PART 5 MISCELLANEOUS AND GENERAL
SCHEDULES
MODIFICATION OF COMPENSATION AND COMPULSORY PURCHASE ENACTMENTS FOR THE CREATION OF NEW RIGHTS
LAND IN WHICH ONLY SUBSOIL OR NEW RIGHTS IN AND ABOVE SUBSOIL AND SURFACE MAY BE ACQUIRED
PART 1 FOR THE PROTECTION OF ELECTRICITY, GAS, WATER AND SEWERAGE UNDERTAKERS
1.The provisions of this Part of this Schedule have effect...
2.In this Part of this Schedule— “alternative apparatus” means alternative...
4.(1) Regardless of the temporary stopping up, alteration or diversion...
5.Despite any provision in this Order or anything shown on...
7.(1) Where, in accordance with the provisions of this Part...
9.(1) Subject to the following provisions of this paragraph, the...
10.(1) Subject to sub-paragraphs (2) and (3), if by reason...
PART 2 FOR THE PROTECTION OF OPERATORS OF ELECTRONIC COMMUNICATIONS CODE NETWORKS
PART 3 FOR THE PROTECTION OF DRAINAGE AUTHORITIES
16.The provisions of this Part have effect for the protection...
17.In this Part of this Schedule— “construction” includes execution, placing,...
18.(1) Before commencing construction of a specified work, the undertaker...
19.Without limiting paragraph 18, the requirements which the drainage authority...
20.(1) Subject to sub-paragraph (2), any specified work, and all...
21.(1) Subject to sub-paragraph (5), the undertaker must from the...
22.Subject to paragraphs 24 and 25 and sub-paragraph 21(5)(b), if...
23.If by reason of the construction of the specified work...
24.The undertaker must make reasonable compensation for costs, charges and...
25.(1) The undertaker must make reasonable compensation for costs and...
27.Any dispute arising between the undertaker and the drainage authority...
PART 5 FOR THE PROTECTION OF THE ENVIRONMENT AGENCY
39.(1) The following provisions apply for the protection of the...
40.(1) Before commencing construction of any specified work, the undertaker...
41.Without limiting paragraph 40, the requirements which the Agency may...
42.(1) Subject to sub-paragraph (2), any specified work, and all...
43.(1) Subject to sub-paragraph (5) the undertaker must from the...
44.Subject to paragraphs 47 and 43(5)(b), if by reason of...
45.If by reason of construction of the specified work the...
47.The undertaker must make reasonable compensation for costs, charges and...
48.(1) The undertaker must make reasonable compensation for costs and...
49.Any dispute arising between the undertaker and the Agency under...
Yr Offeryn Cyfan you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.
Gwreiddiol (Fel y’i Deddfwyd neu y’i Gwnaed): Mae'r wreiddiol fersiwn y ddeddfwriaeth fel ag yr oedd pan gafodd ei deddfu neu eu gwneud. Ni wnaed unrhyw newidiadau i’r testun.
Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:
Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:
liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys