PART 6Notification of Completed Measures

Notification requirements for completed measures

25.  A measure is notified to the Administrator in accordance with this article if the notification—

(a)is made, in writing, by the participant that promoted the measure;

(b)is made after the measure is completed;

(c)is made on time within the meaning of article 26;

(d)indicates that the notification is made under this article;

(e)is not withdrawn by a notification made under article 28; and

(f)includes such other information relating to the measure as the Administrator may require.

Deadline for notification of completed measures

26.—(1) For the purposes of article 25, a notification of a measure is made on time if it is made—

(a)on or before the original deadline, which is—

(i)in the case of a measure completed in 2023, 31st January 2024;

(ii)in the case of a measure completed after 2023, the end of the first month following the month in which the measure is completed;

(b)following an application under article 27(1) which is approved by the Administrator, on or before the date determined by the Administrator under article 27(5)(a); or

(c)in the case of a measure falling within the 5% notification threshold for the participant (“the notifying participant”), before—

(i)the end of the third month after the original deadline, if the original deadline is before 1st April 2026; or

(ii)the end of June 2026, if the original deadline is after 31st March 2026.

(2) For the purposes of paragraph (1)(c), a measure falls within the 5% notification threshold for the notifying participant if—

(a)the measure is notified to the Administrator after the original deadline; and

(b)at the time the measure is notified, the result of the following formula is less than or equal to 0.05—

.

(3) In paragraph (2)—

“F” is the number of measures (also counting the measure being notified) which—

(a)

have the same original deadline as the measure being notified; and

(b)

are notified after the original deadline by—

(i)

the notifying participant; or

(ii)

any other participant that is a member of the same group as the notifying participant;

“G” is the number of measures which—

(a)

have the same original deadline as the measure being notified;

(b)

are the subject of an application under article 27(1) which is approved by the Administrator; and

(c)

are notified, after the original deadline and on or before the date determined by the Administrator under article 27(5)(a), by—

(i)

the notifying participant; or

(ii)

any other participant that is a member of the same group as the notifying participant;

“H” is the greater of 1 and the number of measures which—

(a)

have the same original deadline as the measure being notified; and

(b)

are notified on or before the original deadline by—

(i)

the notifying participant; or

(ii)

any other participant that is a member of the same group as the notifying participant.

(4) In this article, “original deadline” has the meaning given in paragraph (1)(a).

Applications for extension of time to notify

27.—(1) A participant may apply on or before 31st May 2026 to the Administrator in writing for a measure to be notified after the original deadline.

(2) An application under paragraph (1) must include—

(a)details of why the participant is seeking an extension of time to notify the measure; and

(b)such other information relating to the measure as the Administrator may require.

(3) The Administrator must reject the application if—

(a)the requirements in paragraph (2) are not met; or

(b)it is not satisfied that the participant has a reasonable excuse for seeking an extension of time to notify the measure.

(4) If the Administrator rejects the application, it must in writing notify the participant of the reasons for that decision.

(5) If the Administrator approves the application, it must—

(a)determine a date for the notification of the measure (“the new deadline”); and

(b)notify the participant in writing—

(i)of the new deadline; and

(ii)of the reasons for the date determined as the new deadline.

(6) The date determined by the Administrator under paragraph (5)(a) must—

(a)be a date falling after the original deadline and before 1st July 2026; and

(b)be determined having regard to—

(i)the reasons why the participant is seeking an extension of time to notify the measure; and

(ii)any guidance published by the Administrator under this article.

(7) Before the end of the 6 week period beginning with the commencement date, the Administrator must publish, on its website, guidance on how it will exercise its functions under this article.

(8) The Administrator may revise any guidance published under this article by publishing the revised guidance on its website.

(9) In this article, “original deadline” has the meaning given in article 26(1)(a).

Withdrawal of notifications

28.—(1) A participant may withdraw a notification made under article 25 by notifying the Administrator in writing.

(2) A notification under paragraph (1) must—

(a)be made by the participant that promoted the measure;

(b)be made on or before 30th June 2026; and

(c)include such information relating to the measure as the Administrator may require.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Memorandum

Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Impact Assessments

Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:

  • Why the government is proposing to intervene;
  • The main options the government is considering, and which one is preferred;
  • How and to what extent new policies may impact on them; and,
  • The estimated costs and benefits of proposed measures.
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources