The Keadby 3 (Carbon Capture Equipped Gas Fired Generating Station) Order 2022

4.  Maximum parameters for length (m), width (m) or diameter (m) exclude external support structures such as (but not limited to) ladders, platforms, external piping and structural supports.E+W+S

Table 6

(1)

Component

(2)

Length (m)

(3)

Width (m) or diameter (m)

(4)

Height (m) above ground level (AGL) (in the case that the finished ground level is 2.8m AOD)

(5)

Height (M) AOD (in all cases)

Gas Turbine Hall (Work No. 1A)225031.834.6
Steam Turbine Hall (Work No. 1A)504034.837.6
HRSG Building (Work No. 1A)285055.858.6
Absorber (Work No. 1C) (in the case that a single absorber is developed)16 (Note 4)43 (Note 4)98.8101.6
Absorber Stack (Work No. 1C) (in the case that a single absorber is developed)-6.7104.8107.6
Twin Absorbers (Work No. 1C) (in the case that two absorbers are developed)-19.0 (Note 4)8082.8
Twin Absorber Stacks (Work No. 1C) (in the case that two absorbers are developed)-6.795.598.3
HRSG Stack (Work No. 1A)-8.084.887.6
Carbon Dioxide stripper (Work No. 1C)-15.0 (Note 4)6365.8

Table 7

(1)

Component

(2)

Length (m)

(3)

Width (m)

(4)

Height (m) above ground level (AGL)

(5)

Height (m) AOD

A18 Gatehouse (Work No. 8B)6745.5

Commencement Information

I1Sch. 11 para. 4 in force at 29.12.2022, see art. 1