The Norfolk Offshore Wind Farm Order 2003

 Help about what version

What Version

  • Latest available (Revised)
  • Original (As made)
 Help about opening options

Opening OptionsExpand opening options

Status:

This is the original version (as it was originally made). This item of legislation is currently only available in its original format.

  1. Introductory Text

  2. Expand +/Collapse -

    PART I PRELIMINARY

    1. 1.Citation and commencement

    2. 2.Interpretation

  3. Expand +/Collapse -

    PART II WORKS

    1. Principal powers

      1. 3.Power to construct and maintain works

      2. (4).Power to deviate

    2. Protection of navigation and air traffic and control of noise

      1. 5.Works not to be executed without approval of the Secretary of State

      2. 6.Provision against danger to navigation

      3. 7.Abatement of works abandoned or decayed

      4. 8.Survey of works

      5. 9.Permanent lights or buoys near works and colour and other markings

      6. 10.Lights on works during construction

      7. 11.Active safety management system

      8. 12.Noise and vibration

      9. 13.Execution by Secretary of State of works in default

      10. 14.Offences

  4. Expand +/Collapse -

    PART III MISCELLANEOUS AND GENERAL

    1. 15.Power to operate and use works

    2. 16.Disapplication of section 36 of the Electricity Act 1989

    3. 17.Obstruction and misuse of works

    4. 18.Temporary exclusion zones

    5. 19.For protection of Environment Agency

    6. 20.For protection of Cromer Lighthouse

    7. 21.Certification of plans etc.

    8. 22.Transfer of powers

    9. 23.Crown rights

  5. Signature

    1. Expand +/Collapse -

      SCHEDULE 1

      SCHEDULED WORKS

      1. 1.The works which the undertaker is authorised to construct and...

      2. 2.In this schedule references to the locations of a wind...

    2. Expand +/Collapse -

      SCHEDULE 2

      FOR PROTECTION OF ENVIRONMENT AGENCY

      1. 1.The following provisions shall, unless otherwise agreed in writing between...

      2. 2.In this Schedule: “accumulation” means any accumulation of silt or...

      3. 3.If, during the construction of a specified work or within...

      4. 4.Should any such accumulation or erosion or alteration of the...

      5. 5.To the extent that damage would have been caused in...

      6. 6.For the purposes of paragraphs 3 and 4:

      7. 7.In paragraphs 3, 4 and 5, “damage” means any damage...

      8. 8.For the purposes of paragraph 3 the date of completion...

      9. 9.Without prejudice to the other provisions of this article and...

      10. 10.The Agency shall— (a) give to the undertaker notice of...

      11. 11.If by reason of the construction of any specified work...

      12. 12.Nothing in paragraph 9 or 11 shall impose liability on...

      13. 13.Except as otherwise provided by this article nothing in this...

      14. 14.Any dispute or difference between the undertaker and the Agency...

    3. Expand +/Collapse -

      SCHEDULE 3

      FOR PROTECTION OF CROMER LIGHTHOUSE

      1. 1.Within 30 days of anticipated completion of the authorised works,...

      2. 2.If, within 6 months of receipt of the completion notice,...

      3. 3.For the purpose of paragraph 2 Trinity House shall provide...

      4. 4.If in the reasonable opinion of Trinity House, immediate action...

      5. 5.Trinity House may recover from the undertaker its reasonable costs...

      6. 6.Following issuance of the direction the undertaker shall use its...

      7. 7.Trinity House shall indemnify the undertaker against all claims or...

      8. 8.The undertaker shall indemnify Trinity House against all claims or...

      9. 9.The undertaker or Trinity House shall give to the other...

  6. Explanatory Note