PART 1PRELIMINARY

Title and commencement

1.  The title of this Order is the Network Rail (Summerway Overbridge) Order 2017 and comes into force on 15 November 2017.

Interpretation

2.—(1) In this Order—

“the 1961 Act” means the Land Compensation Act 1961(1);

“the 1965 Act” means the Compulsory Purchase Act 1965(2);

“the 1981 Act” means the Acquisition of land Act 1981(3);

“the 1995 Order” means the Town and Country Planning (General Permitted Development) Order 1995(4);

“authorised works” means the works required to demolish the Summerway Overbridge (Network Rail asset No. 133A) and any associated temporary works authorised by the 1995 Order;

“the book of reference” means the book of reference certified by the Welsh Ministers as the book of reference for the purposes of this Order;

“building” includes any structure or erection or any part of a building, structure or erection;

“electronic transmission” means a communication transmitted—

(a)

by means of an electronic communications network; or

(b)

by other means but while in electronic form;

“the land plan” means the plan certified by the Welsh Ministers as the land plan for the purposes of this Order;

“the limits of land to be acquired or used” means the limits so shown and described on the land plan;

“Network Rail” means Network Rail Infrastructure Limited (company registration number 02904587) whose registered office is 1 Eversholt Street, London NW1 2DN; and

“owner” in relation to land, has the same meaning as in section 7 (interpretation) of the 1981 Act(5).

(2) All measurements stated in any description of lands in the book of reference are approximate.

(3) References in this Order to numbered plots are references to plot numbers shown on the land plan.

PART 2OCCUPATION CROSSING

Summerway Overbridge occupation crossing

3.—(1) Regardless of anything in section 68 (accommodation works by the company) of the Railways Clauses Consolidation Act 1845(6) as incorporated in the South Wales Railway Act 1845(7) and the Great Western Railway Act 1895(8) or any other enactment or instrument, all public or private rights of way (if any) between points A1 and A2, as shown on the land plan, over the former occupation crossing known as the Summerway Overbridge (Network Rail asset No. 133A) in the City and County of Newport are extinguished.

(2) Any person who suffers loss by the extinguishment of any public or private right of way under this article is entitled to compensation to be determined, in the case of dispute, under Part 1 of the 1961 Act.

PART 3LAND PROVISIONS

Temporary possession of land

4.—(1) Network Rail may, in connection with the carrying out of the authorised works, enter upon and take temporary possession of the land specified in columns (1) and (2) of the Schedule (land of which temporary possession may be taken) for the purposes specified in relation to that land in column (3) of that Schedule relating to the authorised works.

(2) Not less than 14 days before entering upon and taking temporary possession of land under this article Network Rail must serve notice of the intended entry on the owners and occupiers of the land.

(3) Network Rail may not, without the agreement of the owners of the land, remain in possession of any land under this article after the end of the period of one year beginning with the date of completion of the authorised works.

(4) Before giving up possession of land of which temporary possession has been taken under this article, Network Rail must remove all temporary works and restore the land to the reasonable satisfaction of the owners of land, but Network Rail is not required to replace a building removed in connection with the carrying out of the authorised works.

(5) Network Rail must pay compensation to the owners and occupiers of land of which temporary possession is taken under this article for any loss or damage arising from the exercise in relation to the land of the powers conferred by this article.

(6) Any dispute as to a person’s entitlement to compensation under paragraph (5), or as to the amount of compensation, is to be determined under Part 1 of the 1961 Act.

(7) Without affecting article 10 (no double recovery), nothing in this article affects any liability to pay compensation under section 10(2)(9) (further provision as to compensation for injurious affection) of the 1965 Act or under any other enactment in respect of loss or damage arising from the execution of any works, other than loss or damage for which compensation is payable under paragraph (5).

(8) Where Network Rail takes possession of land under this article, Network Rail is not required to acquire the land or any interest in it.

Application of Part 1 of the 1965 Act

5.  Sections 1 (application of Part 1 and interpretation), 3 (acquisition by agreement in pursuance of compulsory purchase order) and 13 (refusal to give possession to acquiring authority) of the 1965 Act, in so far as not inconsistent with the provisions of this Order, apply to the temporary use of land under this Order to the same extent as they apply to a compulsory purchase to which the 1981 Act applies and as if this Order were a compulsory purchase order under that Act.

Suspension of private rights of way

6.—(1) Subject to paragraph (3), all private rights of way over land of which Network Rail takes temporary possession under this Order are suspended and unenforceable for as long as Network Rail remains in lawful possession of the land.

(2) Any person who suffers loss by the suspension of any private right of way under this article is entitled to compensation to be determined, in the case of dispute, under Part 1 of the 1961 Act.

(3) Paragraph (1) has effect subject to—

(a)any notice given by Network Rail before Network Rail takes temporary possession of the land that paragraph (1) does not apply to any right of way specified in the notice; and

(b)any agreement which makes reference to this article (whether made before or after Network Rail takes temporary possession of the land and before or after the coming into force of this Order) between Network Rail and the person in or to whom the right of way in question is vested or belongs.

(4) If any such agreement as is mentioned in paragraph (3)(b) is expressed to have effect also for the benefit of those deriving title from or under the person in or to whom the right of way in question is vested or belongs, it is effective in respect of the persons so deriving title, whether the title was derived before or after the making of the agreement.

Time limit for exercise of powers of temporary possession

7.—(1) The powers conferred by article 4 (temporary possession of land) cease after the end of the period of 5 years beginning with the day on which this order comes into force, except that nothing in this article prevents Network Rail remaining in possession of land after the end of that period, if the land was entered and possession of it was taken before the end of that period.

PART 4MISCELLANEOUS AND GENERAL

Certification of plans etc.

8.  Network Rail must, as soon as practicable after the making of this Order, submit copies of the book of reference and the land plan to the Welsh Ministers for certification that they are, respectively, true copies of the book of reference and land plan referred to in this Order; and a document so certified is admissible in any proceedings as evidence of the contents of the document of which it is a copy.

Service of notices

9.—(1) A notice or other document required or authorised to be served for the purposes of this Order may be served—

(a)by post; or

(b)with the consent of the recipient and subject to paragraphs (6) to (8), by electronic transmission.

(2) Where the person on whom a notice or other document to be served for the purposes of this Order is a body corporate, the notice or document is duly served if it is served on the secretary or clerk of that body.

(3) For the purposes of section 7 (references to service by post) of the Interpretation Act 1978(10)as it applies for the purposes of this article, the proper address of any person in relation to the service on that person of a notice or document under paragraph (1) is, if that person has given an address for service, that address, and otherwise—

(a)in the case of the secretary or clerk of a body corporate, the registered or principal office of that body; and

(b)in any other case, the last known address of that person at the time of service.

(4) Where for the purposes of this Order a notice or other document is required or authorised to be served on a person as having any interest in, or as the occupier of, land and the name or address of that person cannot be ascertained after reasonable enquiry, the notice may be served by—

(a)addressing it to that person by name or by the description of “owner”, or as the case may be “occupier”, of the land (describing it); and

(b)either leaving it in the hands of a person who is or appears to be resident or employed on the land or leaving it conspicuously affixed to some building or object on or near the land.

(5) Where a notice or other document required to be served or sent for the purposes of this Order is served or sent by electronic transmission the requirement is taken to be fulfilled where the recipient of the notice or other document to be transmitted has given consent to the use of electronic transmission either in writing or by electronic transmission.

(6) Where the recipient of a notice or other document served or sent by electronic transmission notifies the sender within 7 days of receipt that the recipient requires a paper copy of all or any part of that notice or other document the sender must provide such a copy as soon as reasonably practicable.

(7) Any consent to the use of electronic transmission given by a person may be revoked by that person in accordance with paragraph (8).

(8) Where a person is no longer willing to accept the use of electronic transmission for any of the purposes of this Order—

(a)that person must give notice in writing or by electronic transmission revoking any consent given by that person for that purpose; and

(b)such revocation is final and takes effect on a date specified by the person in the notice but that date must not be less than 7 days after the date on which the notice is given.

(9) This article does not exclude the employment of any method of service not expressly provided for by it.

No double recovery

10.  Compensation is not payable in respect of the same matter both under this Order and under any other enactment, any contract or any rule of law.

Arbitration

11.  Any difference under any provision of this Order, unless otherwise provided for, must be referred to and settled by a single arbitrator to be agreed between the parties or, failing agreement, to be appointed on the application of either party (after giving notice in writing to the other) by the President of the Institution of Civil Engineers.

Lesley Griffiths

Cabinet Secretary for Environment and Rural Affairs, one of the Welsh Ministers

24 October 2017

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources