The Town and Country Planning (Former RAF Scampton) (Accommodation for Asylum-Seekers etc.) Special Development Order 2024

 Help about what version

What Version

 Help about advanced features

Advanced Features

Changes over time for: The Town and Country Planning (Former RAF Scampton) (Accommodation for Asylum-Seekers etc.) Special Development Order 2024 (without Schedules)

 Help about opening options

Alternative versions:

Changes to legislation:

There are outstanding changes not yet made by the legislation.gov.uk editorial team to The Town and Country Planning (Former RAF Scampton) (Accommodation for Asylum-Seekers etc.) Special Development Order 2024. Any changes that have already been made by the team appear in the content and are referenced with annotations. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the legislation in the affected provisions. Use the ‘more’ link to open the changes and effects relevant to the provision you are viewing.

View outstanding changes

Changes and effects yet to be applied to :

Citation, commencement, extent and applicationE+W

1.—(1) This Order may be cited as the Town and Country Planning (Former RAF Scampton) (Accommodation for Asylum-Seekers etc.) Special Development Order 2024.

(2) This Order comes into force on 11th April 2024.

(3) This Order extends to England and Wales.

(4) This Order applies to the land at Former RAF Scampton, near Lincoln, Lincolnshire LN1 2ST, shown bounded externally by the outer edge of a bold red line on the Map (the “Order land”).

Commencement Information

I1Art. 1 in force at 11.4.2024, see art. 1(2)

InterpretationE+W

2.—(1) In this Order—

the 2015 Order” means the Town and Country (General Permitted Development) (England) Order 2015(1);

adjoining owner or occupier” means any owner or occupier of any land adjoining the Order land;

approved document” means any document listed in Schedule 1 (documents submitted by the Home Secretary), or any document in respect of which the Secretary of State has given subsequent approval, and where the Secretary of State—

(a)

gives subsequent approval in respect of a replacement for an approved document, the approved document is the document in respect of which such subsequent approval was most recently given;

(b)

gives variation approval in relation to an approved document, the approved document is the version of that document that reflects the cumulative effect of all the amendments to it in respect of which the Secretary of State has given such approval,

and if both subsequent approval as described in paragraph (a) and variation approval have been given in relation to an approved document, the approved document is the document or version that reflects the cumulative effect of all approvals, of either kind, that have been given, and references to any particular approved document are to be construed according to the same principles;

authorised development” has the meaning given in article 4(1) (grant of temporary planning permission);

CEMP” means a construction and environmental management plan submitted and approved in accordance with condition 15 (construction and environmental management plan);

construction” includes installation, provision, operation, maintenance, improvement or alteration, decommissioning or removal (demolition), or any other building or engineering operations, and “constructed” is to be construed accordingly;

contamination expert” means a person—

(a)

with suitable knowledge, skills and experience in relation to the assessment and mitigation of relevant contamination risks, and

(b)

who is a registered Specialist in Land Condition(2), or holds another qualification indicating a similar level of expertise in relation to such risks;

existing” means, in relation to anything on the Order land, that it was present on the Order land on 10th April 2024;

heritage assets” means the following buildings or structures at Former RAF Scampton—

(a)

the four “C-type” aircraft hangars;

(b)

the Officers’ Mess;

(c)

the grave of Wing Commander Guy Gibson’s dog;

the Home Secretary” means the Secretary of State for the Home Department;

the Map” means the document numbered Figure 2 in Schedule 1;

Multi-Agency Forum” means the group to be established by the Home Secretary under condition 27 (Multi-Agency Forum);

OMP” means an operational management plan submitted and approved in accordance with sub-paragraph (1) of condition 21 (OMP: establishment and review);

Order land” has the meaning given in article 1(4);

reinstatement works” means development(3) for which planning permission is granted by article 4(1)(c);

relevant contamination risk” means a risk to human health or the environment posed by hazardous substances including gases, vapour concentrations and radiological contamination in, on, under or over the Order land;

relevant duty” means a duty imposed by an enactment (other than this Order) that applies to the Home Secretary when the Home Secretary carries out relevant functions;

relevant functions” means providing, or arranging for the provision of, accommodation and support under section 4 (accommodation), section 95 (persons for whom support may be provided) or section 98 (temporary support) of the Immigration and Asylum Act 1999(4);

relevant ordnance risk” means a risk to human health or the environment associated with the presence of unexploded ordnance in, on, under or over the Order land;

relevant person” means a person who—

(a)

is male,

(b)

is at least 18 years old and no more than 64 years old,

(c)

has no dependants within the meaning of section 94(1) of the Immigration and Asylum Act 1999 (interpretation of Part VI)(5), and

(d)

is—

(i)

an asylum-seeker within the meaning of that section, or

(ii)

otherwise receiving accommodation or support under section 4 of that Act;

relevant risk” means a relevant contamination risk or a relevant ordnance risk;

remedial step” means any step, the taking of which by the Home Secretary secures compliance with a duty imposed on the Home Secretary, by an enactment (other than this Order) or a rule of common law, to prevent or mitigate a relevant risk;

resident service user” means a service user who is accommodated on the Order land;

the Secretary of State” means, except in the definition of “Home Secretary”, the Secretary of State for Levelling Up, Housing and Communities;

service user” means a person in respect of whom the Home Secretary carries out relevant functions;

site operator” means the person designated as such under condition 1 (site operator);

subsequent approval” means the Secretary of State’s approval, after the date on which this Order is made, in respect of a plan, report, scheme or programme that this Order requires or permits the Home Secretary to submit for the Secretary of State’s approval, where—

(a)

the plan, report, scheme or programme is submitted for such approval for the first time, or

(b)

approval is sought in respect of a replacement for such a plan, report, scheme or programme under sub-paragraph (3) of condition 2 (approved documents);

unsuitability criterion” means any of the criteria specified, on pages 17 to 22 of the Home Office publication “Allocation of asylum accommodation policy”, version 11.0, dated 12th February 2024(6), as making a person potentially unsuitable (either generally, or in certain circumstances) to be accommodated on an “ex-MoD site”, or to share a room;

variation approval” means the Secretary of State’s approval in respect of an amendment, proposed by the Home Secretary, to the details of a matter set out in an approved document.

(2) A reference in this Order to a numbered “condition” is to the paragraph that is so numbered in Schedule 3 (conditions subject to which planning permission is granted).

(3) A reference in this Order to the height of a building or other structure is a reference to its height when measured from ground level, and in this paragraph “ground level” means—

(a)the level of the surface of the ground adjoining the building or structure;

(b)if the level of the surface of the ground where the building or structure is situated or is to be situated is not uniform, the level of the highest part of the surface of the ground adjacent to it.

Commencement Information

I2Art. 2 in force at 11.4.2024, see art. 1(2)

Application of the 2015 OrderE+W

3.—(1) Subject to the provisions of this Order, the 2015 Order applies to the Order land.

(2) Planning permission granted by article 3(1) of the 2015 Order (permitted development) does not apply to development carried out in, on, under or over the Order land during the period beginning with 11th April 2024 and ending with 10th October 2027, unless it is—

(a)development of a class that is described as permitted development in Part 13 (water and sewerage), Part 15 (power related development) or Part 16 (communications) of Schedule 2 to the 2015 Order (permitted development rights);

(b)the replacement of a window or door as part of refurbishment of a building or structure.

(3) Planning permission granted by article 3(1) of the 2015 Order for development of a type specified in Schedule 2 to this Order that was carried out on or before 10th April 2024—

(a)ceases to apply on 11th April 2024;

(b)applies again on and from 11th April 2027, but only if, and to the extent that, the planning permission granted for it by article 3(1) of the 2015 Order would not, but for this Order, have ceased before that date.

Commencement Information

I3Art. 3 in force at 11.4.2024, see art. 1(2)

Grant of temporary planning permissionE+W

4.—(1) Subject to the provisions of this Order, planning permission is granted for—

(a)the making of any material change in the use of any buildings or other land of a type specified in paragraph 1 of Schedule 2;

(b)the carrying out of building, engineering or other operations of a type specified in paragraph 2 of Schedule 2;

(c)development comprised in—

(i)the cessation, decommissioning or removal of development within sub-paragraph (a) or (b);

(ii)the reversion of the Order land and any buildings in, on, under or over it to their previous lawful use

(“authorised development”).

(2) The planning permission granted by paragraph (1)—

(a)is subject to—

(i)the conditions specified in Schedule 3;

(ii)such additional conditions as the Secretary of State may impose when giving subsequent approval or variation approval under article 6 (authorised development: decisions of the Secretary of State);

(b)includes, as regards paragraphs (1)(a) and (b), planning permission for the retention and continued operation, after 10th April 2024, of development of a type specified in Schedule 2 that was first carried out on or before 10th April 2024 under planning permission granted by article 3(1) of the 2015 Order;

(c)does not include planning permission for any material change in use, or building, engineering or other operations to take place, in respect of any heritage asset, other than the works that are to be undertaken by virtue of sub-paragraph (2)(b) of condition 10 (fencing) or sub-paragraph (2) of condition 12 (heritage management scheme).

(3) The conditions referred to in paragraph (2)(a) apply to development within paragraph (2)(b) if and to the extent that it is retained and continues to operate after 10th April 2024, but they do not apply as regards its construction before that date.

(4) Authorised development may only be carried out by or on behalf of the Home Secretary.

(5) The planning permission granted by paragraph (1)(a) and (b) ceases at the end of 10th April 2027, and any development within those paragraphs must cease by that time.

(6) The planning permission granted by paragraph (1)(c) ceases at, and reinstatement works must be completed by, the end of 10th October 2027.

Commencement Information

I4Art. 4 in force at 11.4.2024, see art. 1(2)

Subsequent approval and variation approvalE+W

5.—(1) A replacement for an approved document has no effect for the purposes of this Order unless the Home Secretary has submitted it for subsequent approval under sub-paragraph (3) of condition 2, and the Secretary of State has given subsequent approval in respect of the replacement.

(2) An amendment to an approved document has no effect for the purposes of this Order unless the Home Secretary has sought, and the Secretary of State has given, variation approval in respect of that amendment.

(3) Where the Home Secretary submits a document for subsequent approval or seeks variation approval, the Home Secretary must make an application—

(a)to the Secretary of State in writing, signed by the site operator on behalf of the Home Secretary;

(b)including a copy of any document that it is proposed should be an approved document following the giving of subsequent approval or variation approval as requested.

(4) No subsequent approval or variation approval may be sought or given in respect of any replacement of, or amendment to, the Map.

Commencement Information

I5Art. 5 in force at 11.4.2024, see art. 1(2)

Authorised development: decisions of the Secretary of StateE+W

6.—(1) When giving or declining to give subsequent approval or variation approval, the Secretary of State must give the Home Secretary a written notice of the Secretary of State’s decision on the application made under article 5(3) (subsequent approval and variation approval).

(2) The Secretary of State may give subsequent approval or variation approval either unconditionally, or subject to conditions set out in a notice given under paragraph (1).

(3) The Secretary of State must not give—

(a)subsequent approval or variation approval;

(b)any other consent or agreement provided for under this Order or an approved document in relation to the authorised development

(each a “relevant approval”), unless the condition specified in paragraph (4) or the condition specified in paragraph (5) is satisfied.

(4) The condition is that the Secretary of State has concluded that—

(a)the giving of the relevant approval will not result in the authorised development having any impacts that are materially new, or materially different, as compared with the impacts that the Secretary of State took into account before making this Order,

(b)the authorised development will not, as a result of the relevant approval, be EIA development as defined in regulation 2(1) of the Town and Country Planning (Environmental Impact Assessment Regulations 2017(7) (the “2017 Regulations”), and

(c)development carried out as a result of the relevant approval will not otherwise give rise to any significant environmental effect.

(5) The condition is that the Secretary of State has directed under regulation 63(1) of the 2017 Regulations (exemptions) that the authorised development is exempt from the requirements of those Regulations.

Commencement Information

I6Art. 6 in force at 11.4.2024, see art. 1(2)

Documents to be made available by the Secretary of StateE+W

7.—(1) This paragraph applies to—

(a)approved documents;

(b)notices given under article 6(1).

(2) Subject to paragraph (4), the Secretary of State must arrange for a copy of each document to which paragraph (1) applies to be made available for inspection by the public—

(a)on a website maintained by or on behalf of the Secretary of State(8);

(b)in person, upon giving reasonable notice to the Department for Levelling Up, Housing and Communities, at 2 Marsham Street, London SW1P 4DF.

(3) This paragraph applies to information contained in a document to which paragraph (1) applies, where the Secretary of State is satisfied that that information relates to—

(a)matters of national security;

(b)measures taken or to be taken to ensure the security of any premises or property, whose efficacy may be impaired by the disclosure of that information.

(4) Where paragraph (3) applies—

(a)the Secretary of State may redact the information to which it applies from any copy of the document that is made available under paragraph (2);

(b)if the Secretary of State considers that it is appropriate, having regard to national security or other security considerations, to redact the entire contents of a document under sub-paragraph (a), the Secretary of State may make available a statement to that effect, identifying the document, instead of making available a copy of the document with the contents entirely redacted.

Commencement Information

I7Art. 7 in force at 11.4.2024, see art. 1(2)

Signed by authority of the Secretary of State for Levelling Up, Housing and Communities

Lee Rowley

Minister of State

Department for Levelling Up, Housing and Communities

20th March 2024

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Memorandum

Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources