- Latest available (Revised)
- Original (As made)
This is the original version (as it was originally made). This item of legislation is currently only available in its original format.
Statutory Instruments
Electricity
Made
29th March 2022
Coming into force in accordance with regulation 1(2)
The Secretary of State has before making these Regulations—
(a)consulted the persons listed in sections 24(1)(a) to (g) and 40(2)(a) and (b) of the Energy Act 2013(1) (“the 2013 Act”) and such other persons as the Secretary of State considered it appropriate to consult; and
(b)had regard to the matters in section 5(2) of the 2013 Act.
The Secretary of State, in exercise of the powers conferred by sections 6(1) and (6), 9(1) and (2), 27, 30, and 40(1) of the 2013 Act, makes the following Regulations.
In accordance with sections 6(8) and 40(5) of the 2013 Act, a draft of this instrument was laid before Parliament and approved by a resolution of each House of Parliament.
1.—(1) These Regulations may be cited as the Electricity Supplier Payments (Amendment) Regulations 2022.
(2) These Regulations come into force on the day after the day on which these Regulations are made, except for regulation 2 which comes into force on 1st April 2022.
2. In paragraph (7)(a) of regulation 23 of the Contracts for Difference (Electricity Supplier Obligations) Regulations 2014(2)—
(a)omit paragraph (i);
(b)renumber paragraph (ii) as paragraph (i);
(c)in paragraph (i) as so renumbered, omit “or during any subsequent operational cost period; and”; and
(d)after paragraph (i) as so renumbered, insert—
“(ii)0.0879 per megawatt hour for any day during the operational cost period that begins on 1st April 2022;
(iii)0.0994 per megawatt hour for any day during the operational cost period that begins on 1st April 2023;
(iv)0.1089 per megawatt hour for any day during the operational cost period that begins on 1st April 2024 or during any subsequent operational cost period; and”.
3.—(1) In paragraph (2) of regulation 9 of the Electricity Capacity (Supplier Payment etc.) Regulations 2014(3) for “£7,472,000 where year Y is the relevant financial year commencing in 2021 or any subsequent financial year” substitute—
“as follows—
(a)£6,954,000 where year Y is the relevant financial year commencing in 2022;
(b)£7,382,000 where year Y is the relevant financial year commencing in 2023;
(c)£7,734,000 where year Y is the relevant financial year commencing in 2024 or any subsequent financial year.”.
(2) Paragraph (1) does not apply in respect of any financial year commencing before 2022.
(3) In paragraph (2) “financial year” means a period of one year commencing with 1st April.
Greg Hands
Minister for Business, Energy and Clean Growth
Department for Business, Energy and Industrial Strategy
29th March 2022
(This note is not part of the Regulations)
These Regulations make amendments to the Contracts for Difference (Electricity Supplier Obligations) Regulations 2014 (S.I. 2014/2014) (the “ESO Regulations”) and the Electricity Capacity (Supplier Payment etc.) Regulations 2014 (S.I. 2014/3354) (the “Supplier Payment Regulations”). Those Regulations impose an obligation on electricity suppliers to pay an “operational costs levy” (as per the ESO Regulations) and a “settlement costs levy” (as per the Supplier Payment Regulations) in order to fund the operational costs of the respective schemes.
This instrument makes the following changes. Firstly, regulation 2 amends the rate for the annual operational costs levy in the ESO Regulations from 1st April 2022, and for the next two operational cost periods and subsequent such periods. Secondly, regulation 3(1) provides an amended figure for the settlement costs levy in regulation 9(2) of the Supplier Payment Regulations from 1st April 2022, for the next two years and subsequent financial years. The revised figure does not apply in respect of any financial year before 2022. A financial year for this purpose means a period of one year commencing with 1st April.
A full-impact assessment has not been produced for this instrument as no, or no significant impact on the private, voluntary or public sectors is foreseen.
S.I. 2014/2014; relevant amending instruments are S.I. 2018/449 and S.I. 2021/235.
S.I. 2014/3354; relevant amending instruments are S.I. 2018/449 and S.I. 2021/235.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including:
The data on this page is available in the alternative data formats listed: