Commission Decision of 3 November 2010 laying down criteria and measures for the financing of commercial demonstration projects that aim at the environmentally safe capture and geological storage of CO2 as well as demonstration projects of innovative renewable energy technologies under the scheme for greenhouse gas emission allowance trading within the Community established by Directive 2003/87/EC of the European Parliament and of the Council (notified under document C(2010) 7499) (2010/670/EU)

 Help about what version

What Version

 Help about advanced features

Advanced Features

More Resources

 Help about UK-EU Regulation

Legislation originating from the EU

When the UK left the EU, legislation.gov.uk published EU legislation that had been published by the EU up to IP completion day (31 December 2020 11.00 p.m.). On legislation.gov.uk, these items of legislation are kept up-to-date with any amendments made by the UK since then.

Close

This item of legislation originated from the EU

Legislation.gov.uk publishes the UK version. EUR-Lex publishes the EU version. The EU Exit Web Archive holds a snapshot of EUR-Lex’s version from IP completion day (31 December 2020 11.00 p.m.).

Changes over time for: Commission Decision of 3 November 2010 laying down criteria and measures for the financing of commercial demonstration projects that aim at the environmentally safe capture and geological storage of CO2 as well as demonstration projects of innovative renewable energy technologies under the scheme for greenhouse gas emission allowance trading within the Community established by Directive 2003/87/EC of the European Parliament and of the Council (notified under document C(2010) 7499) (2010/670/EU) (without Annexes)

 Help about opening options

Version Superseded: 01/01/2024

Status:

Point in time view as at 31/01/2020.

Changes to legislation:

There are currently no known outstanding effects for the Commission Decision of 3 November 2010 laying down criteria and measures for the financing of commercial demonstration projects that aim at the environmentally safe capture and geological storage of CO2 as well as demonstration projects of innovative renewable energy technologies under the scheme for greenhouse gas emission allowance trading within the Community established by Directive 2003/87/EC of the European Parliament and of the Council (notified under document C(2010) 7499) (2010/670/EU). Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

Article 1U.K.Subject matter

This Decision lays down rules and criteria for the following:

(1)

the selection of commercial demonstration projects that aim at the environmentally safe capture and geological storage of CO2 (‘CCS demonstration projects’) and demonstration projects of innovative renewable energy technologies (‘RES demonstration projects’) referred to in Directive 2003/87/EC;

(2)

the monetisation of the allowances referred to in Directive 2003/87/EC for the support of CCS and RES demonstration projects, and the management of the related revenues;

(3)

the disbursement of revenues and the implementation of CCS and RES demonstration projects.

This Decision, including the provisions in relation to the monetisation of allowances, shall be without prejudice to other implementing acts adopted pursuant to Directive 2003/87/EC.

Article 2U.K.Principles

1.The number of allowances in the new entrants’ reserve referred to in Article 10a(8) of Directive 2003/87/EC shall be 300 million.

2.Selection of CCS and RES demonstration projects for funding under this Decision shall take place through two rounds of calls for proposals organised by the Commission and addressed to Member States, covering the equivalent of 200 million allowances for the first round of call for proposals, and the equivalent of 100 million allowances and the remaining allowances from the first round of calls for proposals for the second round of calls for proposals.

3.Subject to the fourth sentence in the fourth subparagraph of Article 10a(8) of Directive 2003/87/EC, financing under this Decision shall be 50 % of the relevant costs. Where the total request for public funding is less than 50 % of the relevant costs, the total request for public funding shall be financed under this Decision.

However, where financing under this Decision is combined with financing from the European Energy Programme for Recovery (EEPR), the financing under this Decision shall be reduced by the amount of financing received from the EEPR.

[F14. Any non-disbursed revenues from the first round of calls for proposals shall be available to support first-of-a-kind innovative, replicable and ready to demonstrate at scale CCS and RES demonstration projects, using relevant financial instruments managed by the European Investment Bank Group, with a priority given to the InnovFin EDP Facility and the Debt Instrument in the sector of transport under Connecting Europe Facility.

The preceding paragraph, Articles 6, 8, 11(1) to (5), the first and second subparagraphs of Article 11(6) and Article 13 shall not apply to the use of these revenues.

The Commission shall report sufficiently in advance to the Climate Change Committee on the development of the relevant Delegation Agreements between the Commission and the European Investment Bank, in particular as regards the related eligibility criteria, implementation of the relevant financial instruments, especially the build-up of the project pipeline, assessment of the project applications and finally on the use of the redeployed revenues, and take appropriate account of the views of Member States.]

Article 3U.K.Relevant costs

1.For the purposes of Article 2(3), the rules in paragraphs 2 to 5 of this Article shall apply.

2.The relevant costs of CCS demonstration projects shall be those investment costs which are borne by the project due to the application of CCS net of the net present value of the best estimate of operating benefits and costs arising due to the application of CCS during the first 10 years of operation.

3.Relevant costs of RES demonstration projects shall be those extra investment costs which are borne by the project as a result of the application of an innovative renewable energy technology net of the net present value of the best estimate of operating costs and benefits arising during the first 5 years compared to a conventional production with the same capacity in terms of effective production of energy.

4.The investment costs referred to in paragraphs 2 and 3 shall cover the cost of investment in land, plant and equipment.

Investment costs may also relate to investment in technology transfer and operating licenses of know-how (hereinafter ‘intangible assets’) where the following conditions are fulfilled:

(a)the intangible asset can be considered as a depreciable asset;

(b)the intangible asset is purchased on market terms at the lowest price possible;

(c)the intangible asset remains in the establishment of the recipient for at least 5 years.

If the intangible asset is sold before the expiry of the 5-year period referred to in point (c) of the second subparagraph, the yield from the sale shall be deducted from the relevant costs.

5.The net operating costs and benefits referred to in paragraphs 2 and 3 shall be based on the best estimate of operating expenses borne by the project regarding production costs and take into account any additional benefits resulting from support schemes even if they do not constitute State aid within the meaning of Article 107(1) of the Treaty, avoided costs and existing tax incentive measures.

Article 4U.K.Role of the EIB

The European Investment Bank (EIB) shall perform its tasks under this Decision on request of, on behalf of and for the account of the Commission. The Commission shall be responsible with regard to third parties.

The EIB shall be reimbursed for the performance of those tasks from income generated from its management of the revenues.

The Commission and the EIB shall enter into an agreement laying down the specific terms and conditions under which the EIB shall perform its tasks.

Article 5U.K.Selection procedure

1.The calls for proposals shall be published in the Official Journal of the European Union.

2.Member States shall collect funding applications for projects that are intended to take place on their territory.

However, where a project is intended to take place on the territory of several Member States (hereinafter a ‘transboundary project’), the Member State receiving the funding application shall inform the other Member States concerned thereof and shall cooperate with the other Member States with a view to reaching a common decision on the submission of the project by the Member State receiving the funding application.

3.Member States shall assess whether a project meets the eligibility criteria referred to in Article 6. Where this is the case and where the Member State supports the project, that Member State shall submit the proposal to the EIB and inform the Commission thereof.

When submitting proposals for funding, the Member State shall provide the following information for each project:

(a)the relevant costs, in euro, referred to in Article 2(3);

(b)the total request for public funding in euro, which is the relevant costs minus any contribution to those costs from the operator;

(c)the best estimate of the net present value of additional benefits resulting from support schemes as calculated according to Article 3(5);

(d)for CCS demonstration projects, the total projected amount of CO2 stored in the first 10 years of operation, or, for RES demonstration projects, the total projected amount of energy produced in the first 5 years of operation.

Member States shall also notify the Commission of any financing for the project involving State aid pursuant to Article 108(3) of the Treaty so as to allow coordination of the selection procedure with the State aid assessment.

4.On the basis of the proposals submitted pursuant to paragraph 3 of this Article, the EIB shall perform an assessment of the financial and technical viability (financial and technical due diligence) of the project in accordance with Article 7.

Where that assessment has been concluded positively, the EIB shall, in accordance with Article 8, make recommendations for award decisions to the Commission.

5.On the basis of the recommendations referred to in paragraph 4, after reconsulting the Member States concerned to confirm, where appropriate, the value and structure of the total public funding contribution, and following an opinion from the Climate Change Committee pursuant to Article 3 of Council Decision 1999/468/EC(1), the Commission shall adopt award decisions addressed to the relevant Member States, indicating the awarded funding for the projects concerned in euro.

Article 6U.K.Eligibility criteria

1.A project shall be eligible for funding where the following criteria are fulfilled:

(a)the project must fall into one of the categories set out in Part A of Annex I;

(b)the project must comply with the requirements set out in Part B of Annex I;

(c)the projects listed in Part A.II of Annex I must be innovative in nature. Existing, proven technologies are ineligible.

2.Where a Member State is not in a position to submit proposals for projects falling under any of the subcategories specified in Part A.II of Annex I which meet the relevant thresholds to the EIB pursuant to Article 5(3), proposals for projects below the relevant thresholds for any of the subcategories concerned may be submitted by this Member State and shall be considered eligible for the award of financing by way of derogation from paragraph 1.

Article 7U.K.Financial and technical due diligence

The EIB shall perform the due diligence assessment of any proposed project in accordance with specifications laid down in the calls for proposals referred to in Article 5(1) and shall cover at least the following aspects:

(1)

technical scope;

(2)

costs;

(3)

financing;

(4)

implementation;

(5)

operation;

(6)

environmental impact;

(7)

procurement procedures.

Article 8U.K.Project selection

1.Eight projects falling under Part A.I of Annex I and one project in each project subcategory specified in Part A.II of Annex I shall be funded.

However, where resources allow, further projects may be funded while maintaining the balance between CCS and RES demonstration projects.

Where no more than two proposals are submitted in a given subcategory, the Commission shall assess the possible impact of the limited number of proposals on the competition for selection under this Decision, and may, where appropriate, decide to postpone award decisions in the relevant subcategory to the second round of calls for proposals.

2.Projects shall be ranked in order of increasing cost-per-unit performance. CCS demonstration projects shall be ranked as a single group. RES demonstration projects shall be ranked within each of the subcategories specified in Part A.II of Annex I.

For the purposes of the first subparagraph, cost-per-unit performance shall be calculated as the sum of the amounts specified in Article 5(3)(b) and (c), divided by the total projected amount of CO2 stored in the first 10 years of operation for CCS demonstration projects, or, the total projected amount of energy produced in the first 5 years of operation for the RES demonstration projects.

Where the relevant Member States confirm, pursuant to Article 5(5), that there is a sufficient public funding for CCS demonstration projects, the highest ranked projects shall be selected in order of their ranking, provided all the following criteria are met:

(a)at least one project and at most three projects are selected in each project category;

(b)at least three projects with hydrocarbon reservoir storage are selected;

(c)at least three projects with saline aquifer storage are selected.

Where those criteria are not met, the project under consideration for selection shall not be selected, and the next highest ranked project shall be considered for selection. The procedure shall be repeated until eight projects are selected.

Where the relevant Member States confirm, pursuant to Article 5(5), that there is a sufficient public funding for RES demonstration projects, the highest ranked project in each subcategory shall be selected. Where, in either of the rounds for calls for proposals there are no eligible and financially and technically viable projects in one or more project subcategories, a corresponding number of additional projects shall be funded in other subcategories of the same project category. Details shall be specified in the call for proposals pursuant to Article 5(1).

The selected CCS demonstration projects shall collectively constitute ‘the CCS group’ and the selected RES demonstration projects shall collectively constitute ‘the RES group’.

3.By way of derogation from paragraph 1, where the total request for funding under this Decision is higher than the available funds, the number of selected projects shall be reduced so that the request for funding is reduced in the same proportion in each of the groups referred to in the third and fifth subparagraphs of paragraph 2.

For each of the groups, the project representing the highest cost-per-unit performance shall be deselected first, the project representing the highest cost-per-unit performance in another category shall be deselected next. The procedure shall be repeated until the requested funding is covered by the available funds.

4.Subject to the availability of proposals submitted to the EIB pursuant to Article 5(3) and recommended by the EIB for award decisions to the Commission pursuant to Article 5(4), at least one and no more than three projects shall be funded within one Member State.

However, the first subparagraph shall not apply to transboundary projects.

Article 9U.K.Award decisions

Award decisions shall be conditional upon all relevant national permits in accordance with relevant requirements under Union law being issued, approval by the Commission of any State aid in respect of a project being granted, and final investment decisions being reached by the sponsors, within [F248 months] of adoption of the award decisions.

With regard to CCS demonstration projects, with saline aquifer storage, award decisions shall be conditional upon all relevant national permits in accordance with relevant requirements under Union law being issued, approval by the Commission of any State aid in respect of a project being granted, and final investment decisions being reached by the sponsors, within [F260 months] of adoption of the award decisions.

Award decisions shall cease to have legal effect where the conditions referred to in the first or second paragraph are not met.

Article 10U.K.Monetisation of allowances and management of revenues

1.For the purposes of monetisation of allowances and management of revenues, the Commission shall act on behalf of Member States.

2.The Member States and the Commission shall ensure that the 300 million allowances referred to in Article 2(1) shall be transferred to the EIB for monetisation and management of the revenues.

3.The EIB shall sell the allowances for the first round of calls for proposals before the award decisions are adopted by the Commission for each round of calls for proposals referred to in Article 5(1).

The EIB shall manage the revenues and shall pass them to Member States as required for disbursement pursuant to Article 11.

Article 11U.K.Disbursement of revenues and use of non-disbursed revenues

1.Member States shall disburse the revenues to project sponsors on the basis of legally binding instruments which shall set out at least the following:

(a)the project and the awarded funding in euro;

(b)the date of entry into operation;

(c)the requirements for knowledge-sharing pursuant to Article 12;

(d)requirements regarding disbursement of the revenues pursuant to paragraphs 2 to 6 of this Article;

(e)requirements for reporting pursuant to Article 13;

(f)the information on conditions of applicability of the decision referred to in Article 9.

For the first round of calls for proposals referred to in Article 5(1), the date of entry into operation referred to in point (b) of the first subparagraph of this paragraph shall be [F231 December 2017] at the latest except where the respective award decision is adopted after 31 December 2011, in which case the date of entry into operation shall be no later than [F26 years] from the date of the award decision.

[F3Where the project has not entered into operation by the date of entry into operation set for that project that date is automatically extended by 1 year.

Award decisions shall cease to have legal effect where the project has not entered into operation by the date of entry into operation applicable pursuant to the third subparagraph. In this case, any funding disbursed or received for the purpose of disbursement shall be returned.]

2.Disbursement shall take place annually. The disbursed amount shall be, for CCS demonstration projects, the amount of CO2 stored in the relevant year as monitored, reported and verified pursuant to Articles 14 and 15 of Directive 2003/87/EC multiplied by the funding rate, and for RES demonstration projects, the amount of energy produced multiplied by the funding rate.

The funding rate shall be calculated by dividing the awarded funding by 75 % of the projected total amount of stored CO2 in the first 10 years of operation in case of CCS demonstration projects, or 75 % of the projected total amount of energy produced in the first 5 years of operation in the case of RES demonstration projects.

3.Disbursement for a given year shall take place only where the knowledge-sharing requirements are met for that year.

4.Disbursement shall be limited to a period of 10 years from the date referred to in paragraph (1)(b) in the case of CCS demonstration projects, and to a period of 5 years from that date in the case of RES demonstration projects. The total funds disbursed shall not exceed the awarded funding referred to in paragraph 1(a).

5.Where the Member State concerned guarantees that any funding which exceeds the funding determined pursuant to paragraphs 2, 3, and 4 will be returned to the EIB, part or all of the funding for a project may be disbursed prior to the entry into operation of that project in accordance with specifications set out in the award decision.

6.Without prejudice to the second paragraph of Article 4, revenues which are not disbursed to projects and income generated from the management of revenues shall be used to co-finance further demonstration projects under this Decision until 31 December 2015.

Member States shall return revenues which are not disbursed to the EIB.

After 31 December 2015, any remaining funds shall accrue to the Member States. At the end of disbursement, these funds shall be passed on to the Member States in accordance with the principles laid down in Article 10a(7) of Directive 2003/87/EC.

Article 12U.K.Knowledge-sharing

Member States shall ensure that all project operators, consortium members, suppliers and subcontractors who receive substantial benefit regarding the development of their product or service from the public finance provided, share the information on the elements set out in Annex II with other project operators, public authorities, research institutes, non-governmental organisations and the public in accordance with the further specifications set out in the calls for proposals referred to in Article 5(1).

Information shall be shared on an annual basis and shall comprise all information generated and processed in a given year.

Article 13U.K.Reporting by Member States

During the periods referred to in Article 11(4), Member States shall, by 31 December of each year, submit reports on the implementation of the projects to the Commission.

Those reports shall include at least the following information for each project:

(1)

the amount of CO2 stored or clean energy produced;

(2)

the funds disbursed;

(3)

any significant problems with project implementation.

Article 14U.K.Reporting by the Commission

After completion of the first round of calls for proposals, the Commission shall report to the Climate Change Committee on the implementation of that round of calls for proposals, indicating whether any amendment to this Decision is necessary with the view to ensuring geographical and technical balance in the second round of calls for proposals.

[F1The Commission shall report regularly to the Climate Change Committee on the use of the revenues referred to in Article 2(4), including upfront information on the planned support for projects and the part of support to be made available in the form of grants, geographical distribution of projects, scale of projects and technological coverage, ex-post information on the progress of realization of projects, avoidance of CO 2 emissions, financial leverage, awareness-raising and lessons learned, as appropriate.]

Article 15U.K.Addressees

This Decision is addressed to the Member States.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As adopted by EU): The original version of the legislation as it stood when it was first adopted in the EU. No changes have been applied to the text.

Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as adopted version that was used for the EU Official Journal
  • lists of changes made by and/or affecting this legislation item
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different versions taken from EUR-Lex before exit day and during the implementation period as well as any subsequent versions created after the implementation period as a result of changes made by UK legislation.

The dates for the EU versions are taken from the document dates on EUR-Lex and may not always coincide with when the changes came into force for the document.

For any versions created after the implementation period as a result of changes made by UK legislation the date will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. For further information see our guide to revised legislation on Understanding Legislation.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as adopted version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources