Sub-paragraphs (1) to (5) do not apply to waste deliveries originating from and returning to the railway depot at Ridham Docks accessing and egressing the K3 Generating Station by the use of Ridham Dock Road.
11.—(1) All trees and shrubs planted under the approved Landscape Masterplan shall be maintained for a period of 5 years.
(2) Any trees or shrubs that either die, are lost, damaged or become diseased during this 5 year period shall be replaced with a tree or shrub of the same species within the next available planting season.
12. All surface water drainage from the authorised development discharging to a local water course shall be attenuated for a 1:100 year return storm with a limited discharge of 7 litres per second per hectare or the equivalent run off from a greenfield site for a 1:2 storm.
13.—(1) Within 12 months of ceasing to supply heat and/or power to the Kemsley Paper Mill, the undertaker must submit to the relevant planning authority for its approval a strategy (“the CHP strategy”).
(2) The CHP strategy submitted and approved must—
(a)consider the opportunities that reasonably exist at the time of submission for the export of heat and/or power from the K3 Generating Station to other users; and
(b)include a list of actions (if any) that the undertaker is reasonably to take (without material additional cost to the undertaker) to increase the potential for the export of heat from the K3 Generating Station to other users.
(3) The undertaker must take such actions as are included, within the timescales specified, in the approved CHP strategy.
(1) Title | (2) Reference | (3) Revision |
---|---|---|
Environmental Statement | March 2010 | |
ES Addendum (Air Quality) | June 2013 | |
ES Chapter 10 – Hydrology and Flood Risk – Supplementary Report | May 2017 | |
ES Addendum | May 2018 | |
Design and Access Statement | March 2010 | |
Surface Water Management and Foul Drainage Design Philosophy | December 2016 | |
Ecological Mitigation and Management Plan | JPP1804-MP-001d | July 2013 |
Flood Risk Assessment | May 2019 | |
Proposed (Permitted) Site Location Plan | 16315/A0/P/0060 | Rev N |
Proposed Site Layout | 16315/A1/P/0100 | Rev U |
Proposed Building Layout | 16315/A0/P/0105 | Rev L |
Boundary Treatment | 16315/A0/P/0106 | Rev R |
South East Elevation | 16315/A1/P/0110 | Rev U |
North East Elevation | 16315/A1/P/0111 | Rev T |
South West Elevation | 16315/A1/P/0112 | Rev U |
North West Elevation | 16315/A1/P/0113 | Rev T |
Proposed Structure for Air Cooled Condenser (URC) Elevations | 16315/A1/P/0121 | Rev N |
Main Building – Proposed South East Elevation | 16315/A0/P/0125 | Rev K |
Main Building – Proposed North East Elevation | 16315/A1/P/0126 | Rev K |
Main Building – Proposed South West Elevation | 16315/A1/P/0127 | Rev L |
Main Building – Proposed North West Elevation | 16315/A0/P/0128 | Rev K |
Site Layout and Access | 16315/A1/P/0160 | Rev K |
Typical Office and Staff Amenities Building (UYA) Floor Plans | 16315/A1/P/0171 | Rev H |
Proposed Gatehouse Floor Plan | 16315/A2/P/0172 | Rev L |
Site Sections | 16315/A0/0250 | Rev J |
Proposed Drainage Layout | 16315/A0/0301 | Rev J |
Proposed Levels Site Plan | 16315/A1/0600 | Rev H |
Illustrative Visual 1 of 7 | 16315/P/0150 | Rev R |
Illustrative Visual 2 of 7 | 16315/P/0151 | Rev P |
Illustrative Visual 3 of 7 | 16315/P/0152 | Rev O |
Illustrative Visual 4 of 7 | 16315/P/0153 | Rev Q |
Illustrative Visual 5 of 7 | 16315/P/0154 | Rev O |
Illustrative Visual 6 of 7 | 16315/P/0155 | Rev O |
Illustrative Visual 7 of 7 | 16315/P/0156 | Rev R |
Landscape Masterplan | 16315/A1/4.21 | Rev M |
Fuel Bunker Level +2.0000m | 16315/A1/P/0220 | Rev D |
Fuel Bunker Level +20.000m and Level +36.000m | 16315/A1/P/0221 | Rev E |
Fuel Bunker Section A-A | 16315/A1/P/0222 | Rev C |
Fuel Bunker Section B-B | 16315/A0/P/0223 | Rev C |
Tipping Hall Layout Level +2.000m | 16315/A1/P/0201 | Rev E |
Tipping Hall Section A-A | 16315/A1/P/0202 | Rev D |
Overall Roof Layout Comparison Drawing | 16315/A1/P/0200 | Rev H |
Lighting Discharges Report | 20020117LXI0019 | Rev C |
External Lighting Technical Submission | 20020117LXJ0922 | Rev I |
External Lighting Drawing | 20020117LXG0907 | Rev H |
K3 External Lighting Strategy | ECO00047 Fig1 | - |
Access Road - Proposed Proposed Internal Access Layout | 9163-0135-01-JNY9060 | Rev 01 |
K3 Employment Strategy | March 2012 |
Article 18
1. This Schedule applies to an application made by the undertaker to the planning authority (referred to in this Schedule as “the authority”) for an approval, consent or agreement required by any of the requirements.
2.—(1) The authority must give written notice to the undertaker of its decision on the application before the end of the decision period.
(2) In sub-paragraph (1), “the decision period” means—
(a)where the authority does not give written notice under paragraph 3(1) or (2) requiring further information, the period of eight weeks from the later of—
(i)the day immediately following the day on which the authority receives the application, and
(ii)the day on which the authority receives the fee payable under paragraph 4; or
(b)where the authority gives written notice under paragraph 3(1) or (2) requiring further information, the period of eight weeks from the day immediately following the day on which the undertaker provides the further information; or
(c)such longer period as may be agreed in writing by the undertaker and the authority.
3.—(1) If the authority considers that it requires further information to make a decision on the application, it must give written notice to the undertaker specifying the further information required within seven business days from the day on which it receives the application.
(2) If the relevant requirement requires that authority to consult a person (referred to in this Schedule as a “consultee”) in relation to the application—
(a)the authority must consult the consultee within five business days from the day on which it receives the application;
(b)if the consultee considers that it requires further information to respond to the consultation, it must so notify the authority, specifying what further information is required, within 18 business days from the day on which the authority received the application; and
(c)within five business days from the day on which it receives any such notification from the consultee, the authority must give written notice to the undertaker specifying the further information required by the consultee.
(3) If the authority, after consultation with any consultee, considers that further information provided by the undertaker in response to a written notice from the authority under sub-paragraph (1) or (2) is not sufficient to allow it to make a decision on the application, it must give written notice to the undertaker specifying what further information is still required, within seven business days from the day on which the undertaker provided the information.
(4) If the authority does not give written notice in accordance with sub-paragraph (1), (2) or (3), it is not entitled to request any additional information in relation to the application without the prior agreement in writing of the undertaker.
4.—(1) The undertaker must pay the authority a fee of £116, or such greater fee as for the time being is payable to the authority in respect of an application for the discharge of a condition imposed on a grant of planning permission, in respect of each application.
(2) The authority must refund the fee paid under sub-paragraph (1) to the undertaker, within the relevant period, if it—
(a)rejects the application as being invalidly made;
(b)fails to give the written notice required by paragraph 2(1).
(3) Sub-paragraph (2) does not apply if, within the relevant period, the undertaker agrees in writing that the authority may retain the fee paid and credit it in respect of a future application.
(4) In sub-paragraphs (2) and (3) “the relevant period” means the period of eight weeks from, as the case may be—
(a)the day on which the authority rejects the application as being invalidly made;
(b)the day after the day on which the decision period expires.
5.—(1) The undertaker may appeal to the Secretary of State against—
(a)the authority’s refusal of an application;
(b)the authority’s grant subject to conditions of an application;
(c)the authority’s failure to give the written notice required by paragraph 2(1);
(d)a written notice given by the authority under paragraph 3(1), (2) or (3).
(2) In order to appeal, the undertaker must, within 10 business days from the relevant day, send the Secretary of State the following documents—
(a)its grounds of appeal;
(b)a copy of the application submitted to the authority;
(c)any supporting documentation which it wishes to provide.
(3) In sub-paragraph (2), “the relevant day” means—
(a)in the case of an appeal under sub-paragraph (1)(a) or (b), the day on which the undertaker is notified by the authority of its decision;
(b)in the case of an appeal under sub-paragraph (c), the day after the day on which the decision period expires;
(c)in the case of an appeal under sub-paragraph (1)(d), the day on which the undertaker receives the authority’s notice.
(4) At the same time as it sends the documents mentioned in sub-paragraph (2) to the Secretary of State, the undertaker must send copies of those documents to the authority and any consultee.
(5) As soon as reasonably practicable following receipt of the documents mentioned in sub-paragraph (2), the Secretary of State must—
(a)appoint a person (referred to in this Schedule as “the appointed person”) to determine the appeal on his behalf;
(b)give written notice to the undertaker, the authority and any consultee of the appointment and of the appointed person’s address for correspondence in relation to the appeal.
(6) Within 20 business days from the day on which the Secretary of State gives notice under sub-paragraph (5)(b), the authority and any consultee—
(a)may submit written representations in respect of the appeal to the appointed person; and
(b)must, at the same time, send a copy of any such representations to the undertaker and (if applicable) to each other.
(7) Within 10 business days from the last day on which representations are submitted to the appointed person under sub-paragraph (6), any party—
(a)may make further representations to the appointed person in response to the representations of another party; and
(b)must, at the same time, send a copy of any such further representations to each other party.
6.—(1) The appointed person may—
(a)allow or dismiss the appeal;
(b)reverse or vary any part of the authority’s decision, irrespective of whether the appeal relates to that part;
(c)make a decision on the application as if it had been made to the appointed person in the first instance.
(2) The appointed person—
(a)if he considers that he requires further information to make a decision on the appeal, may by written notice require any party to provide such further information to him and to each other party by a specified date;
(b)if he gives such a notice, must—
(i)at the same time send a copy of it to each other party, and
(ii)allow each party to make further representations in relation to any further information provided in response to the notice, within 10 business days from the day on which it is provided.
(3) The appointed person may waive or extend any time limit (including after it has expired) for the provision of representations or information in relation to an appeal.
7.—(1) The decision of the appointed person on an appeal may not be challenged except by proceedings for judicial review.
(2) If the appointed person grants approval of an application, that approval is to be taken as if it were an approval granted by the authority in relation to the application.
(3) Subject to sub-paragraph (4), the undertaker must pay the reasonable costs of the appointed person incurred in deciding the appeal.
(4) On written application by the authority or the undertaker, the appointed person may make a direction as to the costs of the parties to the appeal and of the appointed person, including imposing an obligation on any party to pay all or part of such costs to the party which incurred them.
(5) In considering an application under sub-paragraph (4) the appointed person must have regard to the National Planning Practice Guidance: Advice on planning appeals and the award costs or any circular or guidance which may from time to time replace it.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: