SCHEDULE 6
FOR PROTECTION OF NETWORK RAIL
Introductory
1.(1) The following provisions of this Schedule have effect unless...
Powers requiring Network Rail’s consent
2.(1) The undertaker must not, in the exercise of the...
Approval of plans
3.(1) The undertaker must, before commencing construction of any relevant...
Election by Network Rail to construct relevant work itself
4.(1) If Network Rail reasonably considers that any relevant work...
Protective works
5.(1) When signifying approval of the plans of any relevant...
Construction of relevant work
6.(1) Any relevant work must, when commenced, be constructed—
Access
7.The undertaker must— (a) at all times afford reasonable facilities...
8.Network Rail must— (a) at all times afford reasonable facilities...
Fencing
9.Where so required by the engineer the undertaker must, to...
Maintenance of relevant work
10.The undertaker must secure that any relevant work, other than...
Alterations, etc. to railway property: repayment of additional expenses
11.If— (a) any alterations or additions, either permanent or temporary,...
Repayment of Network Rail’s costs in connection with construction
12.The undertaker must pay to Network Rail a sum equivalent...
Additional costs of Network Rail in maintaining new works
13.(1) As soon as reasonably practicable following completion of the...
Additional costs of Network Rail in maintaining existing railway property
14.(1) Subject to sub-paragraph (2), the undertaker must pay to...
General indemnity
15.(1) The undertaker must pay to Network Rail a sum...
Compensation for train operators
16.(1) The sums payable by the undertaker under paragraph 15...
17.In the assessment of any sums payable under this Schedule,...
Saving for access agreements
18.(1) Where, under this Schedule, Network Rail is required to...