4.  Maximum parameters for length (m), width (m) or diameter (m) exclude external support structures such as (but not limited to) ladders, platforms, external piping and structural supports.E+W+S

Table 6

(1)

Component

(2)

Length (m)

(3)

Width (m) or diameter (m)

(4)

Height (m) above ground level (AGL) (in the case that the finished ground level is 2.8m AOD)

(5)

Height (M) AOD (in all cases)

Gas Turbine Hall (Work No. 1A)225031.834.6
Steam Turbine Hall (Work No. 1A)504034.837.6
HRSG Building (Work No. 1A)285055.858.6
Absorber (Work No. 1C) (in the case that a single absorber is developed)16 (Note 4)43 (Note 4)98.8101.6
Absorber Stack (Work No. 1C) (in the case that a single absorber is developed)-6.7104.8107.6
Twin Absorbers (Work No. 1C) (in the case that two absorbers are developed)-19.0 (Note 4)8082.8
Twin Absorber Stacks (Work No. 1C) (in the case that two absorbers are developed)-6.795.598.3
HRSG Stack (Work No. 1A)-8.084.887.6
Carbon Dioxide stripper (Work No. 1C)-15.0 (Note 4)6365.8

Table 7

(1)

Component

(2)

Length (m)

(3)

Width (m)

(4)

Height (m) above ground level (AGL)

(5)

Height (m) AOD

A18 Gatehouse (Work No. 8B)6745.5

Commencement Information

I1Sch. 11 para. 4 in force at 29.12.2022, see art. 1

Back to top

Options/Help

You have chosen to open The Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Instrument as a PDF

The Whole Instrument you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?