Search Legislation

The Little Crow Solar Park Order 2022

 Help about what version

What Version

 Help about advanced features

Advanced Features

 Help about opening options

Opening OptionsExpand opening options

Changes over time for: Paragraph 1

 Help about opening options

Alternative versions:

Status:

Point in time view as at 27/04/2022.

Changes to legislation:

There are currently no known outstanding effects for the The Little Crow Solar Park Order 2022, Paragraph 1. Help about Changes to Legislation

InterpretationE+W+S

1.  In this Schedule—

BSMP” means battery safety management plan;

business days” means a day other than Saturday or Sunday which is not Christmas Day, Good Friday or a bank holiday under section 1 of the Banking and Financial Dealings Act 1971(1);

CEMPs” means construction environmental management plan and construction environmental management plan for biodiversity;

contaminated land” has the same meaning as that given in section 78A of the Environmental Protection Act 1990;

CTMP” means construction traffic management plan;

first export date” means the date on which the generating station first exports electricity to the Northern Powergrid network on a commercial basis;

landowner” means the freehold owner of the land within the Order limits on which the relevant part of Work No. 5 is constructed;

phase” means a defined section or part of the authorised development, the extent of which is shown in a scheme submitted to and approved by the local planning authority under requirement 5 (phases of authorised development); and

substation operator” means the operator of the substation from time to time constructed as part of Work No. 4.”

Commencement Information

I1Sch. 2 para. 1 in force at 27.4.2022, see art. 1